Essential formulae in project appraisal 2 tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất cả...
Trang 1Fin650:Project Appraisal
Lecture 3 Essential Formulae in Project Appraisal
Trang 2some are realized only for a temporary period
generate benefits later, Dams, entail
environmental costs long after their economic benefits have lapsed, A life lost now entails cost for at least as long into the future as the person would have lived
Trang 4Moving Money Through
Time
annual interest rates
in time is ‘compounded’, whilst money moved
backward in time is ‘discounted’
Trang 5Financial Calculations
Time value calculations in capital budgeting usually assume that interest is annually compounded
flows’: the symbol is:
Ct is Cash flow at end of period t
Trang 6Financial Calculations
The present value of a single sum is:
PV = FV (1 + r)-t
the present value of a dollar to be received at the end
of period t, using a discount rate of r
The present value of series of cash flows is:
Trang 7Financial Calculations:
Cash Flow Series
A payment series in which cash flows are Equally
sized and Equally timed is known as an annuity
There are four types:
1. Ordinary annuities; the cash flows occur at the
end of each time period (Workbook 5.10 and
5.11)
2 Annuities due; the cash flows occur at the start
of each time period
3 Deferred annuities; the first cash flow occurs
later than one time period into the future
(Workbook 5.10 and 5.11)
4 Perpetuities; the cash flows begin at the end of
the first period, and go on forever
Trang 8Evaluation of Project Cash Flows.
are assumed to occur regularly, at the end of
each year
Since they are unlikely to be equal, they will not
be annuities
other types of financing
All future flows are discounted to calculate a Net Present Value, NPV; or an Internal Rate of
Return, IRR
Trang 9Decision Making With
Cash Flow Evaluations
If the Net Present Value is positive, then the
project should be accepted The project will
increase the present wealth of the firm by the
NPV amount
If the IRR is greater than the required rate of
return, then the project should be accepted The IRR is a relative measure, and does not measure
an increase in the firm’s wealth
Trang 10Calculating NPV and IRR With Excel Basics.
correct signs: -$, +$, -Tk, +Tk etc
usually at the end of each year
decimal: e.g 15.6%, not 0.156
to ensure that the formulae have been correctly set up
Trang 11Calculating NPV and IRR With Excel The Excel
Worksheet
Trang 12entered into the formula: MIRR( B6:E6, B13, B14)
Payback – there is no Excel formula The payback
year can be found by inspection of accumulated
annual cash flows
Trang 13ARR and Other
Evaluations With Excel.
Average the annual accounting income by using the
‘AVERAGE’ function, and divide by the chosen asset
Trang 14Calculating Financial
Functions With Excel
Worksheet Errors.
Common worksheet errors are:
Cash flow cell range wrongly specified
Incorrect entry of interest rates
Incorrect cell referencing
Trang 15Calculating Financial
Functions With Excel
Error Control.
Methods to reduce errors:
Use Excel audit and tracking tools
Visually inspect the coding
Trang 16Essential Formulae
Summary
1.The Time Value of Money is a cornerstone of finance.
2 The amount, direction and timing of cash flows, and relevant
interest rates, must be carefully specified.
3 Knowledge of financial formulae is essential for project
evaluation.
4 NPV and IRR are the primary investment evaluation criteria.
5 Most financial functions can be automated within Excel.
6 Spreadsheet errors are common Error controls should be
employed.
7.To reduce spreadsheet errors: -document all spreadsheets, keep a
list of authors and a history of changes, use comments to guide later users and operators.
8 Financial formulae and spreadsheet operation can be demanding
Seek help when in doubt.
