Progress Update Nr... Programme Update - ITSFor Period : Mon 26th October – Friday 6th October - Completed excavations, reinforcement and formwork to perimeter retaining walls - Complete
Trang 2Progress Update (Nr 4)
Trang 3Programme Update - ITS
For Period : Mon 26th October – Friday 6th October
- Completed excavations, reinforcement and formwork to perimeter retaining walls
- Completed installation of reinforcement to basement slab and concrete pour
- Commenced installation of holding down bolts in preparation for steelwork
- Completed internal damp-proofing works to basement walls
- Commenced internal builders work and the removal of remaining load bearing walls: including installing necessary concrete lintels
- Continue first fix mechanical and electrical works within existing building to all floors
Trang 4Progress Photos – External
Basement floor slab & lift pit concrete pour complete
Trang 5Progress Photos – External
Retaining wall steelwork reinforcement installed throughout perimeter walls
Trang 6Progress Photos – External
Retaining wall formwork/shuttering installed and also
temporary props positioned
in preparation for next phase concrete pour
Trang 7Progress Photos – Internal
First fix mechanical and electrical works continued within the existing building through all floors
Trang 8Progress Photos – Internal
Internal structural builderswork ongoing including installation of load bearing lintels
Trang 9Progress Photos – Internal
Commenced infill of new plasterboard ceilings to rooms and corridors
throughout floors
Trang 10Next Few Weeks………
A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and pad foundations
- Complete concrete pours to perimeter retaining walls
- Commence ‘making good’ to walls within rooms of existing building
- Commence self level screeding and preparatory overboarding to existing sub-floors
- Continue internal builders work; including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors