Project finance 2 tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất cả các lĩnh vực kinh tế, k...
Trang 1Project Finance
Campbell R Harvey Aditya Agarwal Sandeep Kaul
Duke University
Trang 2• Real World Cases
• Project Finance: Valuation Issues
Trang 3The MM Proposition
“The Capital Structure is irrelevant as long as the firm’s investment decisions are taken as given”
Then why do corporations:
• Set up independent companies to undertake mega
projects and incur substantial transaction costs, e.g Motorola-Iridium.
• Finance these companies with over 70% debt even though the projects typically have substantial risks
and minimal tax shields, e.g Iridium: very high
technology risk and 15% marginal tax rate.
Trang 4• Real World Cases
• Project Finance: Valuation Issues
Trang 5What is a Project?
• High operating margins.
• Low to medium return on capital.
• Limited Life.
• Significant free cash flows.
• Few diversification opportunities Asset specificity.
Trang 6• Currency, interest rate, inflation.
• Reserve (stock) or throughput (flow).
– Asymmetric downside risks:
Trang 7What Does a Project Need?
Customized capital structure/asset specific governance systems to minimize cash flow volatility and maximize firm value
Trang 8• Real World Cases
• Project Finance: Valuation Issues
Trang 9What is Project Finance?
Project Finance involves a corporate sponsor investing in and owning a single purpose,
industrial asset through a legally independent entity financed with non-recourse debt.
Trang 10Project Finance – An Overview
• Some major deals:
– $4bn Chad-Cameroon pipeline project
– $6bn Iridium global satellite project
– $1.4bn aluminum smelter in Mozambique
– €900m A2 Road project in Poland
Trang 11Total Project Finance Investment
•Overall 5-Year CAGR of 18% for private sector investment.
•Project Lending 5-Year CAGR of 23%.
Trang 12Number of Projects
Trang 13Lending by Type of Debt
Trang 14Project Finance Lending by Sector
• 37% of overall lending in Power Projects, 27% in telecom.
• 5-Year CAGR for Power Projects: 25%, Oil & Gas:21% and
Infrastructure: 22%.
Trang 15• Real World Cases
• Project Finance: Valuation Issues
Trang 17Structure Highlights
• Independent, single purpose company formed to build and operate the project
• Extensive contracting
– As many as 15 parties in up to 1000 contracts
– Contracts govern inputs, off take, construction and operation
– Government contracts/concessions: one off or operate-transfer.– Ancillary contracts include financial hedges, insurance for Force Majeure, etc
Trang 18Structure Highlights
• Highly concentrated equity and debt ownership
– One to three equity sponsors
– Syndicate of banks and/or financial institutions provide credit
– Governing Board comprised of mainly affiliated directors from
sponsoring firms
• Extremely high debt levels
– Mean debt of 70% and as high as nearly 100%
– Balance of capital provided by sponsors in the form of equity or quasi equity (subordinated debt)
– Debt is non-recourse to the sponsors
– Debt service depends exclusively on project revenues
– Has higher spreads than corporate debt
Trang 19Comparison with Other Vehicles
Trang 20Disadvantages of Project Financing
• Often takes longer to structure than equivalent size corporate finance.
• Higher transaction costs due to creation of an
independent entity Can be up to 60bp
• Project debt is substantially more expensive (50-400 basis points) due to its non-recourse nature.
• Extensive contracting restricts managerial decision making.
• Project finance requires greater disclosure of
proprietary information and strategic deals.
Trang 21Motivations: Agency Costs
• Reduce free cash flow through high debt service
• Contracting reduces discretion
• “Cash Flow Waterfall”: Pre existing mechanism for allocation of cash flows Covers capex, maintenance expenditures, debt service, reserve accounts, shareholder distribution
Trang 22Motivations: Agency Costs
• Bank loans provide credit monitoring
• Separate ownership: single cash flow stream, easier monitoring
• Senior bank debt disgorges cash in early years They also act as “trip wires” for managers
Trang 23Motivations: Agency Costs
vertical integration may be absent
• Long term contracts such as supply and off take contracts: these are more effective mechanisms than spot market transactions and long term relationships
Trang 24Motivations: Agency Costs
• Due to high debt level, appropriation of firm value by a partner results in costly default and transfer of ownership
Trang 25Motivations: Agency Costs
• Since company is stand alone, acts
of expropriation against it are highly visible to the world which detracts future investors.
• High leverage forces disgorging of excess cash leaving less on the table
to be expropriated.
Trang 26Motivations: Agency Costs
• Multilateral lenders’ involvement detracts governments from
expropriating since these agencies are development lenders and lenders
of last resort However these agencies only lend to stand alone projects.
