Progress Update Nr... Programme Update - ITSFor Period : Mon 26th October – Friday 6th October - Completed excavations, reinforcement and formwork to perimeter retaining walls - Complete

Trang 2

Progress Update (Nr 4)

Trang 3

Programme Update - ITS

For Period : Mon 26th October – Friday 6th October

- Completed excavations, reinforcement and formwork to perimeter retaining walls

- Completed installation of reinforcement to basement slab and concrete pour

- Commenced installation of holding down bolts in preparation for steelwork

- Completed internal damp-proofing works to basement walls

- Commenced internal builders work and the removal of remaining load bearing walls: including installing necessary concrete lintels

- Continue first fix mechanical and electrical works within existing building to all floors

Trang 4

Progress Photos – External

Basement floor slab & lift pit concrete pour complete

Trang 5

Progress Photos – External

Retaining wall steelwork reinforcement installed throughout perimeter walls

Trang 6

Progress Photos – External

Retaining wall formwork/shuttering installed and also

temporary props positioned

in preparation for next phase concrete pour

Trang 7

Progress Photos – Internal

First fix mechanical and electrical works continued within the existing building through all floors

Trang 8

Progress Photos – Internal

Internal structural builderswork ongoing including installation of load bearing lintels

Trang 9

Progress Photos – Internal

Commenced infill of new plasterboard ceilings to rooms and corridors

throughout floors

Trang 10

Next Few Weeks………

A look ahead to works commencing within the next 2 weeks :

- Complete excavations to new ground floor slab and pad foundations

- Complete concrete pours to perimeter retaining walls

- Commence ‘making good’ to walls within rooms of existing building

- Commence self level screeding and preparatory overboarding to existing sub-floors

- Continue internal builders work; including installing required lintels and steelwork

- Continue first fix mechanical and electrical works within existing building to all floors