Framework for project preparation and appraisal tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về...
Trang 1Saeed Ahmed Rana
ADFD/WB Project Preparation and Appraisal Workshop Abu Dhabi, April 2010
Overall Framework
for Project Preparation and
Appraisal
Trang 2 This is an instrument to provide assistance to the billions in the developing world, who need to
overcome poverty and raise their standards of
living
socio-economic development of member countries.
use of their resources – natural, financial and
human – to alleviate poverty, protect the
environment and enhance effectiveness of public and private sectors.
Why A Project?
Trang 3Why project preparation and appraisal?
Project preparation and appraisal processes play an
important role in enhancing the developmental impact
of investments and building government capacity in national planning and investment
These processes are not intended to be document
driven but to bring together multiple perspectives on a project and various tools of analysis needed to assess,
monitor and improve on the different activities and
expenditure components involved in the project
A strong foundation of preparation and appraisal can
ensure better performance and disbursement during the life of the project and is the primary framework for
conducting project supervision and monitoring
3
Trang 4A Framework for Project Preparation
and Appraisal
I Project Cycle
II Project Rationale and Preparation
III Borrower Roles
IV Donor Roles
V Project Appraisal
Costing Analysis
Environmental and Social Assessments
VI Assessing Project Quality
VII Early Signs of Project Failure
Trang 5The Bank Project Cycle
Project Cycle - The project cycle starts with a development strategy based on selectivity and comparative advantage
It is targeted to country’s development objectives It is
followed by:
Identification
Preparation
Appraisal
Negotiations and Approval
Implementation and Supervision
Completion and
Evaluation
5
Trang 6Stages of the Bank’s Project Cycle (I)
Country Assistance Strategy-the Bank proposes lending and advisory services to help countries identify their
priorities and reach their main development goals.
Identification-Projects are identified that support country strategies and that are financially, economically, socially and environmentally sound
Preparation-The Bank provides policy and project advice along with financial assistance Clients conduct studies and prepare final project documentation.
Appraisal-The Bank appraises the economic, technical, institutional, financial, environmental and social aspects of the project The project appraisal document and draft
legal agreements are prepared.
Trang 7Stages of the Bank’s Project Cycle (II)
Negotiation and Board Approval-The Bank and Borrower agree on loan or credit agreement and the project is
presented to the Board for approval.
Implementation and Supervision-The Borrower
implements the project The Bank ensures that the loan proceeds are used for the loan purposes with due regard for economy, efficiency and effectiveness.
Implementation and Completion-The Bank team evaluates the performance of both the Bank and Borrower.
Evaluation-The Bank’s Independent Operations Evaluation Department prepares an audit report and evaluates the
project Analysis is used for future project design.
7
Trang 8Project/Lending Types
Development Projects can be original projects, pilot projects or repeater
projects
Pilot projects test the design criteria and implementation strategy of new
technologies before embarking upon a full scale investment
Repeater projects adopt the design and practices of a successful project for the
same Project Development Objective (PDO) under similar implementation
conditions and environments
A SWAp is a sectorwide approach that supports locally owned programs for a particular sector in a comprehensive and coordinated manner
SWAps promote increasing reliance on country systems and procedures and use a common framework for planning, implementation, expenditure, and monitoring and evaluation
Project Lending is primarily the Specific Investment type Loan (SIL) Lending is
also extended for sector investment, maintenance, financial-intermediary and technical assistance projects
Trang 9Project Identification
Birth of a Project
Country Development Plans
Borrower Specific Request
Unforeseen Conditions (e.g natural calamities)
Set Project Development Objectives
Trang 10Project Development Objective Guidelines
What group is targeted directly by the project as the key recipient of project
The PDO should not merely restate the project’s components or outputs
Efficient use of inputs or delivery of outputs must be translated into outcomes or results for the primary target group
KISS Your PDO (Keep – It – Short - and - Simple), concise and meaningful
Don’t try to reach the sky in one go
PDO should not encompass higher level objectives that depend on other efforts beyond the scope of the project
Trang 11Strategic Areas of Focus for the Bank
Country capacity building
Measuring and reporting on results
Trang 12Achieving Results
on the Ground
Measuring and Reporting on Results
Enabling Environment
Country Capacity
Building MfDR
Bank’s Communication/Messaging on Results
Harmonization with MDBs/Donors
• Senior Manageme
nt attention
• Recognition
• Tools, IT systems,
RX Platform, CPRT
• Training, KL
• Resources
Trang 13Project Preparation - Borrower Role
Review identification and results
Initiate project preparation
Identify/set institutional framework
Determine need for TA
Set up project preparation office
Appoint project consultants
Inter-agency/departmental coordination
Prepare a Project Information Paper (PInfP)
Approach donors 13
Trang 14Project Preparation - Donor Role
Assign project preparation team
Review borrower progress in project identification/preparation
Identify shortcomings and suggest actions to complete
Review alternative designs and justification for the selected design
Prepare Interim Information document (PID) based on PinfP
Set up peer reviewers
Review consultant’s progress and propose strengthening, if needed
Discussions
Borrower
Stakeholders
Potential donors
Trang 15Sustainability Considerations At Preparation
Post project needs
Follow-up to sustain benefits
Are beneficiaries identified?
Are they organized?
Are they willing to participate in project activities?
[Participation is important to ensure ownership and
sustainability.]
Any NGO participation?15
Trang 16Project Preparation
Update Project Information Document (PID)
Field visit to assess preparation progress
technical, economic, environment, social studies
Completion of feasibility studies
Discussions with probable/potential co-financiers
Prepare Project Implementation Plan (PIP)
Project components
Implementation plan
Monitoring and Evaluation (M&E) Arrangements
Prepare Project Operation Plan (POP)
Guidelines
Arrangements for effective project operation
Risk analysis and mitigation measures
Performance Indicators PI ( see next slide )
Trang 17Performance Indicators and Guidelines
17
Fewer is better Identify a limited set of indicators for the Project Development Objective (PDO)– both qualitative and quantitative
However, make sure that the selected indicators measure all PDO dimensions
Indicators should be S-M-A-R-T
Trang 18The Project Concept Note (PCN)
Draft and Circulate Project Concept Note [PCN] *hyperlink
Three to four page document
It focuses on project concept, not design
It is prepared soon after project identification before project preparation costs become substantial
Functions
Examine the strategic rationale for Bank involvement
Promote consideration of alternative project concepts
Seek a go/no-go decision from the Country Director
Obtain early guidance/agreement on issues and approaches
Flag risks and potential mitigation measures
Seek early guidance on potential safeguard issues, consultation and
disclosure
Agree on a resourced estimate, schedule and team [See PCN Template 1]
Trang 19Sample PCN Cover Sheet
19
Trang 20Preparation Completed
Quality Enhancement Review (QER)
Consistency of design with approved project concept
Quality assurance of the technical aspects of the project
Establish fiduciary (Financial Management and Procurement) requirements that need to be met by appraisal
Review safeguards needed and specify project’s environmental and safeguard classifications and the requirements to be met by appraisal.
Review project feasibility and sustainability aspects
Propose actions to update PCN
At Preparation stage all technical economic financial institutional social environmental M&E O&M aspects must be fully analyzed with viable options presented
PCN review
Discussion at management Level
Follow up on PCN review and finalize PCN
Obtain management’s authorization for project appraisal.
Trang 21 Finalize appraisal arrangements
Assign appraisal mission members
Ensure all subject matter specialists are included
Preferably Bank regular staff – consultants only in specialized areas
Ensure staff continuity until mission accomplished
Draft Project Appraisal Document
21
Trang 22Pre-Mission Actions
Critical elements of PAD are:
Country background
Sector background
Project Development Objectives (PDO) Project
Design (Tech Institutional, Financial, Social,
Environmental, Procurement, M&E)
Project cost and financing
Project analysis (economic, financial)
Implementation arrangements (PIM, Institutional etc.)
Sustainability consideration
Trang 23PAD Cover Sheet (1)
23
Trang 24PAD Cover Sheet (2)
Trang 25Pre-Mission Actions (Contd.)
Prepare issues paper
Explain unresolved issues and proposed solutions
Hold decision meeting
Seek managerial guidance on unresolved issues
[Note: Above two steps may be combined with
activities under PCN Review]
Finalize appraisal arrangements with the
government, borrower and co-financiers, if any.
