2 Installation of wall panels- Install form tie SETTING PROCESS AT SITE... 6 Slab- Install a standard slab panel on the corner of the slab level then install the remaining slab panels a
Trang 1GUIDING SETTING KUMKANG ALUMINUM
FORMWORK SYSTEM
Trang 4• To be used for to secure and tighten the panels together
Wedge
Pin - Φ16
1 Pin & Wedge
Trang 5Pin & Wedge
1 Pin & Wedge
Trang 6• Including of standard and non-standard size panels
• There are internal and external wall panels
• Standard size:
Width: 300, 400, 450, 600 Height: 2300, 2450
2 Wall panels
Trang 7Wall pa nel
2 Wall panels
Trang 8In-corne r wall p
anel (usually steel)
2 Wall panels
Trang 9Slab corner: for slab – wall connection
Slab In-corner: for slab –wall connection
Slab Out-corner: for slab –wall connection
3 Slab corner - SC
Trang 103 Slab corner - SC
Trang 11Slab in-corner
Slab out-corner
Slab corner
3 Slab corner - SC
Trang 12• Connect between supports and beam
• The supports and prop head are connected together for supporting beam and slab.
a Prop head (PH)
4 Beam - Prop head
Trang 13• Middle beam (MB): to be fixed in the middle of 2 prop heads
End beam (EB): to be fixed to the wall section panels and prop head
b Beam (MB-EB)
4 Beam - Prop head
Trang 14• To connect beam and prop-head.
c Joint bar
4 Beam - Prop head
Trang 154 Beam - Prop head
Trang 16Beam & prop head
4 Beam - Prop head
Trang 17End beam (EB)
Middle beam
(MB)
Prop head (PH)
4 Beam - Prop head
Trang 18• There are standard and non-standard size slab panel enable the system
connected as a whole.
• Standard size:
Width: 300, 400, 450, 600 Length: 900, 1050, 1200
5 Slab panel
Trang 195 Slab panel
Trang 22Setting plan drawing to be provied as guidance for assembling
Ensure the person in charge of formwork at jobsite will have
Kumkang formwork plan while setting the formwork.
TIP: The setting drawings were produced
as per the shell drawings confirmed by the client Thus, if any changes arise after the shell drawing confirmation, these changes are not applied on the setting drawings In such case, please discuss with Kumkang Kind Co., Ltd to whether supply the additional materials or the changes will be done by jobsite.
KUMKANG SETTING DRAWING
Trang 23WALL PLAN : WALL PANELS
KUMKANG SETTING DRAWING
Trang 24WALL PLAN : BEAM & SOFFIT PANELS
KUMKANG SETTING DRAWING
Trang 25SLAB PLAN : SLAB PANELS
KUMKANG SETTING DRAWING
Trang 26STAIRCASE PLAN
KUMKANG SETTING DRAWING
Trang 27KUMKANG SETTING DRAWING
Trang 29Tasks to be done before setting
• Verification of the first slab’s level
• Completion of rebar and M&E
• Study Kumkang system
PREPARATION WORKING
Trang 30Datum line marking Cheaping concrete (if concrete is higher)
PREPARATION WORKING
1 Datum line level making
Trang 31Ladder for staircase Formoil and roller
PREPARATION WORKING
2 Working tool
Trang 32PREPARATION WORKING
2 Working tool
Sinu
Trang 33PREPARATION WORKING
3 Training at site
Trang 35Verify whether the type, size and quantity of
Verify whether the seal is as per
the container details
Prepare forklift 7Ton for unloading container
Handover accessories
HANDOVER WORKING
Trang 36Depend on site schedule, KK supervisor decide suitabled handover plan
Any package which open by site, should handover all.
HANDOVER WORKING
Trang 37The placement of materials at
the jobsite should be as
follow:
• Accessories
• Corners (I/C, O/C, hunch)
• Standard wall panels
• Non-standard wall panels
• Standard slab panels
• Non-standard slab panels
TIP: Prepare enough
space to place the pallets and display the panels according to type, size and zone (unit) This method will allow jobsite workers to easily find the panels and ensure a faster setting of the Kumkang
TIP: Do not open all pallets
when starting the setting of the
Kumkang aluminum formwork
Open the pallets as per the setting
order This will avoid confusion
and delay in looking for the right
HANDOVER WORKING
Trang 38Block name
On each panel,
Zone area
No drawing of manufacture drawing
Panel type
Panel size
HANDOVER WORKING
Trang 401) Installation of I/C panels
- When the setting of the Kumkang Aluminum Formwork starts,
the I/C panels shall be the first panels to be installed.
- Based on the formwork plan, identify the I/C panels to be
installed and place them at its location.
- Install wall panels only when the I/C panels have been installed
as per the formwork layout.
SETTING PROCESS AT SITE
Trang 412) Installation of wall panels
- Once the I/C panels have been installed, start installing the wall
panels.
- When installing the wall panels, start the installation on one side of
the wall and then install the opposite side.
1 st : Arrrange 2 nd : Setting
SETTING PROCESS AT SITE
Trang 422) Installation of wall panels
- Install form tie
SETTING PROCESS AT SITE
Trang 43TIP: Train jobsite workers
to respect the installation order If not followed properly, it will only damage the panels and delay the construction period.
3) Installation of Beam bottom – beam side
panels
- 1 st : Installing beam bottom panel
- 2 nd : Installing beam side panel
1 st : Beam bottom panel 2 nd : Beam side panel
SETTING PROCESS AT SITE
Trang 444) Installation of Slab Corner (SC)
- 1 st Assemble the SC at the corner (SIC, SOC) first
- 2 nd install the remaining SC.
SETTING PROCESS AT SITE
Trang 455) Slab frame
- In order to assemble the beam, use the middle beam, prop head and end beam with the joint bars/long pin.
SETTING PROCESS AT SITE
Trang 465) Slab frame
- Assemble the beams on the floor before installing them on the slab level.
- When installing the beams, assign at least 2 workers:
SETTING PROCESS AT SITE
Trang 476) Slab
- Install a standard slab panel on the corner of the slab level
then install the remaining slab panels as per the formwork
layout.
SETTING PROCESS AT SITE
Trang 487) Staircases
- When unloading the pallets, staircases pallets should be
located separately from the rest of the materials.
- The setting of staircases is very complex; thus, assign
workers who are skilled with the aluminum formwork.
TIP: The staircase panel has notching on every 150mm for setting easy
Depending on jobsite situation, the flat-tie can
be installed accordingly.
SETTING PROCESS AT SITE
Trang 497) Staircases
7.1 Assembly of kicker to support the staircase wall panel.
SETTING PROCESS AT SITE
Trang 507) Staircases
7.2 Install I/C panel
7.3 Install stair wall panel
SETTING PROCESS AT SITE
Trang 517) Staircases
7.4 Install SC for stair
SETTING PROCESS AT SITE
Trang 527) Staircases
7.5 Install stair slab panel
TIP:
- While assembling the slab panels, install the
prop head simultaneously.
SETTING PROCESS AT SITE
Trang 537) Staircases
7.6 Install stair wall of next level
SETTING PROCESS AT SITE
Trang 547) Staircases
7.7 Install “Gun” panel
SETTING PROCESS AT SITE
Trang 557) Staircases
7.8 Install side panel and pardi wall panels
Setting side panel Setting pardi panel
SETTING PROCESS AT SITE
Trang 577) Staircases
7.11 Install cover panel
SETTING PROCESS AT SITE
Trang 587) Staircases
7.12 Install bracing for staircase
SETTING PROCESS AT SITE
Trang 598) Pin installation
8.1 Pin of wall panel
SETTING PROCESS AT SITE
Trang 608) Pin installation
8.1 Pin of wall panel
SETTING PROCESS AT SITE
Pin at form tie
positions/ at panel
profile
Panel profile
Panel profile
Panel profile
Trang 618) Pin installation
8.1 Pin of wall panel
SETTING PROCESS AT SITE
Bolting
Wall Top Panel with Wall Panel
Wall Top panel
Wall panel
Pin
Wall Top Panel with Wall Panel
Trang 628) Pin installation
8.1 Pin of wall panel
SETTING PROCESS AT SITE
SC
Wall panel
Pin
Wall Panel to SC
Trang 638) Pin installation
8.2 Pin of slab panel
SETTING PROCESS AT SITE
7 6
11 10
9 5 4
3
2 1
8
PIN POSITION
3 4
5 8
9 10
6 7
Trang 648) Pin installation
8.2 Pin of slab panel
SETTING PROCESS AT SITE
8
PIN POSITION
3 4
5 8
9 10
6 7
3 4 5
6 7
Trang 65Kumkang Bldg, 1445 - 2, Seocho-Dong
Seocho-Ku, Seoul, Korea Phone : +82 2 3415 4188 Fax : +82 2 3415 4165
http://www.kumkangkind.com
8) Pin installation
8.2 Pin of slab panel
SETTING PROCESS AT SITE
8
5 8
9
6 7
Prop head
Trang 668) Pin installation
8.3 Long Pin
SETTING PROCESS AT SITE
Long Pin
Trang 679) Slab transfer box (if any)
SETTING PROCESS AT SITE
Trang 6810) Panel numbering
Once the Kumkang aluminum formwork setting has been completed,
mark the panels using code and/or color by unit/zone/room (as per jobsite’s
preference)
Labeling (numbering) is very important, it will make sure:
SETTING PROCESS AT SITE
TIP:
- Each team each colour
Trang 6910) Notes when pour concrete
a) Ensure that the concrete
pouring speed be below 2m/hr.
b) Pour the concrete uniformly
over the slab in order to avoid
giving too much pressure on 1
area.
c) Use the vibrator in order to
avoid air bulb to form on the
concrete surface after concrete
casting.
d) Have workers verify the wedge
pins whether they become
loose due to the effect of the
vibrator.
SETTING PROCESS AT SITE
Trang 70TIMBER BY SITE Down area
10) Notes when pour concrete
e) Should pour concrete until slab line in down area
SETTING PROCESS AT SITE
Trang 71TYPICAL 6 DAYS CYCLE
Trang 73Dismantlement of the Kumkang
aluminum formwork should be done:
Lateral part of structure,
Bottom part of slab, beam and
• Based on the Korean Temporary Equipment Association
Guideline (www.kaseol.or.kr)
DISMANTLE PROCESS
Trang 74Once the concrete pressure reaches 5MPa or 14MPa,
depending on the area, the dismantlement team must be prepared with below
tools:
1 Dismantle tool
2 Accessory box (for keep pin, wedge pin, …)
The dismantlement sequence will follow below order:
1 Wall
a) Removal of waler b) Removal of wedge pins c) Dismantlement of wall panels d) Move the dismantled panels
to next level using the slab transfer box
2 Beam
a) Dismantlement of beam bottom panel b) Dismantlement of beam SC
DISMANTLE PROCESS
Trang 753 Slab
a) Removal of joint bar
b) Dismantlement of middle beam and end beam
c) Dismantlement of slab panels
d) Move the dismantled panels
to next level using the slab transfer box
- Dismantling process is an very important process Thus, ensure that the
dismantling team are organized and know the dismantling method.
- While dismantling the slab, ensure that the steel prop and prop head will not be dismantled These materials will be dismantled only after the next level casting Moreover, when dismantling the slab panel, do not make the panels to free-fall on the floor nor force the panels to be dismantled; it will damage the panels.
- Once a panel is dismantled, do not leave it on the floor; rather lean it on the wall and move it to the next level through the slab transfer box only when the whole portion of the dismantling area has been dismantled.
- Finally, when moving the panels to the next floor, ensure that the panels
will be moved as per the marking written on the panel.
DISMANTLE PROCESS
Trang 76Before re-installing the panels, the panels must be cleaned:
1 Using a hammer, gently remove the remaining big concrete blocks.
2 After removing big concrete blocks, apply formoil on the panels and using a paddle, gently remove the smaller concrete blocks.
TIP: When using the hammer or the
paddle, gently remove the concrete
blocks since it might not only damage
the panels but also remove the initial
coating done at our factory.
DISMANTLE PROCESS
Trang 77Once the panels have been lifted to the
next level, verify the following:
Whether the wall is neat If there are
air bulbs, the concrete vibrator was
not used uniformly
1 Whether the wall is horizontally and
vertically straight If the wall is
bulging, the flat-ties, wedge and pins
were not installed correctly.
2 Whether the color of the wall is
“grey” If the color of the wall is
“brownish”, the form oil was mixed
with grease.
3 Whether the prop heads and steel
props were not dismantled
4 Ensure that any problems will be
rectified on the next level in order to
No tie
No tie
DISMANTLE PROCESS
Trang 78competence, reliable partner many years
of practical job site
experience
PARTNERSHIP-SUCCESS