Development project appraisal for sustainable development tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài t...
Trang 1Development Project Appraisal for sustainable development
M A Kamal, Ph.D Director General National Academy for Planning and Development
Trang 26 Objectives of Project Appraisal
7 Scope of Project Appraisal
8 Methods of Calculating Profit Worthiness
Trang 31 Introduction:
1.1 Development projects impose a series of
communities or countries.
1.2 Those costs and benefits can be social,
environmental, or economic in nature, but may often involve all three.
1.3 Irrigation projects may facilitate the
growing of cash crops in one locality, but cause water shortages, and hence economic, social and environmental pressures in another locality
Trang 42 Definition: Project
2.1 A Project is a set of interrelated
investment activities to attain certain specific objectives by utilizing limited resources within a particular period of time.
Trang 53 Projects types:
Projects are:
3.1 Type ‘x’ : Self financing projects i.e projects which
earn revenue through sale of output (goods & services) These are called directly productive projects,
i.e Industrial Projects
3.2 Type “y” : In directly productive but non-revenue
earning projects, i.e., projects which give rise to tangible output, benefit of which do not accrue directly to projects themselves but to other parties Example: Irrigation Projects, Roads, Bridge etc
3.3 Type “z” : Service Sector Projects Projects which do not
give rise to tangible output but provide service benefits
to the society
Trang 64 Projects Cycle
4.1 There tends to be a natural sequence in the way
projects are planned and carried out and this sequence has come to be known as ‘ the Project Cycle’
4.2 Project Cycle Covers following stages:
I Project Identification.
II Project Preparation & Analysis III Project Approval / Negotiation
IV Project Appraisal
V Project Implementation & Monitoring
VI Project Evaluation & Follow-up Analysis.
4.3 A Project generally goes through all these phases
sequentially from identification to evaluation & follow-up This sequence has come to be termed or referred to as
“Project Cycle”
Trang 85 Project Appraisal
costs and benefits If benefits exceeds costs, the project could be considered for acceptance Otherwise, it is not.
5.2 The basic principle in appraisal / CBA is for
potential acceptance of a project
analysis of a project to determine whether the project should be implemented or not.
Trang 96 Objectives of Project Appraisal
6.1 Project Appraisal is necessitated because the resources or
means are limited as compared to the needs of the society
6.2 As a result, any investment undertaken implies depriving
other projects resources
6.3 Hence, it is very important to appraise each project before
investment decision so that scarce resources are utilized in the best possible ways.
6.4 In other words, before allocation of resources for a
particular project, the decision making authority must convince itself that the proposed project is the best and most economical way of achieving the desired objective (in terms of socio-economic benefits)
6.5 For this and for ensuring economic use of resources, we
have to appraise each project very minutely from different angles
Trang 106 Objectives of Project Appraisal
pre-investment analysis of market & technical feasibility, financial soundness, economic desirability and, finally, measuring its investment worth.
6.7 The task aims mainly at ensuring that scarce
resources are put to most effective use.
6.8 It requires the combined efforts of a team of
persons from various disciplines such as engineers, financial analysts, economists, etc
Trang 117 Scope of Project Appraisal
7.1 Market Feasibility study.
7.2 Technical Feasibility / viability.
7.3 Financial Soundness.
7.4 Management and Organizational
Aspects / Managerial Soundness.
7.5 Economic viability / Appraisal.
7.6 Environmental Appraisal / Viability
Trang 127.1 Market Feasibility
a) Whether does a sufficient demand
exist?
b) In case of import substitution,
whether the domestic cost of
production is less than the cost of
import.
Trang 137.2 Technical Appraisal
a Availability of inputs at reasonable cost.
b Consistency & soundness of engineering
design.
c Economics of scale in production.
d Appropriate technology & alternative ways of
production.
e Advantageous location of the project.
f Maintenance & Repairs.
g Provision for expansion.
h Balancing of equipment
Trang 147.3 Financial Soundness
a Exhaustive & realistic cost estimation
b Sound capital structure: Fund Source
c Provision for working capital requirement
d Generation of sufficient cash flows to cover
debt-service liability
e Generation of adequate profit
f Safety margin
g Break- Even Point
h Pay back period
Project’s Capital recovery It is defined as the length of time it takes to recover the initial investment of a
Trang 157.4 Managerial Soundness
a Experience of the top managerial
personnel in the line.
b Expertise and ability of supervisory
staff.
c Balance between supervisory staff
and workers
d Clarity of job description,
responsibility and accountability
Trang 167.5 Environmental Aspects
The environmental impacts include –
Land / Wet Land Habitats, Forests.
b Physico- Chemical : Flood Control & Drainage
Erosion, Drainage, Congestion / Water Logging, Obstruction to waste water Flow, Soil Fertility, Early Flooding.
c Human Interest : Areas of Settlements,
Communication, irrigation Facilities, Landscape,
Trang 177.6 Measurement of Investment Worthiness
its sponsors or owners?
the national economy?
questions provide the prime test of a project’s acceptability.
Trang 188 Methods of Calculating Profit Worthiness.
8.1 Net Present Value = NPV
8.2 Benefit Cost Ratio = B/C Ratio
8.3 Internal Rate of Return = IRR
Trang 198.1 Formula for:
i) NPV = Discounted Total Benefits – Discounted Total
costs
ii) B/C Ratio = Discounted Total Benefits
Discounted Total costs
Trang 208.3 Formula for IRR:
NPV
iii) IRR = LRD + LRD x ( HRD – LRD )
NPV - NPV LRD HRD Where,
LRD = Lower Rate of Discount at which NPV is positive;
HRD = Higher Rate of Discount at which NPV is negative;
NPV = Net Present value at the Lower Rate of Discount;
LRD NPV = Net Present value at the Higher Rate of Discount.
HRD
What is IRR?
IRR = Internal Rate of Return is that rate of discount
that makes/ reduces the Net Present Value
Trang 21Year Cost Benefit Discount
Factor at 15%
Discounted Cost DiscountedBenefit D.F at 25% Discounted Cost Discounted Benefit
337.04 = 1.08
NPV at 25% = 312.32 – 317.12
= - 4.8 IRR = 15 + 28.4 × (25 -15)
28.4 – (- 4.8)
= 15 + 28.4 × 10
28.4 + 4.8
= 15 + 28.4× 10 33.2 = 15 + 8.55 = 23.55
Trang 2311 The basic difference between Financial
Appraisal &Economic Appraisal
Financial Appraisal Economic Appraisal
a Profitability or worthiness of any
project is determined or judged
from the point of view of an
individual/ Entrepreneur
a Profitability/ viability or
worthiness of any project is determined or judged from the point of view of the society or nation as a whole
b Only direct cost and direct benefits
are considered while determining
the profitability of the project
b Include both direct and indirect
cost and benefits
c Cost and benefit are evaluated at
market prices
c Costs and benefits are
evaluated at shadow price/
Accounting price
d Use Market Rate of Discount d Use Social Rate of Discount
Trang 2412 Types of Project Appraisal
Trang 2513 Conclusion:
13.1 It involves comparison of costs and benefits
13.2 Objectives of a project Appraisal are needed because of
limited resources, allocation of resources, investment analysis, etc
13.3 It involves Market, Technical, Financial, Management,
Economic and Environment Feasibilities
13.4 It entails measurement of investment worthiness
13.5 Methods of calculation of profit worthiness is highly
essential
13.6 Acceptability criteria are needed
13.7 Differences between Financial and Economic Analysis's
and required
Trang 2614 Farewell Call:
14.1 There is a widespread concern that adverse
environmental effects of economic activities will seriously affect both the present and the future welfare of people in less developed countries, and that the present project
address the issues
14.2 It is necessary to use the idea of sustainable
development in project appraisal with the help of cost-benefit analysis methodology.