Programme Update - ITSFor Period : Mon 9th November – Friday 20th November - Completed reduced level dig to to new ground floor slab and pad foundations - Completed concrete pours to per

Trang 1

Progress Update (Nr 5)

Trang 2

Programme Update - ITS

For Period : Mon 9th November – Friday 20th November

- Completed reduced level dig to to new ground floor slab and pad foundations

- Completed concrete pours to perimeter retaining walls and stripped formwork

- Commenced ‘making good’ to walls within rooms of existing building

- Completed self level screeding and preparatory overboarding to existing sub-floors

- Continued internal builders work; including installing required lintels and steelwork

- Continued first fix mechanical and electrical works within existing building to all floors

Trang 3

Progress Photos – External

Basement retaining walls poured and formwork

stripped

Trang 4

Progress Photos – External

Bolt boxes made and cast in preparation for steelwork installation

Trang 5

Progress Photos – External

Pad foundations excavated and DPM/reinforcement installed prior to concrete pour

Trang 6

Progress Photos – Internal

First fix mechanical and electrical works continued within the existing building through all floors

Trang 7

Progress Photos – Internal

Temporary propping system installed to facilitate

installation of internal load bearing steelwork

Trang 8

Progress Photos – Internal

Continued infill of new plasterboard ceilings to rooms throughout floors within existing building

Trang 9

Progress Photos – Internal

Completed overboarding

of existing sub floors to rooms throughout

Trang 10

Progress Photos – Internal

Commenced ‘making good’

to rooms within existing building including wallpaper strip and localised filling of holes etc

Trang 11

Next Few Weeks………

A look ahead to works commencing within the next 2 weeks :

- Complete concrete pour to pad foundations

- Complete external drainage works including new manhole and channel drainage

- Backfill and compact surrounding areas with Type 1 stone

- Commence external steelwork installation

- Continue overboarding existing ceilings to all floors within existing building

- Complete internal builders work; including installing required lintels and steelwork

- Continue first fix mechanical and electrical works within existing building to all floors