This During the last 12 years several of us in Ove Arup Partners, stimulated by the late Peter Rice, have pursued through various projects an interest in tensile systems which provide restraint to slender arches. The most recent of these is the Saga project which John Thornton has presented in a separate paper From Schlumberger to the Dynamic Earth A Sequence of Membrane Roofs 1. paper therefore looks at some of Sagas antecedents. Some of these have cable nets or textile membranes prestressed onto them, others are deadweight glass roofs. In each case it is the geometric stiffness of the tie restraint system which is significant rather than the levels of prestress applied. Each project has relied on the use of nonlinear analysis software to develop and justify structural behaviour. The software is based upon the Dynamic Relaxation technique originated by Alistair Day 2 and it explicitly models the following effects: • Large displacements • Change of stiffness of beam elements due to the axial forces and moments developing within them • Tie and membrane element forces go to zero if they attract zero strain.
Trang 1TENSIONED BRACED RIBS IN ARCHITECTURAL PROJECTS
Brian Forster, Ove Arup & Partners, London
This
During the last 12 years several of us in Ove Arup &
Partners, stimulated by the late Peter Rice, have pursued
through various projects an interest in tensile systems
which provide restraint to slender arches
The most recent of these is the Saga project which John
Thornton has presented in a separate paper - "From
Schlumberger to the Dynamic Earth - A Sequence of
Membrane Roofs" [1]
paper therefore looks at some of Saga's antecedents
Some of these have cable nets or textile membranes
prestressed onto them, others are deadweight glass roofs
In each case it is the geometric stiffness of the tie
restraint system which is significant rather than the levels
of prestress applied
Each project has relied on the use of non-linear analysis
software to develop and justify structural behaviour The
software is based upon the Dynamic Relaxation
technique originated by Alistair Day [2] and it explicitly
models the following effects:
• Large displacements
• Change of stiffness of beam elements due to the
axial forces and moments developing within them
• Tie and membrane element forces go to zero if they
attract zero strain
Day [3] has described the software and its use in the
design development of the first of the following projects:
T H O M S O N L G T , C O N F L A N S S T E
-H O N O R I N E , F R A N C E , 1985
Here it was required to cover a 100m long x 18m wide internal "street" with a PTFE/glass membrane roof The buildings on either side of the street have quite different stiffnesses One is a 2 storey insitu concrete frame, the other a tall single storey steel shed Directly coupling them together with a purely tensile membrane was simply not sensible because of the scale of the displacement that would be imposed upon the membrane, by the relative movement of the buildings The preferred architectural solution was to use a closed framework across which spanned tensioned braced arch ribs support panels of membrane (fig 1) The whole framework was fixed to one building and released from the other
However for reasons of cost the truss was realised as fig
2 with slender struts forming the bottom member of a 3 dimensional truss with tensile shear bracing
\ ' 50.8kN ' /
N o n - L i n e a r Analysis
Fig 1
Fig 2 Thomson, France
Futt W n ,
Ties in compression
Linear Analysis S t e p 1
Linear Analysis S t e p 2
Trang 2Day's paper [3] compares the results of using both N-L and linear analyses The latter involved multiple steps and was awkward and slower to carry out This was because under wind load loading some of the diagonal ties go slack with consequent changes in the geometric stiffness of the structure This means when using a linear analysis method the structure has to be re-analysed with those members removed as fig 3
A larger version of the Thomson roof covers the STAR LRT station at Bukit Jalil in Kuala Lumpur The station serves the National Stadium and was built for the 1998 Commonwealth Games (fig 4)
Trang 3S A N N I C O L A S T A D I U M R O O F , B A R I ,
ITALY, 1989
This project was built for the 1990 Football World Cup
held in Italy The architect, Renzo Piano, conceived the
stadium superstructure tier as a flying saucer hovering
above the arena (fig 8) So the superstructure and the
roof have a simple rounded shape and it was important
that the roof be composed as a series of simple calm
sunshades There are 26 of these cantilevering up to 27m
from the back of the concrete upper tier
The infilling structure within each canopy is minimal
through the use of slender tubular ribs curved to follow
the profile of the roof (fig 9) Each is braced with a
system of "chord-ties" - a set of 3 tie rods springing
from each end of the rib and joining to the 1/5th points
of each arc (fig 10)
Under the downward load the chord-ties act to reduce the
buckling length of the rib by resisting its in-plane
deformation
Straight lateral tubes, used to stabilise the ribs
out-of-plane, complete the framework producing an
architectural effect similar to that of a Japanese screen
"itJIf. "^C1-*^•jjafiuB• 9'i'_h
Fig 5 Aviary, HK
Fig 6 Aviary, HK
Fig 7 Aviary, HK
Trang 4Y O U D E AVIARY, H O N G K O N G , 1990
This project was named after the eminent botanist and is
a sub-tropical aviary situated in an urban park in Central
district on Hong Kong island (fig 5) The aviary
straddles a steep sided twisting valley on the lower slopes
of the Peak It was made tall enough to accommodate
