Methor statement, for production of super, T Girder
Trang 11 General 3
2 Materials 3
3 Main Equipment and Tools 4
1) Fabrication Yard No.1.1 4
2) Fabrication Yard No.1.2 5
3) Fabrication Yard No.2 5
4 Site Organization Chart 6
5 Construction Flow Chart 7
6 Detail Construction Procedure 8
1) Detail Work Procedure 11
a) Preparation work 11
b) Pre-assemble rebar cage 12
c) Installation rebar cage 12
d) Installation PC strands 13
e) Installation inner formwork 18
f) Casting concrete 19
g) Curing and removal of inner formwork 20
h) Cutting tendons 21
i) Lifting girder to stock yard 24
j) Filling the non - shrinkage mortar 25
2) Cycle Time of Super-T Girders Fabrication 25
7 Schedule for Production of Super T Girder 25
8 Quality Control 25
9 Environmental Control 25
10 Safety Control 26
11 Emergency Call out Procedure 36
1) Initiation 36
2) Second Stage 36
3) Third Stage 36
4) Emergency response chart 37
12 Appendix 37 1) Appendix – 1: Plan of fabrication yard No.1.1; No.1.2 and No.2
2) Appendix – 2: Working drawing for production of super T girder
3) Appendix – 3: General drawing gantry crane 80 tons and 5 tons
4) Appendix – 4: General drawing of formwork system
5) Appendix – 5: Drawing of pre-installation of rebar cage frame for super T girder 6) Appendix – 6: Drawing lifting crane of rebar cage for super T girder
Trang 27) Appendix – 7: Drawing of frame system for hanging inner formwork
8) Appendix – 8: Drawing of detail for lifting hook
9) Appendix – 9: Drawing of protection frame during stressing
10) Appendix – 10: Calculation of formwork system
11) Appendix – 11: Calculation of camber of permanents
12) Appendix –12: Lifting device calculation of Super T girder
13) Appendix –13: Calculation for pre-stressing of Super T girder
14) Appendix –14: Inspections and test plan
15) Appendix –15: Inspection sheet form
Trang 31 General:
Project information:
P r o j e c t n a m e : N o r t h – S o u t h E x p r e s s w a y C o n s t r u c t i o n P r o j e c t ( B e n L u c - L o n g T h a n h
Section) – Contract Package No.J2
for Superstructure of Approach Span Structures in accordance with General Specifications
length in consideration with the effect of horizontal curve and change in width of
carriage-way
T h i s w o r k i t e m s h a l l b e d o n e i n a c c o r d a n c e w i t h t h e r e q u i r e m e n t s o f C l a u s e S 0 7 4 5 0
concrete structures of the Technical Specifications
There are 3 types of Pre-cast super-T girders as below table:
Precast Girder
Work Classify Unit Total Comment
Number strand
approved by the engineer shall be shown as the below table:
Trang 4Name of material Specification Quantity Remarks
or others measures
M a t e r i a l q u a l i t y c o n t r o l a t s i t e , e s p e c i a l l y r e b a r , s t r e s s e d c a b l e w h i c h a r e s e n s i t i v e
against corrosion shall be carefully stocked and controlled in dry condition
D e t a i l e d q u a n t i t i e s s h a l l b e i n d i c a t e d a n d s h o w n o n t h e w o r k i n g d r a w i n g w h i c h i s
approved by the engineer
3 Main Equipment and Tools:
The quantity of equipment’s below may be changed with required actual conditions
1) Fabrication Yard No.1.1:
2) Fabrication Yard No.1.2:
Trang 5No Item Capacity Unit Q’ty Remark
3) Fabrication Yard No.2:
Trang 6type 34.3m set 01 Production SPT girder
H y d r a u l i c J a c k i n g M a c h i n e ( H y d r a u l i c p u m p & G a u g e ) w i l l b e v e r i f i e d b y i n d e p e n d e n tlaboratory under supervision of Engineer
4 Site Organization Chart:
5 Construction Flow Chart:
Technical
Surveyor
Worker (25)
TechnicalSurveyorWorker (30)
TechnicalSurveyorWorker (45)
Yard no.2
TechnicalSurveyorWorker (30)
Trang 76 Detail Construction Procedure:
1) Detail Work Procedures:
Inspection of shape and dimension of fabricated rebar
concrete cover…)
rebar cage
Using trussing beams for lifting the whole rebar cage
Inspection of rebar after installation (stability, verticality, position, concrete cover thickness…)
cage
cage
Checking strands testing result, certification of anchorage
Checking the calibration of jack and gauge
strands and
tensioning
cage
Carefully install inner form after tensioning
Checking the stability of inner form after fixing into bed
form work
cage
Checking resource of concrete supply
Checking slump and temperature of concrete
Checking stability and deflection of form during casting process
process
cage
Checking and recording the curing duration, temperature
Shifting girder to storage by gantry crane and lifting
Finishing and repairing (if any) shall be carried out
stock yard
cage
Trang 8a) Preparation Works:
for material testing and calibration of stressing jack and pump shall be confirmed
attendance of the Engineer
production of super-T girder
a c c o r d i n g t o a l l o w a b l e e r r o r i n s p e c i f i c a t i o n a n d w o r k i n g d r a w i n g o f f a b r i c a t i o nyard
b) Pre-assemble Rebar Cage:
provided with suitable cover
in the approved working drawing, and shall be fabricated in a manner that will notinjure the material
b e n t b y h e a t i n g , t h e e n t i r e o p e r a t i o n s h a l l b e a p p r o v e d b y t h e e n g i n e e r Reinforcing bars that cannot be straightened by means of fabrication shall not be
Trang 9 R e i n f o r c i n g b a r s b e f o r e b e p o s i t i o n e d s h a l l b e c l e a n e d a n d f r e e f o r m r u s t , d i r t ,
mud and loose scale and from paint, oil, or any other foreign substance destroys
or reduces the bond
for super T girder
R e i n f o r c e m e n t f r a m e i s f a b r i c a t e d w i t h c o n f o r m i n g d i m e n s i o n s t o e a s i l y i n s t a l l
reinforcement for super T girder
F a b r i c a t e d r e i n f o r c i n g b a r s s h a l l b e i n s t a l l e d o n t h e f r a m e b e f o r e s e t t i n g i n t o
casting bed
Rebar cagePre-installation frame
firmly held during placing concrete
or lager diameter or suitable clips
C o n c r e t e c o v e r s s h a l l b e s e t t o m a i n t a i n t h e d i s t a n c e f r o m t h e f o r m w o r k s t o
reinforcing bars
nominal diameter of bars In lapped splices the bars shall be lapped the required
lapped in any one cross section
working draw
Trang 10bé nèi lo¹i 2 coupler type 2
1140
50 660 50 760
c) Installation Rebar Cage:
tons End form is hold by 4 support jack as below drawing :
SUPPORT JACK
TENSIONING BEAM B2
TENSIONING BEAM B2
SUPER T GIRDER
SUPPORT JACK END FORM
with approved working drawing
Trang 11 Concrete blocks with steel wire or plastic spacer shall be installed at bottom and
side of rebar in order to keep the appropriate concrete covering
the bond
work shall be installed at proper location
Casting bed
Outer form
Lifting frameRebar cage
Plat form
d i s m a n t l e d a n d r e m o v e d t o o u t o f r e b a r c a g e b y g a n t r y c r a n e f o r i n s t a l l a t i o nremaining bar
A f t e r s e t t i n g , r e i n f o r c e m e n t b a r s , c o n c r e t e c o v e r s h a l l b e a d j u s t e d t o e n s u r e
correctly position, spacing, and shall be inspected ,approved by the Engineer
Trang 12 T h e r e i n f o r c e m e n t b a r s d u r i n g t h e p r e - a s s e m b l y p e r i o d a n d w a i t i n g t i m e a f t e r
to prevent rust and corrosion
setting of inner forms
locate PVC holes by ruler, installing PCV D170 pipes in the positions which hadbeen located by the steel wires to create waiting holes for PVC tubes
d) Installation PC strand:
to requirements of ASTM 416 Grade 1860
A l l t h e s t r a n d s s h a l l b e c u t w i t h e n o u g h l e n g t h P V C p i p e s w i t h o u t e r d i a m e t e r
22mm and inner diameter 18mm and adhesive tapes shall be installed at end ofstrands for de-bonding
notice position of each tendon at ends girder must be same
twisted or stuck
W h e n t e n s i o n i n g t h e s t r a n d s s h a l l b e l e n g t h e n e d , t h e r e f o r e t o m a k e s u r e d e
-bonding length of the strands complied with design, ends of PVC pipes shall be
l e n g t h e n e d t o i n n e r f a c e o f t e n s i o n i n g b e a m s s o t h a t P V C p i p e s s h a l l n o t b emoved when the strands are being tension
Trang 13- Before carry out the tensioning work, having to check whether the forms andcasting bed have the defects or not, in case of defects have no repair.
or otherwise instructed by the Engineer
- S t r e s s i n g o n a l l s t r a n d s s h a l l b e m a i n t a i n e d b e t w e e n a n c h o r a g e s u n t i l t h e
c o n c r e t e h a s r e a c h e d t h e c o m p r e s s i v e s t r e n g t h r e q u i r e d a t t i m e t r a n s f e r o fstress to concrete, it is the minimum 85% of design concrete strength
- I n a n y c a s e t h e j a c k i n g s t r e s s s h a l l n o t e x c e e d 7 5 % o f s p e c i f i e d m i n i m u multimate tensile strength of the pre-stressing steel
determination should be done for every jack)
rust, dirt, oil, mud…
strands
- S t r e s s i n g s h a l l b e a c c o m p l i s h e d b y s i n g l e s t r a n d s t r e s s i n g T h e a m o u n t o fstress to be given each strand shall be as shown in the calculation which the
contractor proposed and the Engineer approved
girder with the following sequence
Order of pre- stressing of Super T girder type 38.3m (44 strands):
38 37
39 26
35 36 34
23 24 22
32 33 31
20 21 19
11 10
8 9 7
18 6
Trang 14Order of pre- stressing of Super T girder type 34.3m (35 strand):
20 21 19
11 10
8 9 7
18 6
2322
20 2119
1110
8 97
186
Pk, marking on ends of strands to measure elongation
Trang 15 Tensioning with each force level 0.2; 0.4; 0.6; 0.8; 1 Pk.
both of ends
e) Installing Inner Formwork:
oil which the contractor uses is Sika Separol and It was approved by consultant
lifted by gantry crane and shall be installed inside casting bed
girder web, using tie steel to hold PCV tube on positions which are marked
f) Casting Concrete:
Trang 16 Preparation of Concrete Casting:
- B e f o r e c a s t i n g c o n c r e t e g i r d e r , u s i n g P V C D 1 7 0 t u b e s t o m a k e d r a i n a g e
w a i t i n g - h o l e o f b r i d g e s u r f a c e a t p o s i t i o n s w h i c h a r e m a r k e d o n t h e g i r d e rflange of exterior girder
prepared and checked carefully
openings of forms shall be sealed to prevent leakage concrete
Casting Concrete:
- C h e c k i n g t h e t e m p e r a t u r e a n d s l u m p o f c o n c r e t e C o n c r e t e , w h e n t h i s i splaced, shall have a temperature is satisfied in according to the specification
reinforcing bars and from drying ahead of the final covering with concrete
meters
and make the good connection between layers Proposal layer heights mightbe: layer 1 to layer 5 with 30cm and layer 6 with 25cm
- E x t e r n a l v i b r a t o r s h a l l b e s e t u p o u t s i d e o u t f o r m T h e n u m b e r o f v i b r a t o r sused shall be sufficient to consolidate the concrete properly within 30 minutes
after it is deposited in the forms
down, no air, bubble, surface leveled and no mortar exposed
t h a t t i m e s h a l l b e l e s s t h a n i n i t i a l s e t t i n g t i m e o f l e s s t h a n t i m e f o r r e compaction of previously cast layer
concrete area shall covered in order to ensure the quality of concrete
immediat e adj ustment sh all be don e t o re posit ion t he forms b efore concret eplacing keep on
- A p p o i n t s o m e p e r s o n s c o n t r o l o p e r a t i o n o f v i b r a t o r s o u t s i d e a c c o r d i n g t oconcreting position, avoiding activation of vibrator at positions which concrete
was cure
Trang 17- Vibrators system is operated following each compartments of outer formwork,
l ay e r by l a ye r w e ca rry ou t c om pa ct by R ee d l ey vi b ra t o r t h en u si n g vi b rat or
f r o m 1 0 - 1 5 s P r o c e s s i n g s e q u e n t i a l l y l a y e r b y l a y e r a n d f o l l o w i n g e a c hcompartments of outer formwork
increase temperature of concrete in waiting process
casting concrete
- O n c e c o m p l e t i o n o f c o n c r e t e p o u r i n g a n d c o n c r e t e i n i n i t i a l s e t t i n g t i m e i f
then leveling 2nd time for smoothly and make roughness
Q = 5 Ton
Mixtruck
ConcreteBucket No.1
Gantry crane
5 Tons
