1. Trang chủ
  2. » Kinh Tế - Quản Lý

Lecture Project management in practice (6th Edition) – Chapter 6: Allocating resources to the project

62 122 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 62
Dung lượng 2,55 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

The following will be discussed in this chapter: Expediting a project, resource loading, resource leveling, allocating scarce resources to projects, allocating scarce resources to several projects, goldratt’s critical chain.

Trang 1

Sixth Edition

Chapter 6 Allocating Resources to 

the Project

Trang 7

 ­   crash time

cost  

normal  ­

cost  crash 

slope

Trang 8

Project

Table 6­1

Trang 9

a Project, AOA Network Part 1

Figure 6­1 (Partial)

Trang 10

a Project, AOA Network Part 2

Figure 6­1 (Partial)

Trang 11

Figure 6­2

Trang 12

AOA Network with Node Labels

Figure 6­3

Trang 13

Spreadsheet Model

Figure 6­4

Trang 14

Spreadsheet Model

Figure 6­4

Trang 15

Completed Solver Dialog Box

Figure 6­5

Trang 16

Solution to Crash Project 5 Days

Figure 6­6

Trang 21

• Will see using short documentary DVD 

example

Trang 22

Project Plan and Gantt Chart for  Production of a Short Documentary Film

Figure 6­7

Trang 23

Adjusted for Client Availability

Figure 6­8

Trang 24

Production

Table 6­3

Trang 25

• Most project management software assumes  that any resource assigned to an activity 

Trang 27

Scriptwriter Showing All Activities

Figure 6­9

Trang 28

Report for Scriptwriter

Figure 6­10

Trang 29

Resource Leveled Report for  Scriptwriter Showing All Activities

Figure 6­11

Trang 30

for Scriptwriter

Figure 6­12

Trang 31

for Scriptwriter Leveled 

Table 6­4

Trang 32

Final Gantt Chart Schedule,  Scriptwriters and Producer Leveled

Figure 6­13

Trang 37

• Pseudoactivities are those which have duration but require no resources

Trang 38

Pseudoactivities

Figure 6­15

Trang 43

Figure 6­16

Trang 45

• The budget is frequently unrealistic and therefore 

often exceeded

• It seems like my project is always in competition 

for resources with other projects

Trang 47

Figure 6­17

Trang 50

Based on Simulation

Table 6­5

Trang 54

Figure 6­20

Trang 55

A and B

Figure 6­21

Trang 61

Figure 6­23

Ngày đăng: 08/02/2020, 20:46

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

TÀI LIỆU LIÊN QUAN

w