1| PROJECT INTRODUCTIONLOCATION MAP Hoi An South Development Phase 1, Tay Son Tay Hamlet, Duy Hai Commune, Duy Xuyen District, Quang Nam Province, Vietnam... 3| PACKAGE 2 – 5 Star New

Trang 1

1| PROJECT INTRODUCTION

LOCATION MAP

Hoi An South Development Phase 1,

Tay Son Tay Hamlet, Duy Hai

Commune, Duy Xuyen District,

Quang Nam Province, Vietnam

Trang 2

1| PROJECT INTRODUCTION

MAJOR PACKAGES IN PHASE 1 TENDER

-Package 1 - Welcome Boulevard

-Package 2 - 5 Star New World Hotel, All-Suite Hotel and Casino Complex

- Package 3 - Condo Hotel

- Lagoon

Trang 3

2| PACKAGE 1 – Welcome Boulevard & Site Infrastructure

Trang 4

2| PACKAGE 1 – Welcome Boulevard & Site Infrastructure

Trang 5

3| PACKAGE 2 – 5 Star New World Hotel, All-Suite Hotel and Casino Complex

ALL SUITES HOTEL (ASH)

17 STOREYS

NEW WORLD HOTEL (NWH)

13 STOREYS

CASINO PODIUM

Trang 6

3| PACKAGE 2 – 5 Star New World Hotel, All-Suite Hotel and Casino Complex

Trang 7

3| PACKAGE 2 – 5 Star New World Hotel, All-Suite Hotel and Casino Complex

ALL SUITES HOTEL (ASH)

NEW WORLD HOTEL (NWH)

SOL +22.96

Trang 8

8 COFICO Copyright © 2016

LEVEL 1 FLOOR PLAN GROUND FLOOR PLAN

TYPICAL FLOOR PLAN

VIEW 3D 2

3| PACKAGE 2 – 5 Star New World Hotel, All-Suite Hotel and Casino Complex

Trang 9

4| PACKAGE 3 – Condo Hotel

TOWER 1 – 13 STOREYS

TOWER 2 – 15 STOREYS

Trang 10

4| PACKAGE 3 – Condo Hotel

1300 m2

LEVEL 1 PLAN

Trang 11

5| LAGOON

- The purpose is to pump sand from existing Lagoon area to land filling area;

- The Lagoon area in the drawing is indicative only The depth of Lagoon is NOT YET fixed;

- Excavation of Lagoon is under separate contract

Trang 12

1/ Soil Investigation Works

6| WORKS UNDER PREVIOUS / SEPARATE CONTRACT

Trang 13

7| TIME FOR COMPLETION OF THE WORKS

8 MONTHS  CRITICAL !!!

(INCLUDING TET HOLIDAYS)

TOTAL: 19.5 MONTHS

Trang 14

MASTER SITE PLAN

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 15

TEMPORARY SITE OFFICE & EXISTING ROAD PATH

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 16

EXISTING ROAD PATH

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 17

EXISTING ROAD PATH

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 18

PACKAGE 2 - 5 Star New World Hotel, All-Suite Hotel and Casino Complex

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 19

PACKAGE 2 - 5 Star New World Hotel, All-Suite Hotel and Casino Complex

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 20

PACKAGE 2 - 5 Star New World Hotel, All-Suite Hotel and Casino Complex

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 21

PACKAGE 2 - 5 Star New World Hotel, All-Suite Hotel and Casino Complex

8| SITE VISIT PHOTOS - 10 FEB 2017

SITE OFFICE

Trang 22

PACKAGE 3 - Condo Hotel

8| SITE VISIT PHOTOS - 10 FEB 2017

SITE OFFICE

Trang 23

PACKAGE 3 - Condo Hotel

8| SITE VISIT PHOTOS - 10 FEB 2017

SITE OFFICE

Trang 24

PACKAGE 3 - Condo Hotel

8| SITE VISIT PHOTOS - 10 FEB 2017

SITE OFFICE

Trang 25

8| SITE VISIT PHOTOS - 10 FEB 2017

SITE OFFICE

Trang 26

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 27

WELCOME BOULEVARD AT PACKAGE 8

8| SITE VISIT PHOTOS - 10 FEB 2017

Trang 28

PACKAGE 8 – SEWARAGE TREATMENT PLANT

8| SITE VISIT PHOTOS - 10 FEB 2017