Items needs to be checked & serviced 1 Check main panels 2 Check panel cooling fan & clean its filter 3 Clean main pump inverter & its cooling fan 4 Check all circuit breaker ,magnetic c
Trang 1Maintenance
Trang 2Prepared By : Mazadul Hasan sheshir ID: 2010000400008
13th Batch (session 2009-2013) Department : Wet Processing Technology Email: mazadulhasan@yahoo.com Blog : www Textilelab.blogspot.com (visit)
Trang 3Maintenance is the actions taken to prevent a device or component from failing or to repair normal equipment degradation experienced with the operation of the device to keep it in proper working order.
Maintenance:
Trang 4Classification of Maintenance:
Trang 51 Reactive/ Break down Maintenance.
2 Preventive/ Schedule Maintenance.
3 Predictive/ Planned Maintenance.
4 Capital replacement/ Restorative.
Types of Maintenance:
Trang 6REACTIVE/ BREAK DOWN MAINTENANCE:
Reactive maintenance is basically the “run it till it breaks” maintenance mode No actions or efforts are taken to maintain the equipment as the designer originally intended to ensure design life is reached
Advantages:
Low cost
Less staff
Disadvantages:
Increased cost due to unplanned down time of equipment
We are spending more dollars associated with capital cost because, while waiting for the equipment to break, we are shorting the life of the equipment resulting in more frequent replacement or repair
If it is a critical piece of equipment that needs to be back on line quickly, we will have to pay maintenance overtime cost
Possible secondary equipment or process damage from equipment failure
Trang 7PREVENTIVE/ SCHEDULE MAINTENANCE:
Preventive maintenance can be define as action performed on a time or machine-run-based schedule that detect, preclude or mitigate degradation of a component or system with the aim of sustaining or extending its useful life time to an acceptable level
Advantage:
Increase component life cycle
Flexibility allows for the adjustment of maintenance periodicity
Reduced equipment or process failure and estimated 12% to 18% cost savings over reactive maintenance program
Disadvantage:
Labor intensive
Increased performance of unneeded maintenance
Potential for incidental damage to components in conducting unneeded maintenance
Trang 8PREDICTIVE/ PLANNED MAINTENANCE:
Predictive maintenance can be define as measurement that define the degradation of machine, thereby allowing casual stressors to be eliminated or controlled prior
to any significant deterioration in the component physical state Results indicate current and future functional capability
Basically, predictive maintenance differs from preventive maintenance by basing maintenance need on the actual condition of the machine rather than on some preset schedule
Advantage:
Increased component operational life and availability
Allows preemptive corrective actions
Decrease in equipment or process downtime and estimated 8 to 12% cost savings over preventive maintenance program
Better product quality
Improved worker and environmental safety
Decrease in cost for parts and labor
Disadvantage:
Increased investment in diagnostic equipment
Increased investment for proficient manpower and staff training
Savings potential not readily seen by management
Trang 9CAPITAL REPLACEMENT/ RESTORATIVE:
If it is seen that the repairing cost of machine or machine parts is more or equal or little less than buying a new one, then the old one is replaced instead of repair It is known as capital replacement.
Trang 101 To keep the factory plants, equipment, machine tool etc in optimum working condition.
2 To ensure accuracy of product and time schedule to delivery customers.
3 To minimize down time of machine.
4 To prolong the useful life of factory plant and machine.
5 To modify or improve productivity of existing machine to meet the need for production and thus avoid sinking of additional capital.
OBJECTIVE/ ADVANTAGE OF MAINTENANCE:
Trang 111. Inspection or check-ups:
2. Crews kept for inspection should be well trained
3. External inspection means to detect defects from abnormal sound, vibration, heat, smoke etc
4. Internal inspection means to check internal parts of the machine
5. Lubrication:
6. Systematic lubrication means the application of right type of lubricant at right time at right place and in right quantity
7. It is done to minimize friction and reduce decay of machine parts
8. Planning and scheduling:
9. Every preventive maintenance work should be pre planned
10. The program is specified in detail by mentioning daily, weekly and yearly attention
11. Records and analysis:
Following are some important functions of maintenance department:
Trang 12 Operation manual
Maintenance instruction manual
History cards and history register
Inspection register
Log books
Defects register etc
Training of maintenance personnel:
The technician and supervisors of maintenance department should be well trained in a systemic way
Storage of spare parts:
It is essential to store some essential spare parts which are needed every now and to keep the machine running and reduce stoppage time for machine defects
Following records are generally maintained:
Trang 131. Good supervision and administration of maintenance departments.