Trang 17Discounting Future Benefits
and Costs
Basic Concepts:
A Future Value Analysis
In general, the future value in one year of some amount X is given by:
FV= X(1+i)
where i is the annual rate of interest This is simple compounding
B Present Value Analysis
In general, if the prevailing interest rate is i, then the present value
of an amount Y received in one year is given by:
Discounting is the opposite of compounding.
i
Y PV
1
Trang 1818
Trang 19Discounting Future Benefits and
Costs
Net Present Value Analysis
The NPV of a project equals the difference between the present value
of benefits, PV(B), and the present value of the costs, PV(C):
NPV = PV(B)-PV(C)
Compounding and Discounting Over Multiple Years
Future value over multiple Years
In general, if an amount, denoted X, is invested for n years and
interest is compounded annually at i percent, then the future value is:
FV = X(1+i) n
Present value over multiple years
In general, the present value of an amount received in n years,
denoted Y, with interest discounted annually at rate i percent, then the
present value is:
The term 1/(1+i) n is called thei n discount factor
Y PV
) 1 (
Trang 2020
Trang 21Discounting and Alternative Investment Criteria
Basic Concepts:
A Discounting
Recognizes time value of money
a Funds when invested yield a return
b Future consumption worth less than present
o
r
Trang 22 All mutually exclusive projects need to be
compared as of same calendar year
If NPV = (B o-Co)(1+r) 1 +(B1-C1) + + +(B n-Cn)/(1+r) n-1 and
NPV = (B o-Co)(1+r) 3 +(B1-C1)(1+r) 2 +(B2-C2)(1+r)+(B 3-C3)+ (Bn-Cn)/(1+r) n-3
Then NPV = (1+r) 2 NPV
1 r 3
r
3
r 1r
Trang 231.1(
1440)
1.1(
350)
1.1(
3001
.1
2001000
NPV00.1 2 3 4
88
743)
1.1(
1440)
1.1(
3501
.1
300200
)1.1(1000NPV01.1 2 3
26
818)
1.1(
1440)
1.1(
350300
)1.1(200)
1.1(1000
Trang 24Alternative Investment
Criteria
Trang 25Net Present Value (NPV)
1 The NPV is the algebraic sum of the discounted values of the incremental expected positive and negative net cash flows over a project’s anticipated lifetime
2 What does net present value mean?
Measures the change in wealth created by the project.
If this sum is equal to zero, then investors can expect to recover their incremental investment and to earn a rate of return on their capital equal to the private cost of funds used to compute the present values.
Investors would be no further ahead with a zero-NPV project than they would have been if they had left the funds in the capital market
In this case there is no change in wealth.
Trang 26First Criterion: Net Present Value (NPV)
Use as a decision criterion to answer
following:
a When to reject projects?
b Select project (s) under a budget
constraint?
c Compare mutually exclusive projects?
d How to choose between highly profitable mutually exclusive projects with different lengths of life?
Alternative Investment
Criteria
Trang 27Net Present Value
Criterion
a When to Reject Projects?
Rule: “Do not accept any project unless it generates a positive
net present value when discounted by the opportunity cost of funds”
Examples:
Project A: Present Value Costs $1 million, NPV + $70,000
Project B: Present Value Costs $5 million, NPV - $50,000
Project C: Present Value Costs $2 million, NPV + $100,000
Project D: Present Value Costs $3 million, NPV - $25,000
Result:
Only projects A and C are acceptable The investor is made worse off if projects B and D are undertaken.
Trang 28Net Present Value Criterion (Cont’d)
b When You Have a Budget Constraint?
Rule: “Within the limit of a fixed budget, choose that subset of the
available projects which maximizes the net present value”
Example:
If budget constraint is $4 million and 4 projects with positive NPV:
Project E: Costs $1 million, NPV + $60,000
Project F: Costs $3 million, NPV + $400,000
Project G: Costs $2 million, NPV + $150,000
Project H: Costs $2 million, NPV + $225,000
Result:
Combinations FG and FH are impossible, as they cost too much EG and EH are within the budget, but are dominated by the
combination EF, which has a total NPV of $460,000 GH is also
possible, but its NPV of $375,000 is not as high as EF.
