Programme Update - ITSFor Period : Mon 9th November – Friday 20th November - Completed reduced level dig to to new ground floor slab and pad foundations - Completed concrete pours to per
Trang 1Progress Update (Nr 5)
Trang 2Programme Update - ITS
For Period : Mon 9th November – Friday 20th November
- Completed reduced level dig to to new ground floor slab and pad foundations
- Completed concrete pours to perimeter retaining walls and stripped formwork
- Commenced ‘making good’ to walls within rooms of existing building
- Completed self level screeding and preparatory overboarding to existing sub-floors
- Continued internal builders work; including installing required lintels and steelwork
- Continued first fix mechanical and electrical works within existing building to all floors
Trang 3Progress Photos – External
Basement retaining walls poured and formwork
stripped
Trang 4Progress Photos – External
Bolt boxes made and cast in preparation for steelwork installation
Trang 5Progress Photos – External
Pad foundations excavated and DPM/reinforcement installed prior to concrete pour
Trang 6Progress Photos – Internal
First fix mechanical and electrical works continued within the existing building through all floors
Trang 7Progress Photos – Internal
Temporary propping system installed to facilitate
installation of internal load bearing steelwork
Trang 8Progress Photos – Internal
Continued infill of new plasterboard ceilings to rooms throughout floors within existing building
Trang 9Progress Photos – Internal
Completed overboarding
of existing sub floors to rooms throughout
Trang 10Progress Photos – Internal
Commenced ‘making good’
to rooms within existing building including wallpaper strip and localised filling of holes etc
Trang 11Next Few Weeks………
A look ahead to works commencing within the next 2 weeks :
- Complete concrete pour to pad foundations
- Complete external drainage works including new manhole and channel drainage
- Backfill and compact surrounding areas with Type 1 stone
- Commence external steelwork installation
- Continue overboarding existing ceilings to all floors within existing building
- Complete internal builders work; including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors