1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

KẾT CẤU MỚI CONTROLLING THE INDOOR CLIMATE IN WIDE SPAN ENCLOSURES 4 CASE STUDIES

10 158 0

Đang tải... (xem toàn văn)

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 10
Dung lượng 1,68 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

To the Building Environmental Engineer it is generally not the overall size of a building that creates the challenge it is the internal height and the lack of suitable locations for indoor climate control systems. Large span structures are synonymous with high open spaces. The Engineer seeks to control not only thermal conditions but also Indoor Air Quality (IAQ) both to achieve comfortable conditions within the occupied space and to maintain a healthy environment free from pollutants (of which there are many). Ideally the Engineer would seek to condition the occupied space rather than the whole volume and hence benefit from both reduced plant capacity and reduced energy consumption and C02 emissions. This is not always possible. The temperature within a large space can be controlled using air systems or radiant systems. Indoor Air Quality (IAQ) can only be controlled using fresh air (usually outdoor air). Many systems tend to combine the temperature regulation function with the IAQ function.

Trang 1

CONTROLLING THE INDOOR CLIMATE

IN WIDE SPAN ENCLOSURES

4 CASE STUDIES

Nick Cullen Hoare Lea & Partners - Consulting Engineers

S Y N O P S I S

This paper presents four case studies of different large

span structures, describing the characteristics of, and the

systems used to control, the indoor climate

The first two studies consider the difficulties inherent in

designing systems that 'fight' against the basic laws of

physics The first of the two, the British Aerospace

Aircraft Assembly Hall is based on work undertaken in

the 1980's and highlights the significance of buoyancy

forces and the difficulty in mixing airstreams of different

temperatures The second case study, the ExCel

exhibition centre in London's Docklands, highlights the

need for compromise in the design of Engineering

systems

The second two studies review projects in which the

designs made use of the natural forces of gravity and

buoyancy in order to maintain thermal and Indoor Air

Quality (IAQ) conditions The first, the Millennium

Stadium Cardiff, features a fully retractable roof and

relies upon Natural Cooling and Ventilation enhanced

with the operation of the smoke extract fans as necessary

The final Study details the work undertaken at the House

of Representatives, Brasilia the Capital of Brasil It

discusses the significance of control and alternative

strategies

I N T R O D U C T I O N

To the Building Environmental Engineer it is generally

not the overall size of a building that creates the

challenge it is the internal height and the lack of suitable

locations for indoor climate control systems Large span

structures are synonymous with high open spaces

The Engineer seeks to control not only thermal

conditions but also Indoor Air Quality (IAQ) both to

achieve comfortable conditions within the occupied

space and to maintain a healthy environment free from

pollutants (of which there are many) Ideally the

Engineer would seek to condition the occupied space

rather than the whole volume and hence benefit from

both reduced plant capacity and reduced energy

consumption and C 02 emissions This is not always

possible

The temperature within a large space can be controlled using air systems or radiant systems Indoor Air Quality (IAQ) can only be controlled using 'fresh air' (usually outdoor air) Many systems tend to combine the temperature regulation function with the IAQ function

The problem faced by Engineers is that hot air rises, or more accurately, cold air falls and forces warmer air to high level leading to temperature stratification within the space This fundamental law of physics can work to the Engineers advantage A case in point being Displacement Ventilation Systems (natural or mechanical), which rely upon buoyancy and gravity forces to drive them However displacement air systems require the supply air

to be introduced at low level and at regular -albeit fairly large -intervals This is rarely compatible with the needs

of large span structures and indeed is often in conflict to the use of such structures

The consequences of stratification are twofold Firstly, the increased temperature differential at roof level results

in a greater heat loss increasing energy consumption and thereby C 02 emissions Secondly, thermal conditions within the occupied zones may at times be unsatisfactory, depending of course, on the location of the occupants

High spaces are generally conditioned using mixing systems with the supply air introduced at high level, the objective being, to minimise stratification by producing a fully mixed environment The designer has to ensure that when heating the supply air can deliver heat to low level and when cooling the air arrives at low level without causing discomfort due to cold drafts In the process of creating a mixed condition, pollutants, produced within the space, are diluted by 'fresh' air

The alternative, that of displacement ventilation, seeks to condition and removes pollutants only from occupied zone

