DIFFERENT FABRIC GSM AND THEIR REQUIRED YARN COUNTRib without lycra -Fabric G.S.M Yarn Count... To do this for a definite count of yarn following calculation is followed, In this machin
Trang 1TEXTILE CALCULATION & EQUATION
Trang 2Name : MAZADUL HASAN SHESHIR
ID: 2010000400008
Batch: 13th Batch (Session 2009-2013) Department: Wet Processing Technology Email: mazadulhasan@yahoo.com
Blog: www Textilelab.blogspot.com
Southeast University
Department of Textile Engineering
PREPARED BY ©right
Trang 3Spinning Calculation and Equation
Trang 4Basic Conversions (Spinning)
Trang 5Count Conversion Table (Spinning)
Ne= 1 xNe 0.5905 xNm 590.5 /Tex 5905 /Grex 5315 /Den
Nm= 1.693xNe 1 xNm 1000 /Tex 10,000/Grex 9000 /Den
Tex= 590.5 /Ne 1000 /Nm 1 xTex 0.1 xGrex 0.111 xDen
Grex= 5905 /Ne 10,000 /Nm 10 xTex 1 xGrex 1.111 xDen
Denier= 5315 /Ne 9000 /Nm 9 xTex 0.9 xGrex 1 xDen
Trang 6Draft & TPI Formulas
Trang 7Efficiency Percentage (Spinning)
Cleaning Efficiency (%)
Efficiency (%)
Twists per inch
Trang 8PRODUCTION CALCULATION FORMULAS
Trang 9PRODUCTION FORMULAS
Trang 11Yarn Count in Direct system
System
Pounds/Spyndle Pounds 14400yds Jute
Yarn Count in Indirect system
Trang 12•
Excellence of fiber quality by combing:
Trang 14Fabric ( Knitting & Weaving ) Calculation and Equation
Trang 15SIZING
Trang 16Calculation:
Trang 17Required Chemical &no of Mixing of Sizing Recipe:
Trang 20Production is calculated in accordance with the following
Trang 21Stitch length = (Tex × Ks) / GSM
Ks is a constant Its value is different for different fabric structure and fabric type Ks is calculated and estimated as below:
Ks = (GSM x Stitch length) / Tex
Trang 22Production calculation:
Ks = (GSM x Stitch length) / Tex
Trang 25Relation between yarn count and m/c gauge seen in different m/c.:
Trang 26GSM Calculation
Trang 27DIFFERENT FABRIC GSM AND THEIR REQUIRED YARN COUNT
Rib without lycra
-Fabric G.S.M Yarn Count
Trang 28Interlock without lycra
-Fabric G.S.M Yarn Count
200 - 220 34 S
220 - 230 32 S
230 - 250 30 S
250 - 300 26 S
Lacoste without lycra
-Fabric G.S.M Yarn Count
Trang 30Yarn Dyeing Calculation and Equation
Trang 31Production Calculation of Yarn singeing machine:
Length = Count * Weight
= Count * Weight * 840 yards
= (Count * Weight * 840) / rpm yards per minute
= (Count * Weight * 840) / rpm * 60 * 8 * 3 yards per day = (Count * Weight * 840) / rpm * 60 * 8 * 3 * 0.914
=……X…meter/day
Trang 32Production Calculation of reeling machine:
Trang 33Production Calculation of hank to cone winding machine:
Machine Parameter Yarn quality Speed (rpm)
All single count 500 to 550
Length = Count Weight
= Count * Weight 840 yards = (Count Weight 840) / rpm yards per minute = (Count Weight 840) / rpm 60 8 3 yards per day = (Count Weight 840) / rpm 60 8 3 0.914
=……X…meter/day.
Trang 34GSM Calculation:
WPI = 32 CPI = 45 Stitch length = 3 mm Yarn Count = 20’S Ne
Trang 35No of Needle = π × Machine Diameter (D) × Machine Gauge (N)
Production Calculation Of Yarn Dyeing Machine :
Production of the machine is 146.407 Kg/Shift.
Note: If any parameter in this calculation is changed then production capacity per shift will be changed.
Trang 36Package Density Calculation (Yarn Dyeing):Formula
Trang 37Density Calculation for Several Counts (Yarn dyeing):
1**Before Pressing
• Yarn Quality: 30/1 cc
• Package Height (H) = 162mm = 16.2cm
• Total Package Dia (D1) = 162mm = 16.2cm
• Total Package Weight (W1) = 1.38kg = 1380gm
• Spring Weight (W2) = 0.185kg = 185gm
• Spring Dia (D2) = 65 mm = 6.5cm
Trang 382 **After Pressing
Yarn Quality: 30/1 ccPackage Height (H) = 145mm = 14.5cmTotal Package Dia (D1) = 165mm = 16.5cmTotal Package Weight (W1) = 1.38kg = 1380gmSpring Weight (W2) = 0.185kg = 185gm
Trang 39Length Calculation in Package:
To maintain the constant package density same length of yarn should be wound to all the packages of a batch or lot The dyeing machine capacity is calculated on
weight, so it is necessary to maintain the uniform weight throughout the packages
To do this for a definite count of yarn following calculation is followed,
In this machine length is pre selected For different count of yarn different length
of yarn is pre selected This is due to maintain the constant package weight and package density
Trang 40Package density Calculation
We know package density ρ = mass (m)/volume (v) gm/cc
Volume= π (R2-r 2) h
R= outer radius of package R= inner radius of package h= height of package
Now we consider a sample of 40/1 cotton yarn whose
R=4.138 r= 1.59 h=15.24 Mass m=1000gm
Trang 41Production calculation of RF Dryer :
Length of RF Dryer = 13m
At 28rpm it takes 21 min 9 sec to pass this length
Along this length it can accommodate 416 package 416kgs
So at 21 min9sec or 1269sec it can dry 416kgs
So in 1hr or 3600sec it can dry = 416×3600/1269 kg/hr
Trang 42Knit Dyeing Calculation and Equation
Trang 43Calculations related to batch section:
Now, when a gram per linear meter is low then meters per chamber will be more Thus, fabric loading should be reduced to avoid jamming in the winch
In this case 80-85% fabric
loading is given But when gram per linear meter is more then rope length will reduce and in this case up to 90% fabric loading can be given
Trang 44Calculating the chamber loading
In the following table are listed general recommendations covering rope cycle times and speeds for a wide range of fabrics:
Fabric Rope cycle times in
minutes(Cycle Time)
Rope circulation speed
m/min(Reel speed)
Trang 47Preparation and storage of stock dyes and chemicals
Available stock solution:
1 Red-0.1%, 0.5%, 1%, 2%
2 Yellow-0.1%, 0.5%, 1.0%, 2.0%,
3 Blue- 0.1%, 0.5%, 1.0%, 2.0%
Preparation:
To prepare 0.1% stock solution, it necessary to mix 0.1 gm dye with 100cc water
To prepare 0.5% stock solution, it necessary to mix 0.5 gm dye with 100cc water
To prepare 1.0% & 2.0% stock solution similar procedure is followed
To prepare 10% stock solution of soda ash, it necessary to mix 10 gm soda with 100cc water
SHADE % STOCK SOLUTION %
