Project appraisal tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất cả các lĩnh vực kinh tế, k...
Trang 1Project Ka Bazigaar
1
Trang 2Project Appraisal By-Rahul Jain
Trang 4What is Project Appraisal?
Analysis of potential projects.
Long-term decisions; involve large expenditures.
Very important to firm’s future.
Trang 5Steps in Project Appraisal
Estimate cash flows (inflows & outflows).
Determine r = WACC for project.
Evaluate cash flows.
Trang 6Cash Flow Estimation Of Project
Terminal Cash flow
Annual Cash Flows Initial
outlay
Trang 7Cash Flows Versus Profit
Cash flow is not the same thing as profit, at least, for two reasons:
First, profit, as measured by an accountant, is
based on accrual concept.
Second, for computing profit, expenditures
are arbitrarily divided into revenue and
capital expenditures.
7
CF (REV EXP DEP) DEP CAPEX
CF Profit DEP CAPEX
Trang 8Components of Cash Flows
Initial Investment
Net Cash Flows/Annual Cash Flows
Revenues and Expenses
Depreciation and Taxes
Change in Net Working Capital
Change in accounts receivable
Change in inventory
Change in accounts payable
Change in Capital Expenditure
Free Cash Flows
8
Trang 9Components of Cash Flows
Terminal Cash Flows
Salvage Value
Salvage value of the new asset
Salvage value of the existing asset now
Salvage value of the existing asset at the end of its normal
Tax effect of salvage value
Release of Net Working Capital
9
Trang 10Depreciation for Tax Purposes
Two most popular methods of charging
depreciation are:
Straight-line
Diminishing balance or written-down value
(WDV) methods.
For reporting to the shareholders, companies
in India could charge depreciation either on
the straight-line or the written-down value
basis
For the tax purposes, depreciation is
computed on the written down value (WDV) of the block of assets.
10
Trang 11Terminal Value for a New Business
The terminal value included the salvage value of the asset and the release of the working capital.
Managers make assumption of horizon period because detailed calculations for a long period become quite intricate The financial analysis of such projects should incorporate an estimate of the value of cash flows after the horizon period without involving detailed calculations.
A simple method of estimating the terminal
value at the end of the horizon period is to
employ the following formula, which is a
variation of the dividend—growth model:
Trang 12Additional Aspects of Cash Flow Analysis
Opportunity Costs of Resources
Trang 13Case Study
Warehouse Case
Trang 14There is nothing like
FREE LUNCH
Trang 15Cost of Capital
The project’s cost of capital is the
minimum required rate of return on funds committed to the project, which depends
on the riskiness of its cash flows
The firm’s cost of capital will be the
overall, or average, required rate of return
on the aggregate of investment projects.
15
Trang 16The Concept of the Opportunity Cost of Capital
The opportunity cost is the rate of return
foregone on the next best alternative
investment opportunity of comparable risk
. Government bonds. Risk-free security
Trang 17The Weighted Average Cost of Capital
The following steps are involved for
calculating the firm’s WACC:
Calculate the cost of specific sources of
funds
Multiply the cost of each source by its
proportion in the capital structure.
Add the weighted component costs to get the WACC.
WACC is in fact the weighted marginal cost of
capital (WMCC); that is, the weighted average
cost of new capital given the firm’s target
capital structure.
Trang 18Cost of Equity Capital
Cost of Equity: The Dividend—Growth
Model
1 0
Trang 20 Cost of capital (WACC)=
(Cost of Equity x Proportion of equity from capital)+ (Cost of debt x Proportion of debt from capital)+
Trang 21The number of years required to recover a project’s cost,
or how long does it take to get the business’s money back?
Trang 222.4
Trang 23=
Trang 24Strengths of Payback:
1 Provides an indication of a
project’s risk and liquidity.
2 Easy to calculate and understand.
Weaknesses of Payback:
1 Ignores the TVM.
2 Ignores CFs occurring after the
payback period.
Trang 2510 60 80
CF t
Cumulative -100 -90.91 -41.32 18.79 Discounted
Trang 26 1 .
0
t t n
Trang 28NPV = PV inflows - Cost
= Net gain in wealth.
Accept project if NPV > 0.
Choose between mutually
exclusive projects on basis of higher NPV Adds most value.
Trang 29Using NPV method, which
franchise(s) should be accepted?
If Franchise S and L are mutually
exclusive, accept S because NPVs >
NPVL .
If S & L are independent, accept
both; NPV > 0.
Trang 300 1 2 3
IRR is the discount rate that forces
PV inflows = cost This is the same
as forcing NPV = 0.
Trang 311 .
0
NPV r
CF
t t n
NPV: Enter r, solve for NPV.
IRR: Enter NPV = 0, solve for IRR.
Trang 33If IRR > WACC, then the project’s rate of return is greater than its
cost some return is left over to
boost stockholders’ returns.
Example: WACC = 10%, IRR = 15%.
Profitable.
Trang 34Cost (negative CF) followed by a series of positive cash inflows One change of signs.
Nonnormal Cash Flow Project:
Two or more changes of signs Most common: Cost (negative CF), then string of positive CFs, then cost to close project.
Nuclear power plant, strip mine.
Trang 35Inflow (+) or Outflow (-) in Year
Trang 36Individual Assignment
Complete All the questions