CONSTRUCTION METHOD STATEMENT 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR FOUNDATION OF HOTEL... CONSTRUCTION METHOD STATEMENT 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 1HF
Trang 1COFICO Copyright © 2018
Trang 2HÌNH CONSTUCTION MODEL
COFICO Copyright © 2018
MIKAZUKI PROJECT
CONTENT
Trang 4BUILDING A BETTER FUTURE
Trang 6BUILDING A BETTER FUTURE
6 MIKAZUKI PROJECT
COFICO Copyright © 2018
2.
2.
CONSTRUCTION SITE PLAN
2 TRAFFIC MANAGEMENT PLAN
TEMPORARY ROAD
TEMPORARY ROAD
Trang 7COFICO Copyright © 2018
3 1 TOWER CRANE LAYOUT PLAN
TOWER CRANE (T/C) SPECIFICATION
T/C NAME TYPE CAPACITY
T/C #1 PORTAIN MC 175B, R=60m Q = 2.7~8 TON
T/C #2 PORTAIN MC 175B, R=60m Q = 2.7~8 TON
Trang 8BUILDING A BETTER FUTURE
8 MIKAZUKI PROJECT
COFICO Copyright © 2018
3.
3.
HEAVY EQUIPMENT PLAN
2 PLACING BOOM LAYOUT PLAN
PLACING BOOM SPECIFICATION`
PLACING BOOM NAME TYPE
PLACING BOOM #1 R=60m
PLACING BOOM #2 R=60m
Trang 9COFICO Copyright © 2018
3 3 HOIST LAYOUT PLAN
DESCRIPTION SPECIFICATION
EQUIPMENT TYPE TWIN
EQUIPMENT NAME ANKA SC200/200GZ
CAPACITY 2.0 TON
Trang 10BUILDING A BETTER FUTURE
10 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR FOUNDATION OF HOTEL
Trang 11COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 1F OF HOTEL
Trang 12BUILDING A BETTER FUTURE
12 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 1HF OF HOTEL
Trang 13COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 2F OF HOTEL
Trang 14BUILDING A BETTER FUTURE
14 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 3F OF HOTEL
Trang 15COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 3HF OF HOTEL
Trang 16BUILDING A BETTER FUTURE
16 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 4HF OF HOTEL
Trang 17COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 5F TO 19F OF HOTEL
Trang 18BUILDING A BETTER FUTURE
18 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 20F OF HOTEL
Trang 19COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR LOWER ROOF OF HOTEL
Trang 20BUILDING A BETTER FUTURE
20 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR ROOF OF HOTEL
Trang 21COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR FOUNDATION OF DOME
Trang 22BUILDING A BETTER FUTURE
22 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 1F OF DOME
Trang 23COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR HF OF DOME
Trang 24BUILDING A BETTER FUTURE
24 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 2F OF DOME
Trang 25COFICO Copyright © 2018
4 1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR 3F OF DOME
Trang 26BUILDING A BETTER FUTURE
26 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 PROPOSED CASTING METHOD CASTING ZONING PLAN FOR FOUNDATION OF COVER DOME
Trang 27COFICO Copyright © 2018
4 2 EARTH WORK
Trang 28BUILDING A BETTER FUTURE
Trang 29COFICO Copyright © 2018
1 FOUNDATION / BASEMENTS & GROUND FLOOR
FOUNDATION : PLYWOOD FORMWORK
COLUMN, WALL / CORE WALL : PLYWOOD FORMWORK
STAIRCASE & RAMP : PLYWOOD FORMWORK
BEAM, SLAB : PLYWOOD FORMWORK
2 NON-TYPICAL
COLUMN, WALL / CORE WALL : PLYWOOD FORMWORK
STAIRCASE : PLYWOOD FORMWORK
BEAM, SLAB : PLYWOOD FORMWORK
3 TYPICAL FLOOR
COLUMN, WALL / CORE WALL : ALUMINIUM FORMWORK
BEAM, SLAB : PLYWOOD FORMWORK
STAIRCASE : ALUMINIUM FORMWORK
Trang 30BUILDING A BETTER FUTURE
30 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
FOUNDATION : PLYWOOD FORMWORK
1
Trang 312 COLUMN, WALL : PLYWOOD FORMWORK
SLAB : PLYWOOD FORMWORK
1
Trang 32BUILDING A BETTER FUTURE
32 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
3 FORMWORK METHOD FORMWORK PLAN FOR TYPICAL FLOOR-5F TO 18F
CORE WALL : ALU FORMWORK
3
STAIR : ALU FORMWORK
4
2 COLUMN, WALL : ALU FORMWORK
SLAB : PLYWOOD FORMWORK