Trang 48Stock Solution Making Procedure (Dyeing lab)
For solid,
X gm chemicals/dyes/auxiliaries in the 100 ml water is called x%
stock solution
For liquid,
X ml/cc chemicals/dyes/auxiliaries in the (100 - x ml/cc) water
is called x% stock solution
Conversion formula from percentage to g/l is as
g/l = Required amount (%)× 10
Trang 49Recipe Calculation
Trang 51Dyes and chemicals measuring formula for laboratory:
The amount of dye solution (ml) is calculated as follow –
The amount of chemical soln (ml) is measured as follow –
Trang 53Fabric Type GSM Pump Speed % Reel Speed(MPM)
Polo Pique, Back Pique
& Bubble Knit
Trang 54MONTHLY EFFICIENCY OF KNITTING FLOOR:
Daily production – 6500 kgs Approx
Daily production capacity – 10000 kgs approx
So, monthly production – 6500 x 30 kgs
Monthly production capacity – 10000 x 30 kgs
So, Monthly production efficiency = (6500x30x100)/ (10000x30) % = 65%
Trang 55Garments Calculation and Equation
Trang 56COSTING OF THE PRODUCT:
Packing cost = $0.05Production cost of fabric=$6.15Fabric price (with 25% margin) =$7.79Fabric consumption/ doz
= (Body length + Sleeve length +10) x Chest length x 2 x GSM x12 /10000000
Trang 57Cost of Trims (with 5% Process loss) = $2.36
Production Cost of Garments/ doz=$36.09
Garments Price/doz (with 25% Profit) =$45.12
COSTING OF THE PRODUCT:
Trang 58Costing of Men’s shirt
Fabric consumption for a dozen of shirt π × L size of basic shirt.═ size of basic shirt.Width of body of shirt 1/2 chest═ size of basic shirt
═ size of basic shirt 24"+1"(sewing allowance)
═ size of basic shirt 25"
Body length 32"+1"(sewing allowance)═ size of basic shirt
═ size of basic shirt 33"
Sleeve length 23"+2.5(cost) +1.5"(sewing allowance)═ size of basic shirt
═ size of basic shirt 27"
Consumption of a body shirt:
═ size of basic shirt.{1/2 chest× (body length) ×2} / 36× fabric width (Sq inch) ═ size of basic shirt.25"×33"×2 (Sq inch )
{Let assume fabric width 25"effective width 25"−1" 24"}═ size of basic shirt ═ size of basic shirt
Fabric length 25×33×2 / 44 inch═ size of basic shirt
Trang 59Fabric consumption 25×33×2 / 44×36 yds═ size of basic shirt.
Consumption of sleeve (length of sleeve × width sleeve) ×2 sq inch═ size of basic shirt
═ size of basic shirt.27"×24"×2" (Sq inch)
Fabric consumption in length width
═ size of basic shirt 27×24×2 / 44×36 sq inch
Total fabric consumption of one dozen shirt
═ size of basic shirt [(25×33×2 / 44×36 + / 27×24×2 / 44×36) ×2+ wastage of 8%]
═ size of basic shirt 22.75 yds + 8% wastage
═ size of basic shirt.24.6 yds
Sewing threads consumption:
It is calculated by measuring the total of different kind of seam Normally sewing threads consumption per shirt , 120m
So, sewing threads consumption per dozen,
═ size of basic shirt 120 × 12
═ size of basic shirt 1440m
Costing of Men’s shirt
Trang 60Lab cost : 0.20 Accessories cost : 2.5 Washing cost : 1
Total = $ 28.80 / Doz.
= $ 2.40 / pcs.
Trang 62How can we get Fabric Consumption & Fabrics Price?