Trang 27Motivations: Agency Costs
• Given the nature of projects, investment opportunities are few and thus investment distortions/conflicts are negligible
• Strong debt covenants allow both equity/debt holders to better monitor management
Trang 28Motivations: Agency Costs
Trang 29Why Corporate Finance Cannot Deter
Opportunistic Behavior ?
• Do not allow joint ownership.
• Direct expropriation can occur without triggering default.
• Creeping expropriation is difficult to detect and highlight.
• Multi lateral lenders which help mitigate sovereign risk lend only to project companies.
• Non-recourse debt had tougher covenants than corporate debt and therefore enforces greater discipline.
• In the absence of a corporate safety net, the incentive to
generate free cash is higher.
Trang 30Motivations: Debt Overhang
Problems:
• Under investment in
Positive NPV projects at the
sponsor firm due to limited
corporate debt capacity
Equity is not a valid option
due to agency or tax reasons
Fresh debt is limited by
pre-existing debt covenants
corporate debt capacity.
Trang 31Motivations: Risk Contamination
Problems:
• A high risk project can
potentially drag a
healthy corporation
into distress Short of
actual failure, the risky
project can increase
cash flow volatility
and reduce firm value
Conversely, a failing
corporation can drag a
healthy project along
with it
Structural Solutions:
• Project financed investment exposes the corporation to losses only to the extent of its equity commitment, thereby reducing its distress costs
• Through project financing, sponsors can share project risk with other sponsors Pooling of capital reduces each provider’s distress cost due to the relatively smaller size of the investment and therefore the overall distress costs are reduced This is
an illustration of how structuring can enhance overall firm value That, contradicting the MM Proposition
Trang 32Motivations: Risk Contamination
Problems:
• A high risk project can
potentially drag a
healthy corporation
into distress Short of
actual failure, the risky
project can increase
cash flow volatility
and reduce firm value
Conversely, a failing
corporation can drag a
healthy project along
with it
Structural Solutions:
• Co-insurance benefits are negative (increase in risk) when sponsor and project cash flows are strongly positively
correlated Separate incorporation eliminates increase in risk
Trang 33Motivations: Risk Mitigation
• Completion and operational risk can be mitigated
through extensive contracting This will reduce cash flow volatility, increase firm value and increase debt capacity.
• Project size: very large projects can potentially
destroy the company and thus induce managerial risk aversion Project Finance can cure this (similar to the risk contamination motivation).
Trang 34Motivations: Other
• Tax: An independent company can avail of tax holidays.
• Location: Large projects in emerging markets cannot be
financed by local equity due to supply constraints Investment specific equity from foreign investors is either hard to get or expensive Debt is the only option and project finance is the optimal structure.
• Heterogeneous partners:
– Financially weak partner needs project finance to participate
– It bears the cost of providing the project with the benefits of project finance
– The bigger partner if using corporate finance can be seen as
free-riding
– The bigger partner is better equipped to negotiate terms with banks than the smaller partner and hence has to participate in project finance
Trang 35On or Off-Balance Sheet
Professor Ben Esty: Your question
regarding on vs off balance sheet is a good one, but not one with a simple answer I do not know of a good
place to refer you to either
Trang 36On or Off-Balance Sheet
The on/off balance sheet decision is mainly a function
of both ownership and control Project finance for a single sponsor with 100% equity ownership results in on-balance sheet treatment for reporting purposes But because the debt is a project obligation, the
creditors do not have access to corporate assets or
cash flows (the rating agencies view it as an "off
credit" obligation in other words, not a corporate
obligation) Even though people refer to PF as balance sheet financing" it can, as this example
"off-shows, appear on-balance sheet
A good example is my Calpine case where the company has financed lots of stand alone power plants In the aggregate, the company showed D/TC = 95% on a
consolidated basis.
Trang 37
On or Off-Balance Sheet
With less than 100% ownership, it gets a lot trickier
Many projects are done with 2 sponsors each at 50%
In this case, they both can usually get off-balance
sheet treatment for the debt and the assets Instead, they use the equity method of reporting the
transaction (with even lower ownership, they use the cost method of reporting) All of this changes if they have "effective control" which is a very nebulous
concept (with 40% ownership but 5 out of 8
directors you might be deemed to have control)
Even if you do not have to report the debt on a
consolidated basis, there are often lots of obligations that do need to be disclosed For example, if you
agree to buy the output of a project, that should be
disclosed as a contingent liability in the footnotes to your annual report There are differences between
tax and accounting conventions.
