Lecture Project management in practice (Fifth Edition) – Chapter 5: Scheduling the project. The following will be discussed in this chapter: Pert and CPM networks, project uncertainty and risk management, simulation, the gantt chart, extensions to PERT/CPM.
Trang 1Sixth Edition
Chapter 5 Scheduling the Project
Trang 7Sample AON Network
Trang 8Sample AOA Network
Trang 11Critical Path and Critical Time
Table 52
Trang 12Table 52 and Figure 58
Trang 13Time for Sample Project
Figure 510
Trang 18in Table 52
Table 53
Trang 19PERT/CPM Network from Table 53
Figure 511
Trang 21Variance
2 2
E
6
)
( Var
6
) 4
( T
a b
b m
a
Trang 22) ( b a
Trang 23) ( b a
Trang 24• Expected time (TE) for each activity is calculated
• Variance ( 2) for each activity is calculatedσ
• TE for each activity is used to find the critical path and critical time for the network
• The variance ( 2) of a path is the sum of the σ
activity variances for that path
Trang 25Example
Table 54
Trang 26Is it Really the Critical path
• Given uncertainty, cannot be sure that any specific path is the critical path
Trang 301 00 4 00 0 25 0 78 1
47 50
2
D Z
Trang 31Completion Times for Example
Figure 516
Trang 32Selecting Risk and Finding D
Trang 33• Simulation is a different approach to
managing risk
• Builds on the probabilistic functions already discussed
• Helps to understand the consequences of
uncertainty
• Provides insight into the range and
distribution of project completion times
Trang 34Completion Time
Figure 517
Trang 38Figure 519
Trang 39Path, Path Connections, Other Data
Figure 520
Trang 42Conventions
Figure 521