Trang 63Poly bag costing :
Total Length X width X Thickness
= 36cm X 28cm X 10mm
= 10080/72000
= 0.14pcs/lb
Fabrics Price:
Total Fabric Need 5.00 Kg $ 6.00 = $ 30.00
Trim/ Accessories (Minimum Charge) = $ 2.50
Cutting & Making Charge (C.M) = $ 5.00
Printing Charge (If any) = $ 0.00
Embroidery Charge (If any) = $ 0.00
Buying Commission (If necessary) 5% = $ 1.97
Final/Total = $ 39.47/12
Costing of a garment:
Fabric cost + Accessories cost + Trimming cost + Production cost + Transport cost + Commission + Profit
Trang 65Consumption of T-Shirt:
Equation:
{(Body length + Sleeve length) Chest} 2 GSM 10000 1000 5000
Solution:
Body Length = 50 + 6 (Allowance) = 56 cm
Sleeve Length = 15 + 3 (Allowance) = 18 cm
Chest = 37 + 3 (Allowance) = 40 cm
GSM = 180 cm
= {(56 + 18) 40} 2 180 10000 1000 5000
= 532.8 kg
Trang 66Collar depth =2.5 cm 2 = 5 cm GSM = 240
= {(44 + 5) 5} 2 140 10000 1000 5000
= 58.8 kg
Total = 532.8 + 58.8 kg = 591 kg
Trang 67Collar & Cuff measurements
Size Collar measurement (cm) Cuff measurement (cm)
Trang 68Consumption of bottom part:
Trang 691.5705kg
Trang 70Costing process:
Finish fabric cost: (Yarn price + Knitting cost + dyeing cost)
Body fabric cost: (Total fabric consumption + Total yarn consumption)
Cost of making (CM):………$
Accessories cost:……… $
Overhead cost………$
Others cost:……….$
Buyer commission:……….$
Total cost $
Costing process:
PRICE OF THE PRODUCT:
Generally price of product is determined by the required profit adding to the total expenses So,
Price of products
= (Direct expenses + Indirect expenses + Factory Overhead) + Required profit
Trang 72MARKER EFFICIENCY: The marker planner measures his success by the efficiency
of the marker plan The following formula is used to measure the efficiency:
Marker efficiency=Area of the pattern in the marker plan/ Total area of the
marker plan X 100%
MARKER EFFICIENCY:
Trang 73STANDARD TIME = Normal time + Allowances
= Normal time + (Normal time ×Allowances)
= NT (1+ Allowances)
In garments production world, the terms SMV or SAM used frequently
SMV stands for Standard Minute Value
SAM for Standard allocated minute or Standard Allowed Minute
SMV CALCULATION:
SMV calculation of a basic T-shirt from a time study sheet of a garments industry Following formulas are use-
Normal time = (Average observed time) × (Performance rating factor)
SMV (Standard Minute Value) = Basic Time + (Allowances × Basic time)
= Basic Time× (1+ Allowance)
Allowances are assumed for this calculation is 20%
SMV
Trang 74Target Production /Hour = (No Of worker -1) x 60 / SMV
SMV = standard Mean Value (the Time Required to Complete garments by
sewing )
SMV =( Basic time +Allowance )
Trang 75To select sewing thread, thread size or number is very important The number which is used to express the fineness of a sewing thread is called sewing thread number or ticket number It has 2 system as follows-
Cotton system : It is derived from English cotton system.
Cotton ticket number in Ne = ( Yarn count in Ne / Number of ply ) x 3
Metric system : It is derived from Metric count system.
Ticket number in Nm = ( Yarn count in Nm / Number of ply ) x 3
sewing thread number or ticket number
Trang 76Equation For Find Yarn Count (If GSM is Known)
Trang 77Find out Required Yarn Count (If GSM is Known)
Equation :
S/j Ne = (0.141x GSM) + 50.22 Pique Ne = (0.146x GSM) + 57.16 Double Lacost Ne = (0.167 X GSM) + 64.36 1X1 Rib Ne = (0.123X GSM) + 54.57
Interlock = (0.206X GSM) + 80.56 Lycra 1X1 Rib = (0.119 X GSM) + 59.12 Lycra 2X2 Rib = (0.108X GSM) + 56.62
Trang 78Equation :
= GSM / 43” X Width / 1000 X Per kg Prize
=Result [This the Equation define per yards Fabric price ]
Trang 79Equation :
= Length /36 / 2.54 X 1000
=Result [ It is converted Meter To yards ]
Trang 81Textile Testing
Calculation and Equation
Trang 82Four point grading system
Over 3 inch but not over 6 inch 2 point Over 6 inch but not over 9 inch 3 point
Four point grading system
Trang 83Shrinkage Test:
Trang 84Spirality test: