Project planning tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất cả các lĩnh vực kinh tế, ki...
Trang 1Lecture-4
Trang 21 Introduction
2 Objectives of Project Appraisal
3 Scope of Project Appraisal
4 Methods of Calculating Profit Worthiness
5 Formula for
6 Acceptability Criteria
7 The basic Difference between Financial
Appraisal & Economic Appraisal
8 Types of Project Appraisal
9 Conclusion
Trang 31.1 Project Appraisal: Pre-Investment
Analysis/Ex-ante Analysis.
1.2 Project Evaluation: Post-Implementation
Analysis/ Ex-post Analysis.
1 Introduction:
Trang 4Project Appraisal
1.3 Project Appraisal involves comparison of costs and
benefits If benefits exceeds costs, the project could be considered for acceptance.
1.4 The basic principle in appraisal / CBA is for potential
acceptance of a project
1.5 Project Appraisal means a pre-investment analysis of a
project to determine whether the project should be implemented or not.
Trang 5resources or means are Limited as compared to the needs of the society
depriving other projects resources
decision so that scarce resources are utilized in the best possible ways.
project, the decision making authority must convince itself that the proposed project is the best and most economical way of achieving the desired objective (socio-economic benefits).
to appraise each project very minutely from different angles
(Cont.)
Trang 62.6 Project Appraisal involves detailed
pre-investment analysis of market & technical feasibility, financial soundness, economic desirability and, finally, measuring its investment worth.
2.7 The task aims mainly at ensuring that
scarce resources are put to most effective use
2.8 It requires the combined efforts of a team
of persons from various disciplines (engineers, financial analysts, economists etc.) working in close, co-ordination.
Trang 73 Scope of Project Appraisal
3.1 Market Feasibility study.
3.2 Technical Feasibility / viability.
3.3 Financial Soundness.
3.4 Management and Organizational
Aspects / Managerial Soundness 3.5 Economic viability / Appraisal.
3.6 Environmental Appraisal /
Viability
Trang 83.1 Market Feasibility
a) Whether sufficient demand does exist?
b) In case of import substitution whether domestic cost of
production is less than cost of import.
Trang 93.2 Technical Appraisal
a Availability of inputs at reasonable cost.
b Consistency & soundness of engineering
design.
c Economics of scale in production.
d Appropriate technology & alternative
ways of production.
e Advantageous Location of the project.
f Maintenance & Repairs.
g Provision for expansion.
h Balancing of equipment
Trang 103.3 Financial Soundness
b Sound capital structure: Fund Source
d Generation of sufficient cash flow to cover
debt-service Liability
g Break- Even Point
h Pay back period.
of Project’s Capital recovery It is defined as the
Length of time it takes to recover the initial
Trang 113.4 Managerial Soundness
a Experience of the top managerial
personnel in the line.
b Expertise and ability of
supervisory staff members.
c Balance between supervisory
staff and work forces
d Clarity of job description,
responsibility and
accountability
Trang 123.5 Environmental Aspects
The environmental impacts include –
a Ecological : Fisheries, Tree Plantation,
Wet Land / Wet Land Habitat, Forest.
b Physico- Chemical : Flood Control &
Drainage Erosion, Drainage, Congestion / Water Logging, Obstruction to waste water Flow, Soil Fertility, Early Flooding.
c Human Interest : Areas of Settlements,
Agricultural Lands, Navigation / Boat
Trang 133.6 Measurement of Investment Worthiness
a What benefit does the project promise for its sponsors or
owners?
a What benefit does the project promise for the national economy?
The satisfactory answers to these questions provide the prime test of a project’s acceptability.
Trang 144 Methods of Calculating Profit Worthiness.
4.1 Net Present Value = NPV
4.2 Benefit Cost Ratio = B/C Ratio
4.3 Internal Rate of Return = IRR
Trang 155 Formula for:
5.1 NPV = Discounted Total Benefits – Discounted Total
costs.
5.2 B/C Ratio = Discounted Total Benefits
Discounted Total costs
Trang 165.3 Formula for IRR:
NPV
3 IRR = LRD + LRD x ( HRD – LRD )
NPV - NPV LRD HRD
Where,
LRD = Lower Rate of Discount at which NPV is positive;
HRD = Higher Rate of Discount at which NPV is negative;
NPV = Net Present value at the Lower Rate of Discount;
LRD NPV = Net Present value at the Higher Rate of Discount.
HRD
What is IRR?
IRR = Internal Rate of Return is that rate of discount that
makes/ reduces the Net Present Value (NPV) of a project
Trang 17337.04 = 1.08
NPV at 25% = 312.32 – 317.12
= - 4.8 IRR = 15 + 28.4 × (25 -15)
28.4 – (- 4.8)
= 15 + 28.4 × 10
28.4 + 4.8
= 15 + 28.4× 10 33.2 = 15 + 8.55 = 23.55
IRR = 23.55%
Trang 197 The basic difference between Financial
Appraisal &Economic Appraisal
Trang 208 Types of Project Appraisal
8.1 Financial / commercial Appraisal
8.2 Economic Appraisal
8.3 Technical Appraisal
8.4 Social Appraisal
Trang 219 Conclusion:
selecting a project.
measure the different worthiness of a project
implementation.
principal decision making tools.
selection of a project