Gantry crane 5T
Concrete
Gantry crane 5T
Concrete bucket no.2 Moving
Trang 1876
98
1110
1312
141
32
54
76
98
111013
g) Curing and Removal of Inner Formwork:
Curing Concrete:
- A f t e r c a s t i n g c o n c r e t e , w e n e e d p r e v e n t a f f e c t s o f f o r c e s o u t s i d e o n g i r d e r
w h e n g i r d e r c o n c r e t e s t r e n g t h h a s n o t r e a c h e d 8 5 % o f d e s i g n s t r e n g t h ,especially positions on the girder flange
hours
- A f t e r c a s t i n g c o n c r e t e p r o c e s s m a k e r o u g h b y b l o w s i k a d u r a n d u s e s t e e lbesom to cleaning surface
All preparation of curing works must be checked carefully
- T e m p e r a t u r e o f c u r i n g s h a l l b e c a l c u l a t e d c a r e f u l l y f o r c o n c r e t e t o r e a c hrequired strength fast and don’t make bad impact to concrete
Removal of Inner Formworks:
- U s i n g h y d r a u l i c j a c k f o r m o v a b l e o f i n n e r f o r m t o s e p a r a t e i n n e r f o r m a n d
g i r d e r , t h e n u s i n g g a n t r y c r a n e t o l i f t c o r e o f i n n e r f o r m o u t o f g i r d e r I n
o p e r a t i o n w e n e e d p r o c e s s i t v e r y c a r e f u l l y a n d l i g h t l y t o p r e v e n t i m p a c tbetween inner form and girder
Trang 19Removal bolt for PC bar
Casting bed
Inner form
Lifting
Support frame
cast super-T girder
- E x p o s e d s u r f a c e o f g i r d e r ( t o p s u r f a c e o f g i r d e r ) s h a l l b e c o v e r e d b y w e tburlaps immediately after final finishing of concrete surface
Trang 201900 975
have a signal man by using horn
center of girders with the following sequence:
Order of cutting tendons of Super T girder type 38.3m (44 strands):
35 3634
23 2422
32 3331
20 2119
1110
8 97
186
Trang 2120 2119
1110
8 97
186
2322
20 2119
1110
8 97
186
28
24
Trang 22 Measuring p ore-cambert t s o g n a he l op urfacec l o f irder long ongitudinal entre ine f
g i r d e r a f t e r f i n i s h i n g o f c u t t i n g o f t h e s t r a n d s M a r k i n g a t c e n t r e o f b e a r i n g a n dcentre of to monitor the pre-camber Checking the pre-camber at these positions
before and after cutting the strands
shall be covered by Sikadur 731
i) Lifting Girder to Stock Yard:
28-days strength
gantry crane
with slowly speed
agreement of engineer
of casting by using templates
D19 rebar to support and connect girder as drawing:
SUPER - T
wood plate 1200X100X50mm
TUMBUCKLET
C h e c k i n g s t a b i l i t y o f f o u n d a t i o n u n d e r t e m p o r a r y b e a r i n g o f s u p e r T g i r d e r
regularly
No Fabrication yard Quantity Remark
Trang 231 Fabrication yard no.1.1 38 1 layer
j) Filling the bonding mortar.
particles
ends of girder
2) Cycle Time of Super-T Girders Fabrication:
Installation of rebar and PC cable, tensioning(IR)
0.5 day
Trang 247 Schedule for Production of Super T Girder
8 Quality Control:
Q C E n g i n e e r / S i t e e n g i n e e r s h a l l i n s p e c t a l l w o r k s t o e n s u r e c o m p l i a n c e t o t h erequirement of Construction Scheme
A l l m a t e r i a l s h a l l c o m p l y w i t h a l l r e q u i r e m e n t s i n t h e S p e c i f i c a t i o n ; r e f e r t o a t t a c h e d
Inspection and Test Plan on Appendix 14 and Inspection sheet form on Appendix 15
T h e t o l e r a n c e s l i s t e d i n T a b l e 1 a r e t h e a l l o w a b l e d e v i a t i o n s f o r p r e - s t r e s s e d c o n c r e t e
structures These tolerances will be included in assessments for the acceptance of work
Acceptance Tolerances of Pre-stressed Super T Girder (Refer to S07450)
Tolerance
by contractor in construction process
Cutting Tendon and shifting (S)
Trang 25 Prior t s o otartings s wf ubt f tructurem s bork,i het a r ollowing atters hall e nformed o ll elatedstaffs working in the construction site to prevent any environmental pollution.
1) Site Organization Layout
m a i n t a i n a l l n e c e s s a r y b a r r i c a d e s , s u i t a b l e a n d s u f f i c i e n t l i g h t , d a n g e r s i g n a l a n d
o t h e r s i g n , p r o v i d e a s u f f i c i e n t n u m b e r o f w a t c h m e n a n d t a k e a l l n e c e s s a r y
precautions for the protection of the works and the safety of the public
keep the construction site dry and clean Do not let water stagnate on the pavement
or run into the foundation hole For construction sites which are adjacent to sea, river
or stream, there must be method to prevent flood and land slide
t h e e n d o f w i n d d i r e c t i o n t o e n s u r e t h e s a f e d i s t a n c e f r o m t h e s t a f f a n d w o r k e r
accommodation and residential area Otherwise, there must be method, according to
the current regulations of the Government, to prevent hazardous elements
W e l l s , t u n n e l s a n d h o l e s o n t h e g r o u n d a s w e l l a s i n t e r s t i c e s o n w o r k i n g p l a t f o r m
m u s t b e c o v e r e d o r h e d g e d w i t h m i n i m u m h e i g h t o f 1 m F o r d i t c h e s o r f o u n d a t i o n
h o l e s w h i c h l o c a t e s a d j a c e n t t o t r a f f i c r o a d s , t h e r e m u s t b e f e n c e w i t h m i n i m u m
height of 1m and sufficient lighting system at night
ground, without fence, warning signposts or guards, is strictly prohibited
Trang 26 I n t h e s t o r a g e a r e a f o r m a t e r i a l , f u e l , c o m p o n e n t a n d e q u i p m e n t , t h e r e m u s t b e
accesses The width of access must satisfy the size of handling and transporting
vehicles There must be aisles between material stacks with minimum width of 1m
the traffic roads, railways, crane ways
c l o s e d b a s k e t , s i l o o r b u n k e r … C o n c u r r e n t l y , t h e r e m u s t b e m e t h o d t o p r e v e n t
dust when handling material
L i q u i d m a t e r i a l ( p e t r o l , o i l , l u b r i c a n t … ) m u s t b e p r e s e r v e d i n s t o r a g e h o u s e
according to special regulations on fire prevention
1m Brick must be laid on the ground with maximum number of row of 25
(including lining pads)
m a x i m u m h e i g h t o f 2 5 m S t e e l p i l e o r c a s t - i r o n p i p e , w h o s e d i a m e t e r i s o v e r
3 0 0 m m , m u s t b e p i l e d u p a s l a y e r s w i t h m a x i m u m h e i g h t o f 1 2 m a n d s u p p o r t
method
Small-sized ones shall be placed on shelves with the same maximum height The weight
of steel placed on shelves must not exceed the safe load of shelves
a) Daily Safety Housekeeping Cycle
and not allowed to accumulate on site and checking of safety facilities at the end
of the day on daily basis before leaving the site, shall be performed by all workersand checked by their Site Engineers
Trang 27 T h e n i g h t s h i f t w o r k f o l l o w i n g t h e e a r l i e r d a y w o r k r e q u i r e s t h e c o n c l u d e d w o r k
done schedule with the daily safety duties carried out
b) Weekly Safety Housekeeping Cycle
p r e v i o u s w e e k c a r r i e d o u t a n d i t s a c t i v i t i e s w i t h t h e p l a n n e d s c h e d u l e f o r t h ecurrent week shall be informed to all staff and workers
C l e a n i n g o f w o r k p l a c e s b y a l l w o r k e r s s h a l l b e c a r r i e d o u t a f t e r t h e g r o u p
discussion on Saturday morning before the start of that day’s work
c) Monthly Safety Housekeeping Patrol /Cycle
E n g i n e e r s h a l l b e c a r r i e d o u t w i t h r e p o r t s p r e p a r e d b y t h e S a f e t y O f f i c e r f r o mthese patrols These reports shall be issued to all attendees at the Safety Patrols
and also to discuss any issues at the Daily Meeting for follow-up actions
T h e m o n t h l y p a t r o l s h a l l b e h e l d a t e n d o f e a c h m o n t h a s p a r t o f t h e m o n t h l y
s c h e d u l e m e e t i n g w h e r e b y d i s c u s s i o n o n s u g g e s t i o n s f o r a n y s i t e s a f e t y / w o r kschedule relating to the patrol can be taken into action for the following month
4) Working around Equipment / Machineries
accidentally knocked/hit workers working too close to them If such situation arises,
the followings must be observed:
within close vicinity of machineries Site Engineer should inform such requirements to
the workers and operators of machineries
safety or relief valves and pressure gauges
OF SERVICE”, “DO NOT USE” Use of such unsafe equipment is prohibited
P r e s s u r i z e d e q u i p m e n t s h a l l b e o p e r a t e d a n d m a i n t a i n e d o n l y b y q u a l i f i e d a n d
authorized personnel