2. Operators should be well trained
3. Proper maintenance record should be maintained
4. Adequate stock of spare parts should always be kept
5. Manufacturer of the machine tools should be consulted as and when required
6. Maintenance department should remain in contact with planning and purchasing department deciding the type of machine tools to be purchased
Requirements of good maintenance:
Trang 141. Dismantles equipment and removes worn or defective parts, using hand tools
2. Replaces defective parts, such as plugs, reeds, needles, points, shuttles, cots, chains, heddles, slide rods, and side or frame hooks
3. Adjusts parts and tension on parts, such as rollers, chains, and cylinders, using hand tools and gauges
4. Repairs defective parts, such as flats, wires, shuttles, collars, frames, chains, and rollers, using hand tools and soldering and welding equipment
5. Aligns, straightens, spaces, and levels parts, using hand tools, straightedge, level, and plumb bob
6. Replaces worn covering (rubber, cork, leather, cloth, felt) on cylinders, rollers, and roller arbors, using hand tools and arbor press
Tasks of the maintenance departments:
Trang 15-7. Inspects and examines textile machines and equipment to detect defects, by observing or listening to machine or using micrometers and feeler gauges.
8. Verifies accuracy of part repair or replacement, adjustment, or alignment
9. Installs special attachments to equipment
10.Lubricates machinery and equipment
11.Smoothes and polishes equipment, using abrasives and buffing, sanding, and grinding machines
12.Cleans equipment with solvent, brushes, and airhose to remove dirt, lint, oil, and rust
13. Maintains parts and equipment inventory, receipt, and transfer records
14.Moves equipment and machine components, using hoists, rollers, and handtrucks
15. Sorts and stores parts and equipment according to type or size
Tasks of the maintenance departments:
Trang 16-There are different steps in wet processing technology Now we are going to describe about the steps in textile wet processing system where
maintenance needed
Trang 17Inspection: Neps, warp, end breakage, weft end breakage, hole spot remove.
Singeing: Projecting or floating fiber remove from the surface of the fabric
Desizing: It’s done to remove the sized materials from the fabric
Scouring: Using alkali ( NaOH, Na2CO3) for increasing absorbency of fabric
Bleaching: The bleaching process is done to produce Permanent white of the fabric
Dyeing: Dyeing is the procedure done for producing color to the textile materials There are lots of methods in dyeing But it can be classed as three byes the normal method Like 1 Yarn dyeing, 2 Fabric Dyeing, 3 Garments Dyeing,
Mercerizing: To maintain the proper length and width of the fabric
Printing: Specific Color on the fabric
Finishing: Soft finish for consumer satisfaction
Trang 18Here the problem in the process and their maintenance are given below:
Trang 25Efficiency:
Trang 26Wet processing of textiles constitutes innumerable steps leading to finished product, each having a number of complex variables and every lot is like a new lot and much depends on the well-trained manpower rather than modern machines and technology However, developments are taking place at a rapid pace to satisfy the user with quality product and competitive price Though underlying principle for developments is satisfying user needs This in turn will impart cost competitiveness Then, more functional finishes are also being developed However trend is to use more mechanical finishes than chemical finishes The key to success in textile wet processing technology will be the indication of highly trained
Trang 27MAINTENANCE : ELECTRICAL
SL NO Items needs to be checked & serviced
1 Check main panels
2 Check panel cooling fan & clean its filter
3 Clean main pump inverter & its cooling fan
4 Check all circuit breaker ,magnetic conductors & relays
5 Check current setting of all circuit breaker & motor over load
6 Visual checking of all power & control cables
7 Check ail motor’s terminals
8 Check & clean fluff & dirt at all motor fan covers
9 drive of kneel motors
10 Check all pressure switches
11 Check calibration of main vessel & all addition tank
12 Check all signal isolators
13 Check setting & operation of lid safely switches
14 Check setting of tangle sensors
15 Check all pneumatic solenoids
16 Check all indicating lamps
17 Check calibration of heating/ cooling modulating valve
18 Check all on/off switches
Trang 28Power on/off.
↓MPF/Positive feeder current line off
↓MPF belt out/loss
↓Yarn cut
↓Fabric out by handle
↓Cleaning and Oiling
↓Cam box out
↓Needle & sinker out
↓Needle & sinker cleaning by oil
↓Cam box cleaning by air
After opening & cleaning, machine is leveled by using leveling meter and follows the reverse process to ready the machine
Maintenance Sequence of Circular Knitting Machine:
Trang 29YEARLY MAINTENANCE CHECK LIST
DEMAG MONORAIL HOIST
Grease all the moving parts and bearings
Check all the nut and bolts
Check oil level
Check each sprocket, chain and chain collector are ok
Check the thickness of the lines
Check visually the damage of main girders
PRESSING MACHINE
Check rotating table balls and lubricate
Lubricate the axial bearings
YARN SINGEING MACHINE
Clean control cabinet using a vacuum cleaner
Do not touch the circuit card and soldering joints
Every 4 year change the battery on the RAM card
Trang 30YEARLY MAINTENANCE CHECK LIST
SANTEX COMPACTOR MACHINE
Check the machine for visual damages
Replace the worm reduction gear oils
Check the compacting shoes for wearing
Check the blankets for wearing
Check the foundation bolts of the machine
FABRIC DYEING MACHINE
Check the machine for visual damages
Drain & replace the main pump bearing oil
Drain & replace the oil of gearboxes
Check and if necessary replace all plaiter bearings balls
Check the platter/ J-box center alignment
Check the manhole O-ring
Check and grease all greasing points
Check and tight all plaiter, catch basket, reel and other support bolts from the inside of the machine
Check all the PTFE carbon supports and sleeves in the plaiting device system inside the machine
Trang 31YEARLY MAINTENANCE CHECK LIST
SANTEX COMPACTOR MACHINE
Check the machine for visual damages
Replace the worm reduction gear oils
Check the compacting shoes for wearing Replace if necessary
Check the blankets for wearing
Check the foundation bolts of the machine
DORNIER MERCERIZING MACHINE
Grease all the bearings and moving parts
Check the bearing bolts and replace them if necessary
Change the gear oil of the gear boxes
Check the rubber coating of the fixation & drive rollers
Complete check of the cooling plant
Check the spray rings, piping and armatures
Check the pneumatic piping for proper connection
Check and retighten the electric connections of machine
Replace the chains and the chain wheels of the drives
Trang 32HALF YEARLY MAINTENANCE
ALEA HANK DRYER MACHINE
Adjust the chain tension and lubricate it
Check the oil level of the gear box
Change the gear oil once a year
Lubricate the bearings with grease
CALATOR RUCKH INSPECTION MACHINE
Lubricate chain and adjust the tension
Grease all the bearings
Change gear oil once a year
PRECISION WINDING MACHINE
Clean the cable channels and electric cabinet
Clean the flyer set and displacement unit
Check certain
Every 5 year replace buffer batteries on the control cabinet
Trang 33HALF YEARLY MAINTENANCE
LORIS BELLINI HANK DYEING MACHINE
Clean and check the compressed air filter
Check the pneumatic cylinders
Tightening of every bolt
Tightening of foundation bolts
Check and replace the roller bearings if necessary
Maintenance for piston pneumatic valves
Tightening of terminals of electric motors
Tightening of terminals of electric boards
Yarn singeing machine
Check condition of variator, remove any wound on thread
Check automatic contrails of all sensors
Trang 34TWO MONTHLY MAINTENANCE
STALAM YARN DRYER
Check inside of the panel
Check the nut, bolts and belts of dryer
Grease the roller support every 4 month
Trang 35MONTHLY MAINTENANCE CHECK LIST
ASSEMBLY WINDING MACHINE
• Check the cone holder's looseness
• Clean the inverters
• Clean the yarn path properly
• Check the package diameter sensor
JAEGGLI YARN MERCERIZING MACHINE
• Grease hooks draught bearings (B)
• Grease function bearings of the squeegee roller (H)
• Grease fulcrum bushes of the lifting cylinder(L)
• Check the hydraulic oil pressure
LORIS BELLINI HANK DYEING.
• Inspection of wear and tear of lid gasket
• Lubricate the electric motors
• Check the mechanical seals of add pumps
• Inspect the serviceability of safety valves
• Maintenance of stuffing box
Trang 36MONTHLY MAINTENANCE CHECK LIST
PRESSING MACHINE
• Check the function of rotating table moving arm
• Check thoroughly the sliding pneumatic parts
YARN SINGEING MACHINE
• Check spindle motor supply
• Check function of the vacuum monitor of the suction off switch
• Check function of the compressed air monitor on the gas mix section
SCHOLL PACKAGE DYEING
• Check main pump v- belt connection
• Check the safety, steam and water valves
DORNIER MERCERIZING MACHINE
• Clean and lubricate the motors the motors
• Clean and lubricate the pumps and check the impellers
• Clean the switch board and the switching elements visually
• Check the bearings of all rollers
• Check the bearings of the chain reversing sprockets
• Check the magnetic attachment
• Clean the entire plant
Trang 37MONTHLY MAINTENANCE CHECK LIST
HYDRO EXTRACTOR MACHINE
Lubricate the spindle bearings at the end of the shaft and greasing nipple on the rotary treble behind the front part of removable casing
Lubricate the guide pulley behind the front part of removable casing
MONFORTS PADDER, STRETCHER & DRYER MACHINE
Lubricate:
Bearings of padder rolls with "N"
Sprockets and chains with "E"
Hand wheel, idle rollers with "B"
Check, Grease If
necessary.- Nuts of width adjustment spindles for wear
Check all spindle bearings for free running
Free running of guide rollers, deflection rollers & contact rollers
Pressure springs of chain pensioner
Perform visual inspection:
Gear box oil level
Belts, pulleys
Move width adjustment motor to the end position & check counters