1
Trang 33COFICO Copyright © 2018
1 FOUNDATION : PLYWOOD FORMWORK
Trang 34BUILDING A BETTER FUTURE
34 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
Trang 35COFICO Copyright © 2018
4 3 FORMWORK METHOD FORMWORK FOR COLUMN, WALL NON TYPICAL FLOOR
3
2 COLUMN SQUARE, WALL : PLYWOOD FORMWORK
CORE WALL : PLYWOOD FORMWORK
Trang 36BUILDING A BETTER FUTURE
36 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
3 FORMWORK METHOD FORMWORK FOR STAIRCASE NON TYPICAL FLOOR
4 STAIRCASE : PLYWOOD FORMWORK
Trang 37COFICO Copyright © 2018
Trang 38BUILDING A BETTER FUTURE
38 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
3
2 COLUMN SQUARE, WALL : ALU FORMWORK
CORE WALL : ALU FORMWORK
Trang 39COFICO Copyright © 2018
4 STAIRCASE : ALU FORMWORK
Trang 40BUILDING A BETTER FUTURE
40 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
1 ROUND COLUMN : STEEL FORMWORK
Trang 41COFICO Copyright © 2018
4 4 SAFETY PROTECTION SYSTEM
Trang 42BUILDING A BETTER FUTURE
42 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
Trang 43COFICO Copyright © 2018
Trang 44BUILDING A BETTER FUTURE
44 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
Setting out carried out for brick wall
Laying 1st brick course
02
Concrete curb to be casted
Straight line to be used as controlmeasurement
Completion
03
To finish the brick wall
To check quality during progress
To clean mortar debris or wall
Trang 45 Spacer to be installed base or setting out
To chase brick wall following MEP shopdrawing
To fill mortar and install mesh beforerender
Rendering
02
To spray water to archive proper humidity
To render from top downwards
Inspection
03
To inspect render work following ITP
To cure the rendered wall
To clean working space after completion
Trang 46BUILDING A BETTER FUTURE
46 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
COFICO Copyright © 2018
OPENING PROTECTION SAFETY RAILING PERIMETER SAFETY RAILING
Ceiling frame installation
01
To check ceiling level
To install ceiling frame according to shopdrawing
Panel installation
02
To install ceiling panels
To check the flat of installed panels
To install mesh at panels’ joint
Trang 47 To fill MEP openings, floor drains.
Water proofing application
02
To apply 1st layer of water proofing
To apply 2nd layer of water proofing Thewater proofing layers should be appliedfor 300mm height of brick wall from thesurface
Completion
03
Water test in 24 hours
To screed as protection layer.
Trang 48BUILDING A BETTER FUTURE
48 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
5 CONSTRUCTION METHOD FOR FINISHING WORKS EMULSION PAINT WORK
Trang 49 Provide and check floor level pegs
Floor screed execution
02
Clean and spray water on surfaces
Spread spatter dash coat
Spread mix of cement mortar
Floor screed using steel ruler and plastertrowel
Curing work
03
Floor screed should be cured for 5-7 days
Check hollowness/ eveness
Recover gridline for other works
Trang 50BUILDING A BETTER FUTURE
50 MIKAZUKI PROJECT
COFICO Copyright © 2018
4.
4.
CONSTRUCTION METHOD STATEMENT
5 CONSTRUCTION METHOD FOR FINISHING WORKS FLOOR & WALL TILING WORK
COFICO Copyright © 2018
OPENING PROTECTION SAFETY RAILING PERIMETER SAFETY RAILING
Preparation
01
To clean the surface before application
To identify the starting point of tiling shopdrawing
To use spacer during tilling process
To seal the tiling joints and clean aftercompletion.
Trang 51COFICO Copyright © 2018
5 1 HSE MANAGEMENT PLAN
EXIT WAY HOIST DOOR
ELECTRICAL BOX
NON TYPICAL
Trang 52BUILDING A BETTER FUTURE
52 MIKAZUKI PROJECT
COFICO Copyright © 2018
5.
5.
HSE MANAGEMENT PLAN
2 SAFETY PROTECTION SYSTEM
OPENING PROTECTION PERIMETER SAFETY RAILING
EQUIPMENT, PLAN INSPECTION BROAD
SAFETY RAILING