1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

Hydraulic services technical specification

93 456 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 93
Dung lượng 620 KB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

1 General Information 1 1.1 Drawing list 1 1.2 Acoustic and Vibration Isolation – All Building Services 2 1.2.1 Atmospheric noise limits for plant (normal operations): 2 1.2.2 Internal noise limits 3 1.2.3 Proposed vibration isolationstructureborne noise protection. 3 1.2.4 General Information 4 2 Works by Others 1 2.1 Works by Builder 1 2.2 Works by Mechanical Services SubContractor 2 2.3 Works by Electrical Services SubContractor 3 2.4 Works by Fire Protection Services SubContractor 4 3 Works for Others 5 3.1 Works for Builder 5 3.2 Works for Mechanical Services SubContractor 6 3.3 Works for Electrical Services SubContractor 6 3.4 Works for Fire Protection Services SubContractor 6 4 Description of Works 8 4.1 General 8 4.2 Description of Works 8 4.2.1 Overall responsibilities: 8 4.2.2 Particular responsibilities: 9 5 Technical Requirements 14 5.1 General 14 5.1.1 Site Conditions 14 5.1.2 Existing Services 14 5.1.3 Testing 15 5.2 Workmanship 16 5.2.1 Nuisance 16 5.2.2 Making Good 16 5.2.3 Dimensions 16 5.2.4 Protection Of Polished Surfaces 16 5.2.5 Cleaning Of Surfaces 17 5.2.6 Exposed Pipework 17 5.2.7 Fixing Supporting Of Pipes 17 5.2.8 Capping Off 18 5.2.9 Chasing Of Pipes 18 5.2.10 Core Holes Sleeves 18 5.2.11 Fixtures Fixture Points 19 5.2.12 Laying Of Pipes 19 5.2.13 Restoration Of Surfaces 19 5.2.14 Public Utilities Existing Services 19 5.2.15 Pipe Identification 20 5.2.16 Valve identification 20 5.2.17 Water Hammer 20 5.3 Materials 22 5.3.1 Supply of Materials 22 5.3.2 Availability Of Materials 22 5.3.3 Selection of Materials 22 5.3.4 Rejection Of Unsatisfactory Materials 22 5.3.5 Copper Brass Tubes Fittings 22 5.3.6 Galvanised Mild Steel Pipe Fittings 23 5.3.7 PVC Pipes Fittings 23 5.3.8 Nylon Pipes Fittings 24 5.3.9 Vitrified clay pipes fittings (VCP) 24 5.3.10 Cross Linked Polyethylene Pipes Fittings (XLPE) 24 5.3.11 High Density Polyethylene Pipes Fittings (HDPE) 24 5.3.12 Stainless Steel Pipe Fittings for Sanitary Plumbing. 24 5.3.13 Cast Iron Pipes Fittings For Sanitary Plumbing 24 5.3.14 Precast Reinforced Concrete 25 5.3.15 Fibre Reinforced Cement 25 5.3.16 Fire Seals 25 5.3.17 Jointing Materials 25 5.3.18 Valves 26 5.3.19 Check Valves 27 5.3.20 Strainers 27 5.3.21 Drainage Reflux Valves 27 5.3.22 Gas Valves 28 5.3.23 Water Hammer Arrestors 28 5.3.24 Galvanising 28 5.3.25 Cast Iron Surface Boxes 28 5.3.26 Fixings 28 5.3.27 Unions 29 5.3.28 Flanges 29 5.3.29 Flexible Connections to Pumps 29 5.3.30 Flexible Connections to Taps Gas Appliances 29 5.3.31 Gauges 29 5.3.32 Water Service Insulation Materials 30 5.3.33 Concrete 30 5.3.34 Pits Sumps 30 5.3.35 Covers, Grates Frames 31 5.3.36 Pump Control Panels 31 5.4 Excavation 33 5.4.1 Trench Excavation 33 5.4.2 Exceeding Excavation 33 5.4.3 Excavation In Existing Pavement Roadways 33 5.4.4 Timbering Of Excavation 33 5.4.5 Precautions Safeguards 34 5.4.6 Use Of Explosives 34 5.4.7 Pipe Support in Unstable Ground 34 5.4.8 Bedding Materials 34 5.4.9 Side Support Overlay 34 5.4.10 Backfilling 34 5.4.11 Tunnelling 35 5.4.12 Restoration of Surfaces 35 5.4.13 Excess Spoil 35 5.5 Sewer Drainage 36 5.5.1 Pipework 36 5.5.2 Sewer Connection 36 5.5.3 Packaged Sewage Treatment Plant (STP) Basement 36 5.5.4 Overflow Gullies 37 5.5.5 Reflux Valves 37 5.5.6 Sewer Drainage Pump Pit – Basement 38 5.5.7 Sewer Drainage Pumps – Basement 38 5.5.8 Sewer Drainage Pump Control Panel – Basement 38 5.5.9 Drainage Vents 39 5.5.10 Clearouts 39 5.5.11 Garbage Floor Waste 39 5.5.12 Pits Sumps 40 5.5.13 Covers, Grates Frames 40 5.5.14 Testing 40 5.6 Sanitary Plumbing 41 5.6.1 Generally 41 5.6.2 Pipework 41 5.6.3 Branches 41 5.6.4 Expansion Joints 41 5.6.5 Inspection Openings Gates 42 5.6.6 Traps 42 5.6.7 Offsets 42 5.6.8 Vent Penetrations 43 5.6.9 Vent Terminal 43 5.6.10 Acceptance Responsibility of Sanitary Fixtures 43 5.6.11 Testing 43 5.7 Grease Waste Plumbing Drainage 44 5.7.1 Generally 44 5.7.2 Pipework 44 5.7.3 Traps 45 5.7.4 Grease Arrestor 45 5.7.5 Grease Arrestor Remote Suction Pipes 45 5.7.6 Grease Arrestor Chamber Vents 46 5.8 Stormwater Services 47 5.8.1 Pipework 47 5.8.2 Stormwater Connections 47 5.8.3 Pits Sumps 47 5.8.4 Covers, Grates Frames 47 5.8.5 Downpipes 48 5.8.6 Rainwater Outlets 48 5.8.7 Inspection Openings 49 5.8.8 Grated Drains 49 5.8.9 Subsoil Drainage 49 5.8.10 Stormwater Drainage Pumps – Basement 49 5.8.11 Stormwater Drainage Pump Control Panel – Basement 50 5.8.12 Testing 51 5.9 Cold Water Fire Hose Reel Service 52 5.9.1 Pipework 52 5.9.2 Fire Hose Reels 53 5.9.3 Pressure Reduction Valves 53 5.9.4 Urinal Flush Control Equipment 54 5.9.5 Backflow Prevention Devices 54 5.9.6 Acceptance Responsibility Of Tapware 54 5.9.7 Cold Water Fire Hose Reel Pipe Sizes 54 5.9.8 Connection To Existing Authority Water Main 55 5.9.9 Authority Water Meter 55 5.9.10 Fire Hose Reel Test Point 55 5.9.11 Valves 55 5.9.12 Packaged Water Treatment Plant – Basement 55 5.9.13 Water Storage Tank Basement 56 5.9.14 Cold Water Booster Pumps Basement 56 5.9.15 Cold Water Pressure Unit Roof 57 5.9.16 Water Storage Tank Roof 58 5.9.17 Testing 59 5.10 Hot Water Service 60 5.10.1 Generally 60 5.10.2 Hot Water Pipe Sizes 60 5.10.3 Hot Water Pipe Expansion Joints 60 5.10.4 Heat Tracing 61 5.10.5 Hot Water Temperature Control 61 5.10.6 Thermostatic Mixing Valves 61 5.10.7 Hot Water Units 61 5.10.8 Hot Water Circulation Pumps 62 5.10.9 Hot Water Circulating Pump Control Panel 62 5.10.10 Insulation 63 5.10.11 Automatic Air Release Valve 63 5.11 Gas Service 67 5.11.1 Section 1: Capacity calculation specification. 67 5.11.2 Section 2: Technical Requirement Specification 68 C. Requirements of Gas Leakage Control System 72 5.11.3 Section 3: Requirements of Installation Technique 74 5.11.4 Section 4: Technical Requirements – Inspection, testing and Commissioning 81 5.12 Sanitary Fixtures Tapware 82 5.12.1 Generally 82 5.12.2 Sanitary Fixtures 82 5.12.3 Tapware 82

Trang 1

Hanoi Petroleum Trading Center Project Management Board

Hanoi Petroleum Trading

Trang 2

Hanoi Petroleum Trading Center Project Management Board

Hanoi Petroleum Trading

Center

Hanoi, Vietnam

Hydraulic Services Technical Specification

Approver: Niall Gilfillan

Disclaimer

This specification has been prepared for Hanoi Petroleum Trading Center Project Management Board in accordance with the terms and conditions of appointment for Hyder Consulting (Australia) Pty Ltd ABN 34 000 579 046 cannot accept any responsibility for any use of or reliance on the contents of this report by any third party.