existing mature trees and consequently has a maximum
clear internal height of 30m (fig 6) Woven stainless
steel mesh forms the enclosing skin This is suspended
from a cable net system prestressed against 3 tubular
arches The largest of these is 560mm diameter and
spans 62 metres This equates to a span/depth ratio of
110 indicating the stiffening effect that the cable net
provides to the arch (fig 7)
It was found that the bending stiffness of the arch
elements in relation to the axial stiffness of the cables
influenced the size of bending moments developing in
each arch Simply increasing the arch size attracted more
moment The trick was to use thick wall tubes giving the
highest bending capacity (section modulus) but with the
lowest bending stiffness (moment of inertia) for cable net
stiffness (area)
Stability analyses performed on a full model showed that
the nets sufficiently constrained the 60m arch to buckle
in its second mode
Fig 9 Bari Stadium Italy
2 5 m
1 3 9 m m d i a CHS rib
Fig 10
Trang 5L O U V R E , PARIS
This project, completed in 1994, involved covering the three open courtyards of the Richelieu wing of the museum, to give enlarged gallery space for sculpture (fig 11)
The dimensions of the structural elements were an important consideration in the roof design, not only to reduce the visual 'weight' but also to avoid casting deep shadows at floor level within the new sculpture courts The courtyards taper in plan and spans vary from 28-41m The principal means of support are tied arches with radial ties providing restraint to in-plane buckling of each arch member (typically a 139 dia CHS) A spine truss mediates between the stiffness of the hipped ends and the interior arches
Trang 6C H U R S T A T I O N R O O F , S W I T Z E R L A N D
This project was the outcome of a public competition
won by architects Richard Brosi and Robert Obrist The
roof is a fully glazed vault covering both railway and
bus stations in a single span of 52m (fig 12)
The primary structure is a 10m deep tied arch with
intermediate radial ties providing restraint to buckling of
the principal compression members
Each "arch" is a pair of 460mm dia CHS slightly
inclined to one another as they pass over the vault but
converging elegantly onto a common springing point
(fig 13) The inclination of the ribs when combined
with the longitudinal purlins obviated the need for any
other bracing
The main support columns occur at 15m spacing and are
composed of a pair of 406 dia CHS and cantilever from
below (fig 14) They were chosen so as to be strong and
stiff enough to resist lateral wind but, importantly, not so
stiff as to generate untoward resistance to arch spread
under snow load or thermal expansion For a tie braced
arch of this type it is not possible to verify stability using
a conventional "Code" approach As with the previous
structures the Arup programme FABLON was used to
simulate elastic buckling of the framework and capacity
checks were performed using a Merchant-Rankine
approach in a manner consistent with Code
requirements This project received the ECCS Steel
Award of 1993
Fig 12 Chur Station, Switzerland
Fig 13 Chur Station, Switzerland
Fig 14 Chur Station, Switzerland
Trang 7A C K N O W L E D G E M E N T S :
The work of the above projects was carried out by a number of people Those working on the particular topics discussed were:
Thomson J o h n Hewitt, Brian Forster, Alistair Day Bukit Jalil Stadium : Tristan Simmonds, Andrew Trotman, Brian Forster
Youde Aviary : John White, Amanda Gibney, Brian Forster
San Nicola Stadium Tristram Carfrae, Brian Forster, Peter Rice
Richelieu Wing : Alexandre Cot, Alistair Lenczner, Peter Rice
Chur Station : Alistair Hughes, Matthew Lovell, Peter Rice
References:
1 Taylor W., Thornton J: From Schlumberger to the Dynamic Earth, a Sequence of Membrane Roofs , International Symposium
on Widespan Enclosures, University of Bath, April 2000
2 Day A.S: An Introduction to Dynamic Relaxation, The Engineer
219, 1965
3 Day A.S., Haslett T., Carfrae T., Rice P: Buckling and Non-Linear Behaviour of Space Frames, First International Conference on
Lightweight Structures in Architecture, Sydney, Australia 1986
Trang 8THREE WIDESPAN SPACE ENCLOSURES
Tim Macfarlane and Damian Murphy, Dewhurst Macfarlane and Partners
I N T R O D U C T I O N
We are currently constructing three projects in the USA
with roofs spanning between 180' and 420' The design
approach to each roof is fundamentally different and this
paper will discuss in broad terms the different
approaches
P H I L A D E L P H I A R E G I O N A L
P E R F O R M I N G A R T S C E N T R E
The roof geometry is a classical barrel vault within which
two major performance spaces sit as self-contained
structures (fig 1)
The brief called for a completely glazed roof surface with transparent end walls to the barrel to achieve maximum transparency The major axis of the vault is 350 ft long and the diameter of the vault is 174 ft
From the outset studies were carried out to find a structural system that would align with the glazing bars
to ensure that only the primary system would be visible,
to achieve the greatest transparency A folded plate barrel vault constructed of vierendeel frames was adopted, which allowed for simple flat glass panels measuring 3 ' 2 " x 7 ' 1 " to be framed onto the vierendeel members (Fig 2)
The vierendeel frames are fabricated from 5"x4" and 5"x5" tubes with wall thickness altered to reflect the changes in force between the crown and the springing
Trang 9Fig 2
point The fabrication process involves constructing 4
segments 1_ folds wide, welded and jigged in the