Trang 29c When You Need to Compare Mutually Exclusive
Projects?
Rule: “In a situation where there is no budget constraint but
a project must be chosen from mutually exclusive
alternatives, we should always choose the alternative that generates the largest net present value”
Example:
Assume that we must make a choice between the following three mutually exclusive projects:
Project I: PV costs $1.0 million, NPV $300,000
Project J: PV costs $4.0 million, NPV $700,000
Projects K: PV costs $1.5 million, NPV $600,000
Result:
Projects J should be chosen because it has the largest NPV
Net Present Value Criterion (Cont’d)
Trang 30Shortcut Methods for Calculating the Present Value of Annuities
Annuities and Perpetuities
An annuity is an equal, fixed amount received (or paid) each
year for a number of years.
A perpetuity is an annuity that continues indefinitely.
Present value of an annuity
or PV = A x
Where is the annuity factor,
The term , which equals the present value of an annuity of
$/Tk 1 per year for n years when the interest rate is i
percent, is called the annuity factor
1 ( 1 )
n i
a
i
i a
n n
a
n i
a
Trang 31 Present value of benefits (or costs) that grow or
decline at a constant rate in perpetuity
PV(B) = B1/ (1-g), if i>g
Trang 32For most long lived projects, select a relatively short discounting
period (useful life of the project) and include a terminal value to
reflect all subsequent benefits and costs.
Where T(k) denotes the terminal value.
)
( )
1 (
0
k
T i
NB NPV
Trang 33Alternative Methods for
Estimating Terminal Values
Terminal Values Based on:
Simple Projections
Salvage or Liquidation Value
Depreciated Value, economic depreciation
Percentage of Initial Constructions Cost
Setting the Terminal Value equal to zero
Note: Accounting depreciation should never be included as
a cost (expense) in CBA
Trang 34Comparing Projects with Different Time Frames
Two Methods for Comparing Projects with Different Time Frames
Rolling Over the Shorter Project
Comparison between a cogeneration power plan and a hydroelectric project
Equivalent Annual Net Benefit Method (EANB)
EANB of an alternative equals its NPV divided by the annuity
factor
That has the same life as the project
Where is the annuity factor,
n i
a
NPV EANB
n i
a
i
i a
n n
Trang 35Real Versus Nominal Currency
Constant currency
Use CPI as the deflator
If benefits and costs are measured in nominal currency, use nominal discount rate
If benefits and costs are measured in real currency, use real discount rate
To convert a nominal interest rate i, to a real interest rate, r, with an expected inflation rate, m, use the following equation
If m is small, the real interest rate is approximately equals the Nominal interest rate minus the expected rate of inflation:
r = i-m
m
m
i r
1
Trang 36Alternative Investment
Criteria: Benefit Cost Ratio
As its name indicates, the benefit-cost ratio (R),
or what is sometimes referred to as the profitability index, is the ratio of the PV of the net cash inflows (or economic benefits) to the PV of the net cash outflows (or economic costs):
) Costs Economic
or ( Outflows Cash
Net of
PV
) Benefits Economic
or ( Inflows Cash
Net of
PV
R
Trang 37 Mutually exclusive projects of different sizes
Not necessarily true that if RA>RB, that
project “A” is better than project “B”
Basic Rule
Trang 38Problem:The Benefit-Cost Ratio does not adjust for mutually exclusive
projects of different sizes For example:
Project A: PV 0 of Costs = $5.0 M, PV 0 of Benefits = $7.0 M
NPV A = $2.0 M R A = 7/5 = 1.4 Project B: PV 0 of Costs = $20.0 M, PV 0 of Benefits = $24.0 M
NPVB = $4.0 M RB = 24/20 = 1.2 According to the Benefit-Cost Ratio criterion, project A should be chosen over project B because RA>RB, but the NPV of project B is greater than
the NPV of project A So, project B should be chosen
Conclusion: The Benefit-Cost Ratio should not be used to rank projects
Benefit-Cost Ratio (Cont’d)
Trang 39Pay-out or Pay-back period
The pay-out period measures the number of years it will take for the undiscounted net benefits (positive net cashflows) to repay the investment
A more sophisticated version of this rule compares the discounted benefits over a given number of years from the beginning of the project with the discounted investment costs
An arbitrary limit is set on the maximum number of years allowed and only those investments having enough benefits to offset all investment costs within this period will be acceptable.
Alternative Investment Criteria
Trang 40 The criteria may be useful when the project is subject to high level of political risk.
Pay-Out or Pay-Back
Period
Trang 41Internal Rate of Return (IRR)
IRR is the discount rate (K) at which the present value of benefits are just equal to the present
value of costs for the particular project
Note: the IRR is a mathematical concept, not an
economic or financial criterion
0
0 )
1 (
Trang 42Common uses of IRR:
(a) If the IRR is larger than the cost of funds then the
project should be undertaken
(b) Often the IRR is used to rank mutually exclusive
projects The highest IRR project should be chosen
(c) An advantage of the IRR is that it only uses
information from the project
Trang 43First Difficulty: Multiple rates internal rate of return for Project
Solution 1: K = 100%; NPV= -100 + 300/(1+1) + -200/(1+1) 2 = 0 Solution 2: K = 0%; NPV= -100+300/(1+0)+-200/(1+0) 2 = 0
Difficulties With the Internal Rate of Return Criterion
+300
Bt - Ct
-200 -100
Time
Trang 44Second difficulty: Projects of different sizes and also strict alternatives
Project A -2,000 +600 +600 +600 +600 +600 +600 Project B -20,000 +4,000 +4,000 +4,000 +4,000 +4,000 +4,000
NPV and IRR provide different Conclusions:
Opportunity cost of funds = 10%
NPV : 600/0.10 - 2,000 = 6,000 - 2,000 = 4,000
NPV : 4,000/0.10 - 20,000 = 40,000 - 20,000 = 20,000
Hence, NPV > NPV IRRA : 600/KA - 2,000 = 0 or K A = 0.30
IRRB : 4,000/KB - 20,000 = 0 or K B = 0.20
Hence, KA>KB
0 B
0 A
0 B
0 A
Difficulties With The Internal Rate of Return Criterion (Cont’d)
Trang 45Benefits = 5,200 in year 10 NPV : -1,000 + 3,200/(1.08)5 = 1,177.86
NPV : -1,000 + 5,200/(1.08)10= 1,408.60
Hence, NPV > NPV
IRRA: -1,000 + 3,200/(1+KA) 5 = 0 which implies that KA= 0.262
IRRB: -1,000 + 5,200/(1+KB) 10 = 0 which implies that KB= 0.179
Hence, KA>KB
0 B
0 A
0
Difficulties With The Internal Rate of Return Criterion (Cont’d)
Trang 46Fourth difficulty: Same project but started at different times
Project A: Investment costs = 1,000 in year 0
Benefits = 1,500 in year 1 Project B: Investment costs = 1,000 in year 5
Benefits = 1,600 in year 6
NPVA : -1,000 + 1,500/(1.08) = 388.88
NPVB : -1,000/(1.08)5 + 1,600/(1.08)6 = 327.68
Hence, NPV > NPV
IRRA : -1,000 + 1,500/(1+K A) = 0 which implies that KA= 0.5
IRRB : -1,000/(1+K B) 5 + 1,600/(1+K B)6 = 0 which implies that KB= 0.6
Hence, K B >KA
0 B
0 A
Difficulties With The Internal Rate of Return Criterion (Cont’d)
Trang 47Project E is worse than D, yet IRR E > IRR D
IRR FOR IRREGULAR CASHFLOWS
For Example: Look at a Private BOT Project from the perspective of the
Government