Trang 3

Revision Date Descriptions Prepared By Approved By

Trang 4

1 General Information 1

1.1 Drawing list 1

1.2 Acoustic and Vibration Isolation – All Building Services 2

1.2.1 Atmospheric noise limits for plant (normal operations): 2

1.2.2 Internal noise limits 3

1.2.3 Proposed vibration isolation/structure-borne noise protection 3

1.2.4 General Information 4

2 Works by Others 1

2.1 Works by Builder 1

2.2 Works by Mechanical Services Sub-Contractor 2

2.3 Works by Electrical Services Sub-Contractor 3

2.4 Works by Fire Protection Services Sub-Contractor 4

3 Works for Others 5

3.1 Works for Builder 5

3.2 Works for Mechanical Services Sub-Contractor 6

3.3 Works for Electrical Services Sub-Contractor 6

3.4 Works for Fire Protection Services Sub-Contractor 6

4 Description of Works 8

4.1 General 8

4.2 Description of Works 8

4.2.1 Overall responsibilities: 8

4.2.2 Particular responsibilities: 9

5 Technical Requirements 14

5.1 General 14

5.1.1 Site Conditions 14

5.1.2 Existing Services 14

5.1.3 Testing 15

5.2 Workmanship 16

5.2.1 Nuisance 16

5.2.2 Making Good 16

5.2.3 Dimensions 16

5.2.4 Protection Of Polished Surfaces 16

5.2.5 Cleaning Of Surfaces 17

5.2.6 Exposed Pipework 17

5.2.7 Fixing & Supporting Of Pipes 17

Trang 5

5.2.10 Core Holes & Sleeves 18

5.2.11 Fixtures & Fixture Points 19

5.2.12 Laying Of Pipes 19

5.2.13 Restoration Of Surfaces 19

5.2.14 Public Utilities & Existing Services 19

5.2.15 Pipe Identification 20

5.2.16 Valve identification 20

5.2.17 Water Hammer 20

5.3 Materials 22

5.3.1 Supply of Materials 22

5.3.2 Availability Of Materials 22

5.3.3 Selection of Materials 22

5.3.4 Rejection Of Unsatisfactory Materials 22

5.3.5 Copper & Brass Tubes & Fittings 22

5.3.6 Galvanised Mild Steel Pipe & Fittings 23

5.3.7 PVC Pipes & Fittings 23

5.3.8 Nylon Pipes & Fittings 24

5.3.9 Vitrified clay pipes & fittings (VCP) 24

5.3.10 Cross Linked Polyethylene Pipes & Fittings (XLPE) 24

5.3.11 High Density Polyethylene Pipes & Fittings (HDPE) 24

5.3.12 Stainless Steel Pipe & Fittings for Sanitary Plumbing 24

5.3.13 Cast Iron Pipes & Fittings For Sanitary Plumbing 24

5.3.14 Precast Reinforced Concrete 25

5.3.15 Fibre Reinforced Cement 25

5.3.16 Fire Seals 25

5.3.17 Jointing Materials 25

5.3.18 Valves 26

5.3.19 Check Valves 27

5.3.20 Strainers 27

5.3.21 Drainage Reflux Valves 27

5.3.22 Gas Valves 28

5.3.23 Water Hammer Arrestors 28

5.3.24 Galvanising 28

5.3.25 Cast Iron Surface Boxes 28

5.3.26 Fixings 28

5.3.27 Unions 29

5.3.28 Flanges 29

5.3.29 Flexible Connections to Pumps 29

5.3.30 Flexible Connections to Taps & Gas Appliances 29

5.3.31 Gauges 29

5.3.32 Water Service Insulation Materials 30

5.3.33 Concrete 30

5.3.34 Pits & Sumps 30

5.3.35 Covers, Grates & Frames 31

Trang 6

5.3.36 Pump Control Panels 31

5.4 Excavation 33

5.4.1 Trench Excavation 33

5.4.2 Exceeding Excavation 33

5.4.3 Excavation In Existing Pavement & Roadways 33

5.4.4 Timbering Of Excavation 33

5.4.5 Precautions & Safeguards 34

5.4.6 Use Of Explosives 34

5.4.7 Pipe Support in Unstable Ground 34

5.4.8 Bedding Materials 34

5.4.9 Side Support & Overlay 34

5.4.10 Backfilling 34

5.4.11 Tunnelling 35

5.4.12 Restoration of Surfaces 35

5.4.13 Excess Spoil 35

5.5 Sewer Drainage 36

5.5.1 Pipework 36

5.5.2 Sewer Connection 36

5.5.3 Packaged Sewage Treatment Plant (STP) - Basement 36

5.5.4 Overflow Gullies 37

5.5.5 Reflux Valves 37

5.5.6 Sewer Drainage Pump Pit – Basement 38

5.5.7 Sewer Drainage Pumps – Basement 38

5.5.8 Sewer Drainage Pump Control Panel – Basement 38

5.5.9 Drainage Vents 39

5.5.10 Clearouts 39

5.5.11 Garbage Floor Waste 39

5.5.12 Pits & Sumps 40

5.5.13 Covers, Grates & Frames 40

5.5.14 Testing 40

5.6 Sanitary Plumbing 41

5.6.1 Generally 41

5.6.2 Pipework 41

5.6.3 Branches 41

5.6.4 Expansion Joints 41

5.6.5 Inspection Openings & Gates 42

5.6.6 Traps 42

5.6.7 Offsets 42

5.6.8 Vent Penetrations 43

5.6.9 Vent Terminal 43

5.6.10 Acceptance & Responsibility of Sanitary Fixtures 43

Trang 7

5.7.2 Pipework 44

5.7.3 Traps 45

5.7.4 Grease Arrestor 45

5.7.5 Grease Arrestor Remote Suction Pipes 45

5.7.6 Grease Arrestor Chamber Vents 46

5.8 Stormwater Services 47

5.8.1 Pipework 47

5.8.2 Stormwater Connections 47

5.8.3 Pits & Sumps 47

5.8.4 Covers, Grates & Frames 47

5.8.5 Downpipes 48

5.8.6 Rainwater Outlets 48

5.8.7 Inspection Openings 49

5.8.8 Grated Drains 49

5.8.9 Subsoil Drainage 49

5.8.10 Stormwater Drainage Pumps – Basement 49

5.8.11 Stormwater Drainage Pump Control Panel – Basement 50

5.8.12 Testing 51

5.9 Cold Water & Fire Hose Reel Service 52

5.9.1 Pipework 52

5.9.2 Fire Hose Reels 53

5.9.3 Pressure Reduction Valves 53

5.9.4 Urinal Flush Control Equipment 54

5.9.5 Backflow Prevention Devices 54

5.9.6 Acceptance & Responsibility Of Tapware 54

5.9.7 Cold Water & Fire Hose Reel Pipe Sizes 54

5.9.8 Connection To Existing Authority Water Main 55

5.9.9 Authority Water Meter 55

5.9.10 Fire Hose Reel Test Point 55

5.9.11 Valves 55

5.9.12 Packaged Water Treatment Plant – Basement 55

5.9.13 Water Storage Tank - Basement 56

5.9.14 Cold Water Booster Pumps - Basement 56

5.9.15 Cold Water Pressure Unit - Roof 57

5.9.16 Water Storage Tank - Roof 58

5.9.17 Testing 59

5.10 Hot Water Service 60

5.10.1 Generally 60

5.10.2 Hot Water Pipe Sizes 60

5.10.3 Hot Water Pipe Expansion Joints 60

5.10.4 Heat Tracing 61

5.10.5 Hot Water Temperature Control 61

5.10.6 Thermostatic Mixing Valves 61

5.10.7 Hot Water Units 61

Trang 8

5.10.8 Hot Water Circulation Pumps 62

5.10.9 Hot Water Circulating Pump Control Panel 62

5.10.10 Insulation 63

5.10.11 Automatic Air Release Valve 63

5.11 Gas Service 67

5.11.1 Section 1: Capacity calculation specification 67

5.11.2 Section 2: Technical Requirement Specification 68

C Requirements of Gas Leakage Control System 72

5.11.3 Section 3: Requirements of Installation Technique 74

5.11.4 Section 4: Technical Requirements – Inspection, testing and Commissioning 81

5.12 Sanitary Fixtures & Tapware 82

5.12.1 Generally 82

5.12.2 Sanitary Fixtures 82

5.12.3 Tapware 82

Trang 9

1 General Information

The following Hydraulic Services drawings form part of this tender:

Number Description

H-01 Legend & General Notes

H-02 Inground Hydraulic Services Plan

H-03 Basement Floor Hydraulic Services Plan

H-04 1st Floor Hydraulic Services Plan

H-05 2nd Floor Hydraulic Services Plan

H-06 3rd Floor Hydraulic Services Plan

H-07 4th Floor Hydraulic Services Plan

H-08 5th Floor Hydraulic Services Plan

H-09 6th Floor Hydraulic Services Plan

H-10 7th Floor Hydraulic Services Plan

H-11 8th Floor Hydraulic Services Plan

H-12 9-10th Floor Hydraulic Services Plan

H-13 11th Floor Hydraulic Services Plan

H-14 12th Floor Hydraulic Services Plan

H-15 13th Floor Hydraulic Services Plan

H-16 14th Floor Hydraulic Services Plan

H-17 15th Floor Water Supply Plan

H-18 15th Floor Water Drainage Plan

H-19 16th Floor Water Supply Plan

H-20 16th Floor Water Drainage Plan

H-21 17th Floor Water Supply Plan

H-22 17th Floor Water Drainage Plan

H-23 18th Floor Water Supply Plan

H-24 18th Floor Water Drainage Plan

H-25 19th Floor Hydraulic Services Plan

H-26 Roof Floor Hydraulic Services Plan

H-27 Domestic Water Supply Piping Schematic

H-28 Sanitary Drainage Piping Schematic

H-29 Storm Water Piping Schematic

H-30 Sanitary & Water Supply Details of WC1, WC2

H-31 Water Supply Details of WC3

H-32 Sanitary Water Details of WC3

H-33 Sanitary & Water Supply Details of WC4

H-34 Sanitary & Water Supply Details of WC5

H-35 Sanitary & Water Supply Details of WC6

H-36 Sanitary & Water Supply Details of WC7

H-37 Sanitary & Water Supply Details of WC8

H-38 Sanitary & Water Supply Details of WC9

H-39 Sanitary & Water Supply Details of WC10

Trang 10

Number Description

H-40 Sanitary & Water Supply Details of WC11

H-41 Sanitary & Water Supply Details of WC12

H-42 Sanitary & Water Supply Details of Kitchen K1

H-43 Water Supply Details of Kitchen K2

H-44 Sanitary Water Details of Kitchen K2

H-45 Water Supply Details of Kitchen K3

H-46 Sanitary Water Details of Kitchen K3

H-47 Sanitary & Water Supply Details of Kitchen K4

H-48 Detail of technical room on the roof floor

Atmospheric noise limits for plant (normal operations):

Overall Plant Criteria

The cumulative atmospheric noise levels(i) from the development, should not exceed thebackground noise level(i) at the nearest noise sensitive premises(i) by greater than 5 dB,during the operating period of the plant

If the cumulative plant noise level includes tonal or intermittent characteristics which drawspecific attention to itself, the plant noise level should not exceed the background noiselevel

Individual Plant Criteria

No single item of plant should exceed 5 dBA above the background noise level at 5metres from an outlet/inlet where directly adjacent to normal walkways, open public orstaff areas, or pedestrian areas

Individual or cumulative plant noise should not result in noise break-back into thisdevelopment or any other commercial which exceeds the internal noise criteria (proposedahead), e.g via windows, roof, floor or other indirect paths

The above criteria can be superseded by local authority by-laws, development/planningconstraints, national policy regulation or guidance

For standby/ emergency use equipment (generators / UPS etc):

The cumulative atmospheric noise levels(i) from this plant, during testing or inemergency, should not exceed the pre-existing background noise levelat the nearestnoise sensitive premises(iii) by greater than 15 dBA (if commercial/industrial) and 10 dBA(if residential), during the operating period of the plant Further it should not exceed noiselevel at the adjacent noise sensitive boundary by more than 65 dBA (if commercialIndustrial), and 55 dBA/45dBA (for residential day/night respectively)

Such plant should cumulatively not result in noise break-back into the development which

Trang 11

The above criteria can be superseded by local authority by-laws, development/planningconstraints, national policy regulation or guidance, or alternative criteria agreed withrelevant parties.

Internal noise limits

The following maximum noise levelsi are proposed for the various areas within thedevelopment

Private office space, meeting rooms,

Emergency operating generators / fan systems See (vii)

Services which pass across ceiling spaces, through internal walls and along risers should

be considered in terms of their ability to degrade internal sound isolation performanceneeds, and methods of closure around or within services would need to be considered ineach specific instance

Proposed vibration isolation/structure-borne noise protection.

As a principle, major plant and associated equipment should be installed with vibrationisolation selected so as to provide at least 95% isolation efficiency between the plant andadjacent structure All such plant should also include a noise stop pad as separation fromthe structure in order to attenuate structure-borne noise

All isolation systems should to be considered in terms of the need to accommodatesuitable seismic restraints / bracing etc Such systems should be in line with all local by-laws and codes, standards for the area including compliance with Australian StandardAS1170.4 earthquake loads Open type mounts are preferred, but may not be possible ifseismic requirements need to be accommodated All restraints that are included shouldnot restrict the isolation efficiency of the system supported Care needs to be taken toensure that any super-structure, e.g for anchor embedment, is in place to accommodatethese needs

Standby generators should include carefully selected isolators provided by the supplierthemselves or sub-contractor: air spring mounts would be typically anticipated

It would be expected that:

Large pumps or pump sets would be located on inertia bases at least 1.5 x the weight ofthe pump/s The bases would be supported on open type spring mounts offering at least

25 mm static deflection, and including a noise stop pad

Trang 12

Large fans would include open type spring mounts offering 25 mm static deflection Theunit as a whole would be located on 10-15 mm rubber/neoprene pads or strips, offering1-2 mm static deflection.

Large pipework within plant rooms or across roofs above staff areas, such as fromstandby generators, chilled water pumps etc should include vibration isolation and anoise stops as appropriate, i.e vibration isolation hangers, with noise stops, to soffitsupported pipework; and resilient brackets around roof supported pipes Large pipeworkshould be vibration isolated for at least 50 pipe diameters, within plant rooms or over thesensitive area for which they pass , whichever is the longer

Air cooled chillers and cooling towers would be isolated from the building structureappropriate to their type and specific location They would at least need to be located on

at least neoprene/rubber pads offering 2-3 mm static deflection

Other fans and system should include proprietary vibration/noise isolation as applicable.General Information

All fan systems should include sufficient space for either in-line attenuation ( e.g at least1.5 m long) and/or lined ductwork for at least 5-10 metres

Space should be included within the superstructure design to accommodate vibrationisolation supports for plant

All noise and vibration control measures, attenuator selections etc should be provided tothe acoustic consultant for comment

All local codes/criteria which differs from that given above, should be confirmed to theacoustic consultant or appropriate party

All noise and vibration control measures, attenuator selections etc should be provided tothe acoustic consultant for comment

All local codes/criteria which differs from that given above, should be confirmed to theacoustic consultant or appropriate party

All local codes/criteria which differs from that given above, should be confirmed to theacoustic consultant or appropriate party

i.Cumulative noise level should be in terms of the LAeq noise parameter (A-weighted equivalent continuous noise level) measured over sample periods of not less than 15 minutes.

ii.The pre-existing background noise level should be in terms of the LA90 (A-weighted noise level exceeded for 90% of the period) The LA90 parameter should be determined from a noise survey of the site prior to the development being undertaken, and undertaken at appropriate locations adjacent to or suitably equivalent to, the noise sensitive locations Sample measurement periods should be no less than 15 minutes, and the total measurement period should encompass the times of plant operations ( i.e 24 hours) A 7 day survey is recommended, but not compulsory.

iii Noise sensitive properties can be residential or commercial or public buildings This should be determined on

a site specific basis.

iv.The maximum noise level should be in terms of the LAeq parameter measured over a sample period of typically 2-3 minutes for continuous operating plant or over the longer period for any plant which includes cyclic changes in noise level It should be measured when the plant is operating normally.

v.The table also provides a noise limit in terms of NR (noise rating criteria) The overriding criteria is proposed

as the dBA parameter, but an excessive exceedance of the NR criteria at any frequency is not desirable.

vi.Where a plant room is likely to have a noise level in excess of 85 dBA and operate continuously during

Trang 13

vii Noise from standby generators and associated equipment should be no more than 10 dB above the noise level in that respective internal area The noise level during the operation of smoke control systems (including smoke spill fans and air pressurization fans ) shall not exceed 65 dBA in occupied spaces or 5 dBA above the ambient noise levels, to a maximum of 80 dBA Noise levels in fire – isolated exits shall not exceed 80 dBA.

Trang 14

2 Works by Others

The following main works associated with the construction works in this building shall beprovided by the other Sub-Contractors and/or trades for the Hydraulic Services Sub-Contractor It is this Sub-Contractor s responsibility to co-ordinate the execution of theseworks with his and other parties’ construction programs This list is not complete andshall be used only as a cross referenced list instrumental in the development of fullunderstanding of the scope of works and responsibilities specified for this Sub-Contract:

The following works associated with the installation of the Hydraulic Services shall beprovided by the Builder It is the Hydraulic Services Sub-Contractors responsibility to co-ordinate the execution of these works with his and other parties’ construction programs:

Duct riser block outs;

Ducts, access panels and inspection panels;

Roof gutters and outlets;

Roof and terrace overflow systems;

Wall gutters and outlets;

Drainage cell system behind basement retaining walls;

All access panels to ceiling space;

Fire Hydrant and Fire Hose Reel Housings and signage;

Supply and installation of sink benches and/or support frames;

Grading of shower recesses;

All plinths within galvanised steel plinth surrounds Galvanised steel plinth surroundssupplied and installed in place by the hydraulic services sub-contractor

Concrete hobs and plinths;

Acoustic treatment of plant rooms, ducts and ceilings where required;

Cutting of all holes in finished surfaces, timber cupboards, false ceilings, vanitycupboards, shelves etc;

All signage outside the Hydraulic Services cupboards;

Lifting and hoisting of all hydraulic equipment which does not fit into the clients lifts;

Grading of all finished surfaces to drainage grates & outlets

Grading of roof areas to rainwater outlets

Waterproofing of all building elements as required including hydraulic services pitcoverings, retaining walls, hydrostatic slabs, Lift pits & roof areas

Grading of plant room floors to floor waste grates;

Aggregate zone under slabs Aggregate for bedding and trench backfill by hydraulicservices sub-contractor

Hobs to isolate roof areas from roof plant room;

Trang 15

for the passage of ducts, cables, conduit, etc All above activities for penetrations smallerthan 0.07m2 shall be allowed for and executed by the Sub-Contractor.

Concrete kerb & gutters

Construction of required overland flow paths

Ventilation openings to gas meter, gas regulators, & any other gas equipmentenclosures

All concrete works for grated drains Trench frames & grates to be supplied by thehydraulic services sub-contractor

Erosion, Siltation & Sediment and discharge control of stormwater during construction

Supply and install permanent protection of all pipes exposed to damage from vehicles,and the like, including sanitary stacks, fire hydrants, fire hose reels, downpipes etc

Enclosures for fire hydrant booster valve, fire sprinkler booster valve, pumps, and gasequipment

Fire rating of pump and plant rooms

Concrete sumps and pits that form part of the suspended floor

Supply & Installation of Liquid soap dispensers

Supply LPG gas (bottles) located on ground floor within external storage area

Supply and mounting of all kitchen appliances including dishwashers, gas appliances etc

A nominated subcontractor by the Builder shall provide the following works associatedwith the installation of the Hydraulic Services It is the Hydraulic Services Sub-Contractors responsibility to co-ordinate the execution of these works with his and othertrade’s construction programs:

Landscape Contractor

Suspended Planter box Sub-Soil Drainage (e.g Drainage Cell)

Sub-Soil Drainage requirements for within plant areas

Supply and installation of irrigation system including associated pipework and fittingsincluding any required backflow prevention device(s), pump units, solenoid valves,master control valves etc

Supply and installation of all Water Features & Reflection Ponds including construction,design, and equipment

The following works associated with the installation of the Hydraulic Services shall beprovided by Mechanical Services Sub-Contractor It is the Hydraulic Services Sub-Contractors responsibility to coordinate the execution of these works with his and otherparties’ construction programs:

Condensate drains from Air Handling and Fan Coil Units to sanitary floor wastes andtundishes within each plant room

Discharge drains from cooling tower units to hobbed stormwater drainage outlet at rooflevel

Trang 16

Discharge drains from all vertical discharge ducts to nearest sanitary floor waste withinplant room.

Ventilation to hydraulic services plant rooms as required

Water supply pipework from valved off water supplies to mechanical equipment on roof(1x 40dia and 1 x 32 dia)

The Mechanical services sub-contractor shall supply & install all wiring from the hydraulicservices Control Panel & Distribution Board Alarm Signals to the Building monitoringsystem, including the following: -

Water treatment plant Distribution Board – Basement (Alarm);

Cold water booster pump Distribution Board – Basement (Alarm);

Potable Water Tank Levels - High & Low Level - Basement (Alarm);

Stormwater Pump Pit Control Panel – Basement (Alarm);

Sewer Pump Pit Control Panel – Basement (Alarm);

Potable Water Tank Levels - High & Low Level – Roof Plant Room(Alarm);

Cold water pressure unit Distribution Board – Roof Plant Room (Alarm);

Hot water circulator Control Panel - Roof Plant Room (Alarm);

All from volt free contacts Control panels shall be provided by Hydraulic ServicesContractor

The following works associated with the installation of the Hydraulic Services shall beprovided by Electrical Services Sub-Contractor It is the Hydraulic Services Sub-Contractors responsibility to coordinate the execution of these works with his and otherparties construction programs:

Electrical supply and installation of new terminated sub mains to all equipment requiringpower, to control panels & direct to equipment where required including;

Hard wiring to each electric Hot Water Unit within central hot water plant via isolatingswitch – Roof Plant Room

Hot Water Circulating Pump Control Panel - Roof Plant Room

GPO to each urinal flushing system - each male amenity area

Stormwater Pump Pit Control Panel – Basement

Sewer Pump Pit Control Panel – Basement

Cold Water Booster Pump Control Panel – Basement

Water treatment plant control panel – Basement

Water storage tank control panel – Basement

Water storage tank control panel – Roof Plant Room

Trang 17

2.4 Works by Fire Protection Services Sub-Contractor

The following works associated with the installation of the Hydraulic Services shall beprovided by Fire Protection Services Sub-Contractor It is this Sub-Contractorsresponsibility to coordinate the execution of these works with his and other partiesconstruction programs:

Combined fire hydrant / fire sprinkler system throughout the building

Fire water storage tank and associated valves, overflows etc

Combined fire hydrant / fire sprinkler high flow pump test discharge pipes terminating intofire water storage tank

Combined fire hydrant / fire sprinkler low flow pump test discharge pipes terminating tohobbed stormwater drainage outlet within pump room

Trang 18

3 Works for Others

The following main works associated with the construction works in this building shall beprovided by Hydraulic Services Sub-Contractor for other Sub-Contractors and/or trades

It is this Sub-Contractor s responsibility to co-ordinate the execution of these works withhis and other parties’ construction programs This list is not complete and shall be usedonly as a cross referenced list instrumental in the development of full understanding ofthe scope of works and responsibilities specified for this Sub-Contract:

The Hydraulic Services Sub-Contractor shall provide the following works associated withthe construction works for the Builder:

All required complying and fully certified fire ratings of penetrations for pipes, etc throughwalls, ceilings and other fire rated barriers

Cutting of all penetrations required by the Hydraulic Services installation of a size lessthan 0.07m2 Prior to the commencement of any penetration work the Hydraulic ServicesSub-Contractor is required to obtain appropriate approvals from the Structural Engineer

Supply of Hydraulic services to various completed parts of the building all in accordancewith the construction program

Co-ordinate and set out on site all required access panels to hydraulic services

Making good of all Hydraulic Services penetrations

Disconnection and sealing off of existing redundant hydraulic services

Provision to drain membrane or water proofed building elements where required

Supply of grated trench drain frames & grates

Connection of all hydraulic services to mounted kitchen appliances includingdishwashers, gas appliances etc

The Hydraulic Services Sub-Contractor shall provide the following works associatedBuilder’s nominated subcontractor It is the Hydraulic Services Sub-Contractorsresponsibility to co-ordinate the execution of these works with his and other trade’sconstruction programs:

Landscape Contractor

Capped water supply point to serve Irrigation water systems

Drainage from all planter drains, tree pits & other plant drain requirements to thestormwater drainage system

Trang 19

3.2 Works for Mechanical Services Sub-Contractor

The following works associated with the construction works in this building shall beprovided by the Hydraulic Services Sub-Contractor for the Mechanical Services SubContractor:

Sanitary floor wastes and tundishes to receive mechanical condensate discharges withineach plant room

Hobbed stormwater drainage outlet at roof level for discharge from cooling tower units

Sanitary floor waste to receive discharge drains from all vertical discharge ducts asrequired

Valved water supplies including reduced pressure zone device (on each) for mechanicalequipment on roof (1x 40dia and 1 x 32 dia)

Terminal strips for collection of BMS points

The following works associated with the construction works in this building shall beprovided by the Hydraulic Services Sub-Contractor for the Electrical Services SubContractor:

Control / Electrical wiring and installation to all hydraulic services equipment from ControlPanels / Isolation Switches where required including;

Control wiring from each electric Hot Water Unit outlet thermostat within central hot waterplant to hot water circulator control panel to register low temperature – Roof Plant Room

Hot Water Circulating Pump Control Panel - Roof Plant Room

Urinal flushing system - each male amenity area

Stormwater Pump Pit Control Panel – Basement

Sewer Pump Pit Control Panel – Basement

Cold Water Booster Pump Control Panel – Basement

Water treatment plant control panel - Basement

Water storage tank control panel – Basement

Water storage tank control panel – Roof Plant Room

The following works associated with the construction works in this building shall beprovided by the Hydraulic Services Sub-Contractor for the Fire Services Sub Contractor:

Water supply to the fire water storage tank Dual supplies discharging within each tankdivision via float valves Water supply to refill tank within a 24 hour period (from empty)

Hobbed drainage outlet for minor flow fire test discharge (max 4 L/s) within fire pumproom - Basement

Trang 20

Hobbed drainage outlet for minor flow fire test discharge within fire pump room – Level 11

1 Fire Hose Reel system

Trang 21

4.2.1 Overall responsibilities:

Development of the detail design in compliance with the word and intent of thisspecification

Supply and installation of all designed services to the Client’s approval

Supply and installation of all designed services in accordance with the developmentdescription

Supply and installation of all designed services in compliance with construction program

Supply of engineering skills required to execute the specified works

Preparation & submission to authorities of all hydraulic services designs

Payment of all necessary fees to authorities for design approvals and connections toauthority services

Obtaining of all necessary approvals and permits

Co-ordination of the installation with other trades

Co-ordination of the installation with Architectural, Structural, Civil and Building Servicesdesign

Co-ordination of the services on site

Regular issue of design drawings required by the architect and other building designers

Obtaining approval for equipment & samples from the Client prior to installation

Issue of “Workshop” drawings for approval prior to construction

Issue of “As Installed” drawings and Maintenance Manuals

Testing, commissioning and certification as required of completed installations

Maintenance of the installation for the period specified

Compliance with the authority Development Application conditions

Page 8

Trang 22

Installation to AS 3500.2, and other relevant authority requirements.

Collect all sanitary drainage fixtures and sanitary plumbing stacks via gravity housedrainage system and discharge to the Authority sewer main via a packaged sewagetreatment plant

A suitable packaged sewage treatment (PST) plant equal to Kelair Blivet 1500 to enableacceptable discharge quality to authority sewer main (Flow: 30m3; BOD/SS less than400mg/L; Grease/Oil/Fat less than 30mg/L)

Sludge suction point located external to building to authority approval

Dual sewage pumps and pit with alarms located within the basement Extend sewerrising main and discharge directly to the authority sewer main

Floor waste and tundish within each plant room

All Excavation & Backfilling

Fixing & supporting of pipework above & below ground

Inspection pits & manholes

Garbage floor wastes in loading dock area

Supporting of pipework in filled ground on concrete raft tied to slab

Collection of all vertical stacks & sanitary fixtures

Capped provisions for future connection as nominated

Arrange for new connections and pay all fees to the existing authority sewer main(s)

Relief Overflow gully

Reflux valves where required

Junctions, bends, clearouts, inspection openings and pipework as required

Sanitary Plumbing

The work under this section comprises the complete supply and installation of theSanitary Plumbing services for the project to the satisfaction of the Client and shallinclude, but is not limited to: -

Installation to AS 3500.2, Authority and other relevant authority requirements

Soil, waste and vent pipes from the sewer drainage connection points to vent terminals

Fully vented modified sanitary stacks on each floor as nominated for base building and

Trang 23

All bends, offsets, expansion joints, branches, brackets, sanitary fixtures and sundryequipment necessary to complete the installation.

Grease Waste Plumbing & Drainage

The work under this section comprises the complete supply and installation of the GreaseWaste Plumbing & Drainage services for the project to the satisfaction of the Client andshall include, but is not limited to: -

Installation to AS 3500.2, Authority and other relevant authority requirements

In-ground grease arrestor to capture grease waste and oils from kitchen cooking areas(399 meals per day)

Grease suctions points from each grease arrestor to loading dock area terminated onlabelled manifold

Excavation & Backfilling

Fixing & supporting of pipework above & below ground

Supporting of pipework in filled ground on concrete raft tied to slab

Collection of all vertical grease stacks & grease fixtures

Relief overflow gully

Fully vented modified grease stacks on each floor as nominated for base building andfuture connection

Waste and vent pipes from the grease waste plumbing & drainage system

All junctions, bends, offsets, expansion joints, branches, brackets, grease fixtures andsundry equipment necessary to complete the installation

Stormwater Services

The work under this section comprises the complete supply and installation of theStormwater Services for the project to the satisfaction of the Client and shall include, but

is not limited to: -

Installation to AS 3500.3, and other relevant authority requirements

Roof drainage systems to collect and discharge the highest peak discharge flows (=>100year) to in-ground drainage system via gravity downpipe reticulations

In-ground drainage system to collect and discharge 20% (=>20 year) of the peakdischarge flows with fail safe peak discharge flows via overland flow mechanisms(roadways, paving levels, kerbs, gutters etc.)

All catchment areas to include site area + 1/3 of vertical building façades

Stormwater plumbing & drainage systems to the intent of the Hydraulic Servicesdrawings

Sub-soil systems above the water table & tidal level where required

Basement stormwater pump out system including collection of fire service test dischargeflows

Excavation & Back filling

Fixing & supporting of pipework above & below ground

Trang 24

Inspection pits & manholes.

Internal & external downpipes

Roof, Planter, Carpark and Balcony drains of suitable capacity

Rainwater Outlets with 316 Stainless steel grate where exposed to general public

Junctions, bends, clearouts, inspection openings and pipework as required

Connect all stormwater drainage to the existing authority stormwater main(s) and pay allfees to the existing authority as required

Cold Water & Fire Hose Reel Service

The work under this section comprises the complete supply and installation of the ColdWater & Fire Hose Reel Service for the project to the satisfaction of the Client and shallinclude, but is not limited to: -

Installation to AS 3500.1, and other relevant authority requirements

Extend new site water supply from the existing authority water main to serve thedevelopment Reticulate supply, via a single authority master meter, packaged watertreatment plant, basement water storage tank (50m3), coldwater booster pump (2.5L/s),Roof water storage tank (23m3) and cold water pressure unit (5.0L/s) to serve all hot &cold water consuming fixtures and fire hose reels within the building

Packaged water treatment plant - prior to basement storage tank - suitable to providepotable drinking water quality equal or above to World Health Organisation minimumstandards

Dual Cold water Booster (pump) units - Basement

Dual Cold water pressure (pump) units – Roof

Capped water supply including backflow prevention device for Irrigation watering system.Valves, unions, fittings, hose taps, fire hose reels and sundry equipment as necessary tocomplete the whole of the installation

Pressure reduction valves to control all water pressures above 350 Kpa at all tap outletsand sanitary tapware

Fire hose reels installed to Building Code of Australia (BCA) requirements includinglockable isolating valves where required

Hose tap within each plant room

Hose tap within each garbage room

All backflow prevention devices as required by AS3500.1 including site protection, zoneprotection and individual connection

Isolation valves for each branch off main cold water service to minimise effect ofshutdown

Isolation valve for each riser located above floor level within duct

Potable Stainless Steel Water Storage Tank including, 50% division wall, overflows, infills, step ladders, access hatches, support etc

Trang 25

Hot Water Service

The work under this section comprises the complete supply and installation of the HotWater Services for the project to the satisfaction of the Client and shall include, but is notlimited to: -

Installation to AS 3500.4, and other relevant authority requirements

Valves, unions, fittings, circulating pumps, pipework to the various fittings and connectionpoints, and sundry equipment as necessary to complete the whole of the installation

Hot water pipe work insulation

Pressure reduction valves as required to control water pressures above 350 Kpa to alltap outlets and sanitary tapware

Fixing & supporting of pipework above & below ground

Central electric hot water plant in Roof plant room Extend balanced circulating flow andreturn line throughout the building to serve all hot water consuming fixtures Reticulatehot water flow supply to each amenities area (within 10m of flow line)

Hot water plant will be adequate to meet the demand from all hot water consumingfixtures including amenities and kitchen areas (4500L) The plant will be capable ofdelivering the peak demand over an 1 hour (max) period and have 75% of peak demandavailable during plant replacement

Hose tap within loading dock wash down / garbage area

All backflow prevention devices as required by Authority including site protection, zoneprotection and individual connection

Isolation valve for each branch off main hot water service to minimise effect of shutdown.Isolation valve for each riser located above floor level within duct

 Hot water temperature control to AS3500.4 including all personal hygiene fixtures

 Thermostatic mixing valves for all hot water control

 Air release valves on all heat traps in flow and return reticulation

Gas Service

The work under this section comprises the complete supply and installation of the gasservices for the project to the satisfaction of the Client and shall include, but is not limitedto: -

 Installation to AG 601, and other relevant authority requirements

 Extend LP gas reticulation pipework from storage facility on ground floor via pressurereduction devices and reticulate (below 7pka) to all kitchen areas to serve all gasconsuming fixtures

 Allow 1500MJ/Hr per kitchen cooking area

 Fixing & supporting of pipework above & below ground

 Valves, regulators, unions, fittings, flues and sundry equipment etc as necessary tocomplete the whole of the installation

 Isolation valve for each branch off main gas service to minimise effect of shutdown

 Isolation valve for each riser located above floor level within duct

Trang 26

Sanitary Fixtures & Tapware

The work under this section comprises the complete supply and installation of theSanitary Fixtures & Tapware for the project to the satisfaction of the Client and shallinclude, but is not limited to: -

 Installation to AS 3500 1-4, BCA, and other relevant authority requirements

 Order, take delivery of, store if required in secured location, and install all sanitaryfixtures & tapware as specified necessary to complete the installation

 Fixing of all fixtures, bolts, brackets, adhesives, sealants, cement and sundry materialnecessary for installation and connection of sanitary fixtures in accordance with themanufacturer's instructions

 All fixtures and fittings to be Australian Standard water marked approved

 Refer to Section I for detailed description of sanitary fixtures & tapware

Trang 27

The Hydraulic Services Sub-Contractor is obligated to inspect the site and satisfy himself

as to the conditions under which his work will be carried out No claims for additionalcosts resulting from the lack of knowledge of site conditions relating to works to be done

or locations and levels of mains and mains connections to the Authorities mains will beaccepted

If the actual location, levels etc are not as documented, the Hydraulic Services Contractor shall notify the Client, in writing

Sub-The Hydraulic Services Sub-Contractor shall be completely satisfied that all existingservices required to be connected are those to which the documents indicate connectionand that they are of the size and level shown on the drawings No additional claims will

be accepted for rectifying works that have been incorrectly connected as a result of failing

to confirm the documented information, on site, prior to commencing this work

The Hydraulic Services Sub-Contractor shall not close down any existing services withoutgiving at least 48 hours notification to the Client or without written approval to do so Afternotification to the Client that the service is redundant, the Hydraulic Services Sub-Contractor may proceed to cap off or seal the service off in the correct manner, as isrequired by the Authorities and the Client

The Hydraulic Services Sub-Contractor will be responsible for checking with allAuthorities and the Client concerning the location of any existing services on the site

All damage caused by the Hydraulic Services Sub-Contractor to operational services,building structure, paving and roads shall be made good at his own expense as the work

in the affected area proceeds

Trang 28

The Hydraulic Services Sub-Contractor shall carry out all necessary testing of theservices nominated in the Specification and required by the respective Authorities andthe Client

Provide a record of any tests to the Client

The Hydraulic Services Sub-Contractor will be responsible for supplying all labour, plugs,pressure gauges, measuring gauges, pumping equipment and all other necessarymaterials and equipment, etc., required to do such tests

Before enclosing or concealing pipework, carry out an operational test to the satisfaction

of the Client, remedy any defects, particularly water hammer, and retest to thesatisfaction of the Client

Underground or enclosed works shall not be covered or concealed from view unless ithas been inspected, tested and approved by the Client and the Authorities concerned

All services are to be inspected by the Client and the Relevant Authorities

Inspections carried out by the Relevant Authorities will not relieve the Hydraulic ServicesSub-Contractor s responsibility of obtaining an inspection by the Client

The Client at all times reserves the right to inspect all pipework and services Should, forany reason, pipework be concealed before the Client has inspected the work, then theHydraulic Services Sub-Contractor shall expose all pipework requested by the Client athis own cost Any costs associated with the damage and/or repair to any other services,structure, surfaces, plant, equipment, etc shall be borne by the Hydraulic Services Sub-Contractor

On completion, the works included under this part of the specification shall be testedunder normal working conditions and as directed by the Client All defects shall beremedied immediately and the tests reapplied to the satisfaction of the Client and theAuthorities

At least 48 hours notice will be given before the carrying out of tests The Client mayinstruct longer periods

Trang 29

5.2 Workmanship

Nuisance

No work shall be carried out, materials handled in such a manner as to cause nuisance

on the site or to other Contractors, to the public at large or occupants of adjacentbuildings Notify the Client before commencement of necessary works that may causeinconvenience to the parties concerned

All work causing a hazard to others shall have safety barriers surrounding the works

Making Good

The Contractor shall be responsible for and shall make good any damage he may cause

to the building and surfaces generally and any other works that may be disturbed orinjured by cartage, work generally or other operations The reinstatement shall be at least

as good a state of repair as before commencement

Dimensions

The Contractor shall be responsible for taking all dimensions on site The dimensionsmust be checked before work is commenced or prefabricated, all levels and dimensions

of existing services must be confirmed before commencing work The invert levels shown

on the drawings are recommended only, and must be checked on site before excavation

or installation of pipework to ensure connection to supply sources are correct

Protection Of Polished Surfaces

All polished and exposed surfaces and such material as stainless steel, chromium plated,vitreous enamel surfaces shall be protected during all stages of construction by anapplication of a strippable coating similar and equal in all respects to "Behr Manning M.B.614"

The coating shall be applied as soon as practicable and shall not be removed untilcompletion of the project All damaged coating shall be repaired immediately

On removal of the coating, the surface of the material shall be cleaned with methylatedspirits and polished with a soft, dry cloth Any scratched or damaged finished surface willnot be accepted

Cleaning Of Surfaces

Trang 30

After installation and prior to testing of the services, fixtures and equipment, the item shall

be thoroughly cleaned and flushed out in an approved manner All valves, seats, tapwashers, strainers, non-return valves and inspection openings shall be checked andcleaned of any foreign matter

Damaged seats, washers, installations and gaskets, etc., shall be replaced Any pipeworkburied or permanently enclosed before it has been thoroughly cleaned, inspected, testedand proved to be satisfactory by the Client shall be uncovered at the expense of theContractor

Exposed Pipework

Except as otherwise specified or directed, all internal exposed piping throughout andadjacent to plumbing fixtures shall be chromium plated copper finished, and wherepassing through a finished wall, floor or ceiling shall be fitted with an approved typechromium wall or cover plate All other internal and external piping shall be cleaned free

of cement droppings

Fixing & Supporting Of Pipes

All service pipes shall be positioned in approved locations before installation orfabrication of pipework commences

All pipes shall be adequately supported and secured to adjacent walls and slabs andexisting floors

Pipework shall not come into contact with any other service pipes

All pipework shall be fixed in a manner so as to allow free movement without causingundue stresses in the pipework or in the pipe joints and without transmitting lateralstresses via fixing to walls, slab or ceilings

Pipework shall not be, either permanently or temporarily, fixed in position by the use ofnails Should leaking pipework occur due to electrolytic corrosion between the pipeworkand the nails, then the Hydraulic Services Sub-Contractor shall be responsible for allcosts associated with the repair including pipework, walls, finishes, etc whenever theleaks may occur

All supports shall be equal to "Unistrut" P1000 channel complete with all-purpose madespring nuts, framings, fittings and pipe clamps for each pipe

Vertical frames where used to support suspended horizontal runs of pipework, shall allowfor complete adjustment of clamp support to suit pipe grading’s as required

Channels shall be of concrete insert type wherever practicable, where not, the channelshall be fixed with expansion type bolts fixed direct or with purpose made clips to walls orunderside of slabs and hanger rods fixed into the channel

Trang 31

All copper pipes shall be separated from supports by one (1) mm thick rubberised stripequal to “uni-cushion” P2600 or similar approved materials.

All copper hot water pipes shall be separated from supports by 25 mm thickness purposemade wooden block spacer pieces

Explosive power tools may not be used

Remove all cement droppings, dirt and superfluous material from all pipe supports andpaint them at all cut ends with one coat of cold galvanising paint Pipes shall be fixed andsupported in accordance with AS 3500 requirements

Copper soil, waste and vent pipes shall be regarded as being fixed at all supports where

no provision has been made for axial and/or lateral movement Provision for movementshall be achieved by the provision at the support of an annular space around the pipe ofnot less than 8 mm clear

Vertical copper soil and waste pipes must be clear to move vertically at least 8 mm inboth directions through all ceilings, roofs, etc., through which they pass

All pipes shall be supported against sagging or distortion and must be held true to lineand grade by means of approved clips, saddles or other fixings

Capping Off

During the construction the Hydraulic Services Sub-Contractor shall be responsible forchecking that all unfinished work is left in a safe condition, protect against all damage orloss through any cause whatsoever, and make sure to prevent the entry of any foreignmatter including liquids All services capped off for future connection shall be finishedwith an identification marker stating type of service and respective location to thesatisfaction of the Client

Chasing Of Pipes

The Hydraulic Services Sub-Contractor shall carry out all chasing in walls for pipeworkand equipment with a mechanical saw Chasing will not be allowed in concrete walls orslabs unless the Client so gives approval in writing to do

Note: All chased water supply pipework shall be insulated

Core Holes & Sleeves

The Hydraulic Services Sub-Contractor shall set out all core holes and sleeves in floors,walls, beams and columns in conjunction with the fixing of formwork and/or placing ofconcrete All pipe penetrations through the building structures shall comply with theBuilding Code of Australia

To prevent weakening of the building structure all core holes shall be approved by theClient prior to placing of concrete Strip holes from formwork and every pipe passingthrough a core hole shall be backfilled with concrete to the satisfaction and approval of

Trang 32

the Client All holes not used shall be filled by the Hydraulic Services Sub-Contractor withconcrete and to the approval of the Client

All core holes for soil or waste pipes on new suspended floors shall be made by means of

a patented plastic slab seal unit with rubber diaphragm equal to those manufactured bySlabseal Pty Limited

Materials used for forming core holes shall be 0.7 mm sheet metal and shall have adiameter of at least 50 mm greater than the outside diameter of the pipe it serves

Fixtures & Fixture Points

The Hydraulic Services Sub-Contractor shall supply and install all materials, backingplates and noggins necessary to make all fixtures and fixture outlet points rigid (i.e.sanitary fixtures and tap fittings, etc.)

Laying Of Pipes

The Hydraulic Services Sub-Contractor shall install or lay all pipes in a correctworkmanlike manner with correct and even falls and grades, straight and correctly fittedinto the other pipes with rings straight and equal with even pressure all round

The main sewer line shall be installed to the correct grades, with the use of an electronic(laser) level

All rubber-ringed joints shall be cleaned free from sand, grit and moisture prior to themaking of the joint

Restoration Of Surfaces

Restore all roads, paving, bitumen surfaces, etc., damaged as a result of the executedwork Restore with equal quality materials to the same standards of construction andexpected life as existing prior to commencement of works

Public Utilities & Existing Services

Where underground public utility lines, surface drainage works and underground pipes,conduits or cables exist in the vicinity of the works, the Hydraulic Services Sub-Contractor must take care to protect such services Any damage to such services must

be immediately reported to the responsible Authority and to the Client

The cost of the necessary repairs or renewals shall be borne entirely by the Hydraulic

Trang 33

The Service

The Stratum it is serving

For example:

-Common Cold Water & Fire Hose Reel Supply

Building # Cold Water and Fire Hose Reel Supply

The labels shall be located at intervals not exceeding 3 metres, in areas describedunder AS 3500.1 Clause 5.21 & AG 601

Valve identification

All isolating valves, with the exception of single & group fixture-isolating valveswithin the same area as the fixture, shall be clearly identified with a removable tag.The tag shall be durable and marked clearly, indicating a brief description of itspurpose The valve description should also include an assigned valve number Thenumber of the valve shall correspond to the same number, which will be shown onthe “as built” drawings

Water Hammer

Before concealing any water service pipework, the Hydraulic Services Sub-Contractorshall carry out an operational test for water hammer Test results shall be recorded andmade available to the Client when requested Should there be any evidence of waterhammer within the water services, the Hydraulic Services Sub-Contractor will be required

to remedy the problems

Should any pipework be concealed prior to testing, and water hammer exists, then theHydraulic Services Sub-Contractor will be required to remedy the problems and makegood all surfaces, structure, fittings and fixtures at his own cost

Trang 34

Availability Of Materials

The Hydraulic Services Sub-Contractor shall, be fully satisfied that all specified materialsand items relevant to this project are available from manufacturers, at the time ofconstruction

Rejection Of Unsatisfactory Materials

All materials and finishes which are deemed not in accordance with this specification will

be rejected and replaced with materials to comply with the instructions issued by theClient at no extra cost to the Client

Copper & Brass Tubes & Fittings

Copper tubes shall be solid-drawn in accordance AS 1432 and installed in accordance

Trang 35

Fire Hose Reel pipework - BCA, AS 1221 & AS 3500

Fire Hydrant Pipework - AS 2419.1 & AS 3500

Galvanised Mild Steel Pipe & Fittings

Galvanised mild steel (GMS) tubing and fittings shall conform to AS 1074 medium gradewith screwed joints

Galvanised malleable fittings shall comply with BS 1256

All pipe and fittings, including the flanges and bolts shall be hot-dipped galvanised

Pipe and fittings for fire hydrant services shall comply with AS 2419.1 and equal rollgrooved, with victaulic joints

PVC Pipes & Fittings

PVC pipes and fittings shall be in accordance with the following:

-Sanitary Plumbing - AS 3500.2 Class “DWV”

Sewer Drainage - AS 3500.2 Class “DWV”

Stormwater Drainage ( Inground ) - AS 3500.3 Class “SH” or “DWV”

Stormwater Drainage (exposed to ultra violet light) - AS 3500.3 Class “DWV”

Sub-soil drainage slotted type hard drawn tube with geo-fabric sock surround – AS3500.3 Class "HD"

Downpipes - AS 3500.3 Class “DWV”

Downpipes (not exposed to ultra violet light) - AS 3500.3 Class “DWV”

Conduits - AS 1260 Class “SH” or “DWV”

Sewer rising main – AS 3500.2 Class 12 (fittings to be Class 15)

Stormwater rising main – AS 3500.3 Class 12 (fittings to be Class 15)

All PVC pipework and fittings shall be equal to “Vinidex” and installed in accordance withmanufactures recommendations

Nylon Pipes & Fittings

Nylon (Polyamide) pipes & fittings to AG 601 requirements

Trang 36

Vitrified clay pipes & fittings (VCP)

VCP pipe and fittings shall conform to AS 3500.1 - 4 limitations and authorityrequirements

Cross Linked Polyethylene Pipes & Fittings (XLPE)

XLPE pipe and fittings shall conform to AS 3500.1 - 4 limitations and authorityrequirements

All XLPE pipework and fittings shall be equal to “Rehau” and installed in accordance withmanufactures recommendations

High Density Polyethylene Pipes & Fittings (HDPE)

HDPE pipe and fittings shall conform to AS 3500.1 - 4, limitations and authorityrequirements

All HDPE pipework and fittings for Syphonic Downpipe Systems shall be equal to

“Fullflow Syphonic Systems” and installed in accordance with manufacturesrecommendations

All HDPE pipework and fittings for Drainage applications shall be equal to “Geberit” andinstalled in accordance with manufactures recommendations

Stainless Steel Pipe & Fittings for Sanitary Plumbing.

Stainless steel pipe and fittings for use in sanitary plumbing shall be equal to “Blucher”stainless steel pipework systems and shall be installed to the requirements of Authorityand AS 3500.2

Cast Iron Pipes & Fittings For Sanitary Plumbing

Cast iron fittings shall conform to the requirements of AS 1631

Suspended fittings shall have bolted gland mechanical joints for pipes and fittings

Fabrication with epoxy resin or similar type glue on fittings will be acceptable providingthe manufacturer carries out such fabrication and has a test certificate of warrantyprovided by the manufacturer

Screwed type inspection covers shall be provided at bends and junctions to comply withthe testing Authority's normal requirements for examination

Trang 37

Precast Reinforced Concrete

Precast reinforced Concrete Pipes shall:

Conform with AS 1342 Class "X" generally, unless indicated otherwise

Conform with AS 1342 Class "Z" where subject to vehicular traffic or in Public areas

Be rubber ring jointed

Be jointed in accordance with manufacturer's instructions

All junctions, bends etc., shall be made with pits or manufactured fittings

Fibre Reinforced Cement

Fibre reinforced cement (FRC) pipes and fittings shall:

Conform to AS1342 'Class X' generally unless indicated otherwise

Be rubber ring jointed using 'Supertite Joint'

Be jointed in accordance with Manufacturer's instructions

All junctions, bend etc., shall be made with Manufacturer's fittings

All fittings to be supported in accordance with Manufacturer's instructions

All FRC pipes and fittings will be installed in accordance with the relevant authorityrequirements and limitations

Fire Seals

Where PVC pipework penetrates fire rated elements (floors, walls, etc.) allow to provide afire seal to the required fire resistance rating for the element to the approval of theCouncil

Jointing Materials

All joints shall be cleaned free of any foreign materials, dirt and Trade, etc., before anyattempt is made to complete the joints

Joints shall be cut true and square, all burrs, etc., removed and a chamfer lightly ground

or filed around the pipe

Silver solder

Shall contain not less than 5% silver, verification of the silver content shall be given inwriting to the Client Care shall be taken not to overheat the joint, and apply the correctflux as recommended by the manufacturer A slightly carbonising flame shall be used

Soft solder shall be lead free

All joints shall be properly prepared before commencing the soldering and the fluxrecommended by the manufacturer used

Cement

Trang 38

Shall be Portland cement type "A" and respective to AS 1315 stored in a dry andmoisture free state and mixed as required.

Rubber Ring Gaskets

Vitrified Clay Pipes shall be jointed using AS 1693 rubber rings of approved manufacture.Concrete pipes shall be jointed using AS 1646 rubber rings of approved manufacturer.Cast Iron Pipes Rubber ring gaskets for spigots and socket joints on cast iron pipes shall

be moulded of the type recommended by the pipe manufacturer for the joint to be used.This shall be sufficiently durable to last the life of the pipe without leaking under theproposed conditions of usage

Lubricant

For lubricating the rubber ring and insertion type gaskets and the outside surfaces ofspigot ends of pipes shall be of an approved non-toxic vegetable based type and shall beapplied in accordance with the manufacturers' instructions

Nuts and Bolts

Shall generally conform to the relevant Australian Standard and shall be heavilygalvanised by the hot-dip process Where galvanised iron to cast iron flanges butt,galvanised bolts shall be used Where brass-to-brass and cast iron-to-cast iron flangesbutt, brass bolts shall be used

Silicon sealant

Shall be self-polishing with anti-fungicide additive equal to Ciba-Geigy manufacture andused as recommended by the manufacturer White shall be used around vitreous chinasanitary ware and clear for seal under fixture taps and stainless steel, etc

Polyvinylchloride ( PVC or UPVC )

Pipes shall be jointed by solvent welding of the type recommended by the manufacturer.Clean joint with approved solvent cleaning fluid Apply an even liberal layer of theapproved solvent cement to both surfaces of the joint and allow to stand to become touchdry, apply a second coat to both surfaces of the joint and push together, remove allsurplus solvent with a clean, dry cloth in accordance with the relevant AustralianStandard

Valves

All valves used shall be "Johns" or equal approved by the Client and shall be the best oftheir type, quality and grade available All valves shall be placed in easily accessiblepositions for operation and repair

Valves to the pump connections shall be of the gate valve or ball valve pattern.Elsewhere the valves shall be of the loose jumper or ball valve pattern An approvedtesting Authority shall test all valves to a pressure of 2,100 kPa

Balancing valves for hot water service shall be manufactured of bronze

All valves 65 mm and over shall be flanged All other valves shall be screwed Valves up

Trang 39

Spindles shall be non-rising type and must not project into the bore of the valve when thevalve is in the fully open position The bore must be clear and unobstructed when in thisposition.

The internal seats and washers of the valves must be cleaned of all foreign materialduring installation Any valve faces or seats found damaged on completion of theinstallation shall be replaced

Bronze with stainless steel screen for strainers up to 50mm in diameter equal to

"Bestobell" Figure No.510

Drainage Reflux Valves

Reflux valves shall be cast iron horizontal pattern with a bolted inspection cap, andconnected to the sewer drainage system The reflux valve shall be manufactured andtested in accordance with AS 1718 and be approved by the Authority Corp

All reflux valves in ground, and upstream of a sewage boundary trap, may be of themanufactured PVC type

All reflux valves shall be installed in accordance with AS 3500 and Authorityrequirements

Gas Valves

Unless otherwise indicated gas valves shall be:

-Approved by Local Authority

Spherical Ball types with approved lubricant

Trang 40

Water Hammer Arrestors

Supply and install proprietary water hammer arrestors to all isolating valves for clotheswashing machine taps & dishwashing machines

Water hammer arrestors shall be chrome plated where exposed and equal to a 15mm

“Mini-Restor“ water hammer arrestor manufactured by “Sioux Chief”

Cast Iron Surface Boxes

Supply and install cast iron surface boxes marked S.V over all underground valves

The box shall be concreted to a 150 mm diameter vitrified clay pipe riser extending upfrom the valve

Fixings

Fixings shall be " Dynabolts " or equal approved expansion type bolts and shall beinstalled in direct accordance with the manufacturer's instructions and to the approval ofthe Client

All fixings exposed to underwater conditions shall be treated in accordance with themanufacture’s recommendations and to the approval of the Client

Unions

Unions shall be three (3) piece brass, bull-nose taper type unions Brass and copper

“flare nut” type union connections shall not be used under any circumstances Unionsshall be located on the outlet side of all valves

Flanges

Ngày đăng: 21/02/2017, 14:22

TỪ KHÓA LIÊN QUAN

w