workshop and bolted on site at the member mid points
The sections will all be painted with the finish coat
applied prior to erection Fire protection which was
required for the lower 20 ft of the trusses was achieved
using a combination of sprinklers and intumescent paint
The glazed panels will be installed in bands of 3 units on
a minimal aluminium frame and the joints between
panels will be sealed with site-applied silicon The total
weight of steel is 825 tons which is equivalent to 27.0
lbs/ft2 of plan area The vierendeel frames provide
stiffness in the longitudinal direction as well as the span
direction, therefore no additional wind bracing elements
are required, resulting in a clean uniform structure
End Wall Design
The height of the end walls (Fig 3) varies from 84 ft at the crown to 0 at the springing point
Laminated glass panels _" thick measuring 5 ' 9"x 4 ' 2 " are attached to 7/8" diameter steel cables which are suspended from a steel arch and tensioned by attaching cast iron weights of up to 12 tons to each cable
The cables deflect horizontally under wind load up to
2 ' 8 " in the centre and the weights which are attached to the adjacent roof structure via a linked arm move up to
3 " vertically to accommodate the deflection of the wall This arrangement ensures that the load on the steel arch remains constant and that vertical deflection of the arch structure remains unchanged during variable wind pressure The weights are linked together to ensure that should a cable fail, the weight will be retained in place
by the adjacent cables Wind tunnel studies were carried out to ensure that the load variation in pressure which could occur would not cause unpredictable relative movement between adjacent cables
The project will be completed in December 2001
B O S T O N C O N V E N T I O N C E N T R E
The Boston Convention Centre (Figures 4 and 5) will occupy a site some 1800 feet by 500 feet wide with its major entrance addressing the revitalized old dock area and its rear end abutting the finer scale of residential South Boston Architecturally the 3 storey service buildings and hotels were designed as access strips running down each side of the 5 single storey visitor halls Each hall measured 300 feet square on plan and with the front end of the building the final 300 x 300 space was a three storey volume with reception and public function suites
The roof to the convention halls and reception area was conceived as a continuous surface 300 feet wide x 1800 feet long, changing in profile from an arched section at the entrance end with its crown 120 feet above ground,
to a flat section at the residential end with an elevation of
40 feet
At first sight the roof surface looks like a section of a regular solid The geometry however was more complex than this and each section through the roof had a different radius, crown and springing dimension
Initially a strategy was developed which separated the roof from the adjacent service buildings and from the bridge elements which connected these structures This resulted in a number of solutions which involved supporting each individual hall roof with 300 x 300 foot spans from up to eight columns set 60 foot in from the
Trang 11free edges The columns and steel roof trusses for this
structure were inevitably large (each one unique),
resulting in average weights of 25 lbs/sq ft for the roof
steelwork
Value engineering came close to reducing the
architectural gesture of a continuous roof plane to a
series of flat stepped surfaces At the eleventh hour a
solution was found which simplified the erection and
fabrication process and reduced the overall weight to less
than 20 lbs/sq ft
The isolation of the roof from the adjacent service
buildings and bridge links was reconsidered It was
established that the roof could be supported from and
braced by these elements, by introducing a sliding joint
that could accommodate thermal movement but was
capable of supporting vertical and horizontal wind and
earthquake forces Working with a nominal 60' long
W14 section, a surface was created by building out from
the corners of the 300 sq ft plan to each hall
The 60' length was established as the ideal length, both
for normal transportation and because at the steepest
curved section of the roof, a chord of 60' would result in
a maximum difference of only 2" between the actual and
ideal position of the beam, which could be easily
accommodated in the purlin connections
The construction involved lifting each steel beam into place, as a planar single 60' long member or as a 120' long trussed element fabricated on the ground from 60' long straight sections The only exception to this rule was the far corner pieces These were lifted as welded cruciform assemblies supported at three nodes by the boundary walls They offered a positional location at the fourth node for the 4 internal support columns which were then swung into place The remaining members were then lifted into place, building out from the corners using simply supported connections toward the centre defining the roof surface at the connection points, as construction progressed This configuration resulted in a 2-way spanning diagonal co-planar configuration, offering both vertical and horizontal stiffness due to the natural triangulation inherent in its constructional logic Metal deck on purlins or pre-fabricated triangular panels were then erected to complete the surface The 120' long fabricated king post trusses provided an excellent opportunity to incorporate the service walkways designed to run at 60' centres above the exhibition hall