Trang 38Alternative Approach to Risk
Mitigation
Completion Risk Contractual guarantees from manufacturer,
selecting vendors of repute
Price Risk hedging
Resource Risk Keeping adequate cushion in assessment.Operating Risk Making provisions, insurance
Environmental Risk Insurance
Technology Risk Expert evaluation and retention accounts
Trang 39Alternative Approach to Risk
Mitigation
Political and
Sovereign Risk • Externalizing the project company by forming it abroad or using external law or jurisdiction
• External accounts for proceeds
• Political risk insurance (Expensive)
• Export Credit Guarantees
• Contractual sharing of political risk between lenders and external project sponsors
• Government or regulatory undertaking to cover policies
on taxes, royalties, prices, monopolies, etc
• External guarantees or quasi guarantees
Interest Rate Risk Swaps and Hedging
Insolvency Risk Credit Strength of Sponsor, Competence of management,
good corporate governanceCurrency Risk Hedging
Trang 40• Real World Cases
• Project Finance: Valuation Issues
Trang 42Financing Choice: Portfolio Theory
• Combined cash flow variance (of project and sponsor) with joint financing increases with:
– Relative size of the project
– Project risk
– Positive Cash flow correlation between sponsor and project
• Firm value decreases due to cost of financial distress which increases with combined variance.
• Project finance is preferred when joint financing (corporate finance) results in increased combined variance.
• Corporate finance is preferred when it results in lower
combined variance due to diversification (co-insurance).
Trang 43Financing Choice: Options Theory
• Downside exposure of the project (underlying asset) can be
reduced by buying a put option on the asset (written by the banks in the form of non-recourse debt)
• Put premium is paid in the form of higher interest and fees on
loans.
• The underlying asset (project) and the option provides a
payoff similar to that of call option.
Trang 44Financing Choice: Options Theory
• The put option is valuable only if the Sponsor might be
able/willing to exercise the option.
• The sponsor may not want to avail of project finance (from
an options perspective) because it cannot walk away from the project because:
– It is in a pre-completion stage and the sponsor has provided a
completion guarantee
– If the project is part of a larger development.
– If the project represents a proprietary asset.
– If default would damage the firm’s reputation and ability to raise
future capital.
Trang 45Financing Choice: Options Theory
• Derivatives are available for symmetric risks but not for binary risks, (things such as PRI are very expensive).
• Project finance (organizational form of risk management) is better equipped to handle such risks.
• Companies as sponsors of multiple independent projects: A portfolio of options is more valuable than an option on a
portfolio.
Trang 46Financing Choice: Equity vs Debt
• Reasons for high debt:
– Agency costs of equity (managerial discretion,
expropriation, etc.) are high.
– Agency costs of debt (debt overhang, risk shifting) are low due to less investment opportunities.
– Debt provides a governance mechanism.
Trang 47Financing Choice: Type of Debt
• Bank Loans:
– Cheaper to issue
– Tighter covenants and better monitoring
– Easier to restructure during distress
– Lower duration forces managers to disgorge cash early
• Project Bonds:
– Lower interest rates (given good credit rating)
– Less covenants and more flexibility for future growth
• Agency Loans:
– Reduce expropriation risk
– Validate social aspects of the project
• Insider debt:
– Reduce information asymmetry for future capital providers
Trang 48Financing Choice: Sequencing
• Starting with equity: eliminate risk shifting, debt overhang and probability of distress (creditors’ requirement).
• Add insider debt (Quasi equity) before debt: reduces cost of information asymmetry.
• Large chunks vs incremental debt: lower overall transaction costs May result in negative arbitrage.
Trang 49• Real World Cases
• Project Finance: Valuation Issues
Trang 50Real World Cases
BP Amoco: Classic project finance
Australia Japan cable: Classic project finance Poland’s A2 Motorway: Risk allocation
Petrolera Zuata: Risk management
Chad Cameroon: Multiple structures
Calpine Corporation: Hybrid structure
Iridium LLC: Structure and Financing choices Bulong Nickel Mine: Bad execution
Trang 51Case : BP Amoco
Background: In 1999, BP-Amoco, the largest shareholder in AIOC, the
11 firm consortium formed to develop the Caspian oilfields in
Azerbaijan had to decide the mode of financing for its share of the $8bn
2nd phase of the project The first phase cost $1.9bn
Issues:
• Size of the project: $10bn
• Political risk of investing in Azerbaijan, a new country
• Risk of transporting the oil through unstable and hostile countries
• Industry risks: price of oil and estimation of reserves
• Financial risk: Asian crisis and Russian default