Prepare mission TOR
25
Trang 26Appraisal Mission Field Activities
Field check design assumptions
Ensure that all information in the draft PAD is correct – make changes
as necessary to make it a factual document
Reach agreement with the government/borrower on all project aspects
Agree on holding Medium Term Review (MTR) in due course
Prepare an aide memoire summarizing main findings and
understanding reached by the mission, mainly on:
Trang 27Field Mission Completed
Confirm Aide Memoire (AM) findings and
agreements with the government/borrower
27
Trang 28Inputs:
Outputs &
Strategy &
Country/ SectorLong termOutcomes
Eg:
MDGs etc
Managing for Results:
The Results Chain
Doing right things?
Doing them right?
GettingDesired Results?
Lasting Impact?
Time
Level
Learning loop: evaluation
Trang 29Results Framework (RF)
RF is the program logic that
explains how (PDO) is to be
achieved
It links PDO, outputs,
outcomes to be delivered and
indicators used to verify
during implementation for day
to day management and
evaluation of project progress
near the end for overall project
evaluation and feedback.
29
Trang 30Example of Results Framework
Trang 31Post-Mission Activities
conditionality to the government/borrower
memoire
Negotiations
Board approval
Loan agreement signing
Project launch workshop
31
Trang 32Assessing Project Quality
A checklist of commonly found deficiencies
in project preparation is given in the next
A second look at these issues would
determine, among others, if post-appraisal work is needed.
Trang 33Checklist of General Deficiencies in Project
Preparation
33
Overambitious and non achievable Project Development Objectives (PDO)
Project design not fully relevant to PDO
Project implementation period is not long enough
Mismatch with country context
Inflexibility in project design
Complexity of project design compared to absorptive capacity of the
government, including project cost and post project activities
Inadequate M&E arrangements
Weak governmental institutions
Poor risk analysis
Lack of beneficiary participation
Weak ownership by the government
Weak sustainability analysis
Trang 34Early Signs of Project Failure
and signing of the loan agreement, the appraisal team signs off with mission accomplished satisfaction and the ball bounces to the implementation court
equally important for the parties concerned
carefully monitored
Trang 35Early Signs of Project Failure
35
legal requirements] An initial test of the recipient’s
commitment to the project objectives
implementation unit (PIU)
venue to straighten out financial, procurement and
startup issues
the conditionality package including funding
project objectives
Trang 36Some Examples of Project Experience
Republic of Yemen (RoY) Case
General Background
US$1.7 billion and has provided substantial
technical and analytical support
presented in the following slides
Trang 37Taiz: Municipal Development and
Flood Protection
PDO
Protect city residents, businesses and infrastructure from seasonal flash flooding
Capacity development of Taiz local government
Support for Yemen Decentralization Program
Original 4-year time frame was too ambitious; had to be extended
However, in view of satisfactory implementation Bank approved additional financing for enlarged scope.
37
Trang 38Third Public Works Project
PDO
Provide needed infrastructure to improve services and environmental conditions
Creation of short term employment
Community involvement in project selection, preparation and implementation
Development of local contracting and consulting business
Strength
Well designed Repeater Project
Clear objectives applying lessons from previous projects
Strong government support
PMU gained experience and responded to implementation issues (e.g unexpected events such as sharply increasing costs of construction materials)
Weakness
No major weakness Presents a good model for Repeater Projects and Pilots.
Trang 39Groundwater and Soil Conservation Project
PDO
Improve groundwater conservation in farming areas and increasing surface water availability
Improve water use efficiency
Improve recharge and protection of watersheds
Support groundwater management framework and institutions
Strength
PDOs are strategically strong but not fully supported by project design
Project pursued needed policy objectives (increasing fuel price and reducing
subsidy)
Institutional strengthening e.g IAS Fed of WUAs, quality control and agreement with beneficiaries on water usage
Weakness
M&E design – inappropriate indicators
Weak project consultants (funded by other agency with no Bank control)
39
Trang 40Second Rural Access Project
PDO
Reduce isolation of poor rural people by giving them better access to markets and services
Strength
Result framework is well designed
PDO very relevant to government’s Poverty Reduction Strategy Paper (PRSP)
Provides impetus to sound institutional framework
Weakness
Beneficiary participation low
Poor preparation – premature Board presentation - first year’s design not ready
Weak risk analysis - particularly related to benefits to minorities who are the main beneficiaries - elite capture prospects