Once the design well depth is reached, the formation is tested and evaluated. To complete the production well, casing is installed and cemented, and the drilling rig is dismantled. A service rig is brought in to perforate the production casing and run production tubing along with downhole equipments. Production begins after surface safety equipment installation inished.
Trang 1WELL COMPLETION and STIMULATION
Bài giảng được soạn bởi
Bộ môn Khoan – Khai thác Dầu khí
Khoa Kỹ thuật Địa chất và Dầu khí
Trang 31 BASIC COMPLETION METHODS
Trang 4 Once the design well depth is
reached, the formation is tested
and evaluated
To complete the production well,
casing is installed and cemented,
and the drilling rig is dismantled
A service rig is brought in to
perforate the production casing
and run production tubing along
with downhole equipments
Production begins after surface
safety equipment installation
INTRODUCTION
30’’ CASING 20’’ CASING
13 3/8’’ CASING
7’’ LINER
RESERVOIR
SEA BED PLATFORM
Production casing (9 5/8)
Trang 5WHAT IS COMPLETION?
Well completion creates a
dependable pathway to the surface
for the hydrocarbons
The term ‘completion’ describes
the assembly of downhole tubulars
and other safety equipments that is
required to enable the safe and
efficient production of oil or gas
from the well after it has been
drilled
Trang 6BASIC WELL COMPLETION TECHNOLOGY
Each drilled wellbore awaiting completion is unique Even nearby wells drilled to the same reservoir can have differencies in:
A wide variety of equipment designs and procedures have been
developed to provide safe, efficient conduits from subsurface reservoirs to the surface in different situations
The ideal completion design
Trang 7Natural Completions
Natural completions are those in which little or no stimulation is required for production Sandstone and carbonate systems with good permeability and mechanical stability are ideal for natural completions
Trang 8TYPE OF COMPLETION
The design of a particular completion depends on:
1. The number and type of productive zones,
2. The expected pressures and flow rates,
3. The need to control sand production,
4. The need for artificial lift or stimulation the regulations
governing operations in the area.
Trang 9WELL COMPLETION ACTIVITIES
Well completion activities include:
Conducting well test
Setting production casing
Running production tubing along with
downhole equipments
Installing surface safety equipments
Starting production flow
Trang 10BASIC COMPLETION METHODS
Once we drill to the target and evaluate our well by
Mud analysis: density & viscosity
Well logging (electrical, ascoustic, nuclear, etc…)
Coring: at bottomhole or sidewall
Welltest: bottomhole pressure vs time -> reservoir properties
Next decision is whether to complete or abandon it????
In the latter case:
set a cement plug or plugs in the hole,
possibly recover whatever casing can be removed,
and return the drill-site to its original condition
Trang 11The next step usually involves the running of the final string of
casing - the production string
The manner in which this is done determines the basic completion method and may follow one of several configurations: ( interface between the wellbore & reservoir )
the openhole completion,
the liner completion,
the cased and perforated completion
• Without liner
• With liner
BASIC COMPLETION METHODS
Trang 12 The openhole completion : the producing formation is not
isolated by the casing, which extends only to the top of the producing interval.
The slotted liner completion : which is not cemented and not "tied back" to the surface.
BASIC COMPLETION METHODS
Trang 13 The cased and perforated completion
Without liner: cementing the production casing across the productive interval and then perforating the casing for
Trang 14 One of these configurations will be the basis for the completion design, which may incorporate:
one or multiple strings of tubing: single, dual, or triple, etc
and a variety of tubing components to facilitate production (production method): pumping, flowing, etc.
from one or multiple zones: single or multiple zones
For our purposes, a cased and perforated well with a single
tubing string will serve to illustrate the typical completion procedure.
BASIC COMPLETION METHODS
Trang 15Subsea production systems are wells
located on the sea floor, as opposed to
at the surface The safety equipments
are installed underwater on the seabed.
They enable early production from
deepwater, remote, and marginal fields.
Subsea production system offer a means
of producing field extremities not
reachable by directional drilling from
existing platforms, or where field
economics do not justify the installation
SUBSEA COMPLETION
Trang 162 COMPLETION PROCEDURE
Trang 17COMPLETION PROCEDURE
After the contract casing crew runs the final casing, cementing follows the usual procedure , although stage cementing may be necessary to cement an extremely long string
The production string has been hauled out to the location and the inside diameter checked to make sure that imperfections will not prevent the subsequent running in of tubing and packers after the string is set
Trang 18 Special care: to prevent the possibility of future leaks
If stage cementing is necessary:
the bottom section is first cemented in place and then
a series of plugs are pumped down the casing to open ports that allow the upper end of the annulus to receive cement
After the cement has set, the inside of the casing must be
drilled out and
flushed clean of cement and other debris to a depth below that
of the proposed completion
It is important that the inside diameter of the production
COMPLETION PROCEDURE
Trang 19COMPLETION PROCEDURE
It is also important that the cement
form a competent seal between the
casing and borehole over the entire
openhole interval To ensure this,
an acoustic cement bond log is
sometimes run on wireline
to determine if voids exist
between casing and hole because cement has bypassed the drilling fluid.
Trang 20COMPLETION PROCEDURE
If the bond is poor in an area, particularly if the area is between
productive formations, a cement squeeze will be required
Often the cement bond log is run in conjunction with a gamma ray log and a casing collar log The drilling engineers can correlate this gamma ray log with the logs run earlier during formation logging
This correlation is important because as we zero in on the target -
the productive formation - our need to locate tools precisely relative to that formation is critical
⇒ The open hole logging sondes are subjected to a greater amount
of "drag" when being pulled up the hole, the depths at which
Trang 21COMPLETION PROCEDURE
If we were to perforate the casing according to the openhole log depths, we might miss the formation entirely By using the
correlation log and casing collar log to set packers and perforate,
we are assured of precise placement
At this point, many operators
move the drilling rig off location and
replace it with a less expensive, and often less powerful, completion rig
⇒ This gives the operator time to design the rest of the completion, provide for a sales contract, and order equipment.
Trang 22 The casing may also be pressure tested,
and a filtered completion fluid may be circulated into the well to displace the drilling mud prior to perforating
This fluid is usually a heavy brine, because it:
o provides the hydrostatic pressure needed to control the well,
Trang 23COMPLETION PROCEDURE
If perforating is to be done at this point ,
the tubing is removed and
the perforating gun is lowered and positioned according to the correlation log and casing collars
It is critical that the gun be placed precisely ;
once inaccurate perforations are made, they can only be plugged off with a costly cement "squeeze."
Trang 24COMPLETION PROCEDURE
With the well perforated , it may now be time to stimulate the well
by either
acidizing or
hydraulically fracturing the formation.
Acid can be used to dissolve formation-damaging particles left by the drilling mud or, in carbonate formations, to create flow
passages by dissolving portions of the rock itself
Hydraulic fracturing involves the high-pressure pumping of fluid into the formation to split the rock apart and increase its flow capacity of tight formations
Trang 25COMPLETION PROCEDURE
Normally, a completion packer is run and set next , either incorporated into the tubing string or set independently on electric wireline
The packer is pressure tested to ensure its sealing ability (Many
shallow, low pressure wells, however, do not require a packer to isolate the casing from produced fluids.)
The tubing must then be "spaced out." ⇒ This requires that a length of tubing be removed from the upper end so that it can be "landed" in the tubing head, which is some distance bellow the rotary table
Once the tubing has been landed in the tubing head, a temporary plug can be set inside the tubing while the BOP stack is removed and the
surface flow control equipment ("Christmas tree") installed ⇒ This plug
is then removed through the Christmas tree, and the well is completed.
Trang 26COMPLETION PROCEDURE
Of course, this procedure will vary according to
the specific brands of equipment being installed,
the characteristics of the well,
and the policies of different companies,
but the essential sequence of operations will be followed
One variation is the procedure for perforating, which may be
done after the tubing has been run
⇒ This approach allows the formation to be perforated and
immediately "cleaned up" by allowing it to flow as soon as the perforations are created.
Trang 27COMPLETION PROCEDURE
The rig will often be moved off location at this point, allowing the well to brought on production On an offshore platform, the rig may be skidded to the next well slot
If a rod pump is required on the well, it may be installed at this time and the necessary rods and downhole pumping
mechanism run into the tubing
If gas lift valves have been incorporated into the tubing string, gas may be used to blow the completion fluid out of the tubing and permit the well to flow on its own
In some cases, the well will be "swabbed in" at this point , by running a close-fitting plunger into the tubing on wireline and pulling it back up, thereby displacing the completion fluid in the tubing and allowing the formation to flow
Trang 293 PERFORATING
Trang 30 The use of cemented steel casing to line the wellbore and isolate producing zones is only practical when a method for easily
reopening those zones for production exists
Jet perforating is the procedure whereby an explosive charge is
used to selectively open passages to the formation through the casing and cement sheath This method:
relies on a conical-shaped charge of explosives to produce a high pressure stream of particles
casing to penetrate casing, cement, and rock
⇒ This technique has pressure, temperature, and penetration
Trang 31 Jet perforating guns consist of
a carrier with a series of explosive charges linked together by
a detonating cord
A variety of gun designs exist; they vary according to :
- the gun is to be run on an electric conductor line or attached
to the bottom of the tubing;
- the gun is to be run through the casing on electric line or tubing, or is to be lowered through the tubing on electric line;
- the gun is retrievable following detonation or is expendable (meaning it is destroyed when the gun is fired);
Trang 32 Wider, longer perforations require
larger, stronger jet charges,
and, larger guns to hold them
The charge itself is held in a metal case
that is linked to similarly shaped charges by a detonating cord ending in
an electric detonator
When the gun is fired, an electric
current from the surface sets off the blasting cap detonator , which
Trang 33When a charge is fired
The metallic liner collapses to form a stream
of high pressure, high velocity jet particles
Traveling at 30,000 ft/sec (9100 m/sec), the jet
stream strikes the casing at some 15x10 6 psi (100x 106kPa) a fraction of a second after detonation, to form a perforation.
a) before detonation b) after detonation, showing collapsing liner & swelling casing.
c) volatilizing metal liner and formation of particle
Trang 34 Retrievable hollow carrier guns have cylindrical steel bodies with closed ports opposite each jet charge
Fully expendable guns enclose the charges in a frangible aluminum
or ceramic case that disintegrates on firing.
while semiexpendable guns consist of wire or metal strip carriers that are retrieved after firing
Through-casing and through-tubing guns of these types differ
primarily
• 3 to 5 inches [7.6 to 12.7 cm] for casing guns,
Trang 35Type of perforating guns
• Retrievable hollow carrier guns
• Fully expendable guns
Trang 36PERFORATING GUNS
Trang 37 Conventional underbalanced perforating is usually carried out
after tubing has been run and equipment is installed to control the sudden pressure surge when the higher pressure formation is opened to the lower pressure wellbore
Trang 38 For a typical formation the difference between wellbore and
formation pressure may be 300-500 psi (2000-3500 kPa)
For a low permeability formation, the typical difference between wellbore pressure and formation pressure may be 2000 psi (13,800 kPa) or higher -> the immediate surge of formation fluids to
prevent the clogging of the perforation tunnels with debris
When a maximum pressure differential is desired, a
tubing-conveyed perforating gun may be used
it is possible to have the tubing run empty with a ported vent, which opens when the packer is set
Trang 39 In addition to perforation diameter and length , two important considerations in all types of perforating are
the shot density
and phasing of the perforations
The shot density , or shots per foot, is usually 2, 4, 8,12, or 16 holes in each foot of perforated interval
Trang 40 Gun phasing can be particularly important when perforating a
fractured well, a highly deviated well, or a multiple completion, where the gun must be oriented to avoid perforating an adjacent tubing string.
Trang 41 The decision about the interval to be perforated is often made by the
geologist or by the engineer and geologist responsible for the area in which the well is drilled.
Consideration will be given to maximizing flow rate and minimizing production problems such as produced sand, water coning, or
excessive gas production in an oil well
The decision is often made after careful review of the log and core data back at the company office
The geologist's input concerning net pay, sidewall core descriptions, and the areal extent of sand intervals can be crucial in determining the best interval to be perforated.
One of the advantages of the cased and perforated completion: ability to
Trang 42MULTI-LAYER PERFORATION
Trang 434 Stimulation
Trang 44 In many cases,
acidizing
or fracturing
is a routine part of the completion program
Either type of stimulation may also be applied soon after a well
has been completed and
has tested at lower production rates than expected
Stimulation may also be part of a remedial or "workover"
program designed to improve productivity following a decline in production