Trang 2

C A S E S T U D Y N O l

B R I T I S H A E R O S P A C E A I R C R A F T

A S S E M B L Y H A L L , B R I S T O L

" T H E B R A B A Z O N H A N G E R "

BACKGROUND

The aircraft assembly hall was constructed in the 1940's

for the specific purpose of constructing the Brabazon

aircraft, the largest aircraft in the world at the time The

building's clear height (23m) was determined by the

height of the Brabazon tailfin and its clear internal span,

by its wingspan Its overall internal height reaches 35m

At the time the building was completed, it was one of the

largest clearspan structures of its type in the world Its

floor area was approximately 30,000m2 and enclosed a

volume of 1,000,000m3 (Figures 1&2)

Height to Eaves 26 m Height to Apex 35 m Floor Area 30,000 m 2

Total Volume 1 mi 1.1 ton

Fig I The Brabazon Hanger - Exterior View

Fig 2 T h e Brabazon Hanger - Interior View

EXISTING HEATING SYSTEM

The original (1940's) heating system comprised steam unit heaters at catwalk level blowing air vertically down into the space At the perimeter of each bay were located

a row of "swan neck" steam heaters which drew cool air from low level, heated it, and discharged the warm air down towards the hangar floor from a height of about 10m (Figure 3) By 1980 the steam pipework was beyond its useful life and had significant leakage problems The pipework was poorly insulated, mainly with asbestos and as a consequence, apart from the health issues of asbestos the operating efficiency of the system was extremely poor Furthermore, under test it was found that the unit heaters at catwalk level gave insufficient velocity to the hot air to overcome its inherent buoyancy The heated air lost any momentum after the first few metres and rose back up to high level Thus, only the perimeter "swan neck" heaters provided any useful heat to the hangar floor, the remaining capacity being used to heat the roof space Temperatures

at roof level rose regularly towards 40°C in the vain attempt to hold a comfortable temperature within the occupied zone (Figure 4)

He,! Lot* through Roof

Down draught heaters dine!

airdowtw >nry3m Swan Neck Darcharge

C R O S S S E C T I O N - C E N T R E S P A N )

Fig 3 Existing Heating Sytem

Improved thermal performance Reduced heat Ion leading to increase tn temperature

CROSS SECTION -CENTRE SPAN) ORIGINAL ROOT 4 HEATING SYSTEM

CROSS SECTION -CENTRE SPAN) NEW ROOF 4 HEATING SYSTEM

The building has always been difficult to heat effectively

In the early 1980's a complete re-cladding of the building

was undertaken to upgrade the performance of the

building envelope to comply with the Building

Regulations standards of the day Sadly, the cost of

upgrading the doors was prohibitive, a feature which we

will return to later

Fig 4 Temperature Profiles

NEW HEATING SYSTEM

Immediately following the recladding contract, Hoare Lea & Partners were commissioned to design a new direct gas fired heating system to replace the original steam fired system The concept was to replace the

Trang 3

existing steam heaters at catwalk level with direct gas

fired unit heaters, blowing vertically downwards from a

height of 23m (Figure 5) The existing perimeter heaters

were to be modified, and instead of blowing warm air

down to low level, they were to draw cool air from low

level and to discharge the air vertically upwards, mixing

the cool air with warm air at high level, inducing

destratifying circulation currents within the space

Fig 5 Proposed New Heating System

The concept had been developed in conjunction with Bristol

University who carried out performance monitoring on the

existing system and then on a trial mock up, modifying one

of the perimeter "swan neck" heaters Initial results were

promising, showing a much reduced temperature gradient in

the space

The team identified the proposals as carrying significant,

technical risk, there being no precedent for use of reverse

destratification system, least of all, on a building of this size

In order to offset this risk, the team applied to the EEC for a

Thermie Grant which was subsequently awarded, in

recognition of the innovative nature of the project

The client embarked on a significant construction contract,

comprising the removal of the existing heating system,

including the steam pipework installation, asbestos

insulation and heaters In its place was installed a new gas

pipework, new power distribution system, fan powered unit

heaters complete with discharge jet nozzles The complete

installation was undertaken, at a height of 23m, whilst

maintaining production on the factory floor This required

significant protection measures to be provided to allow the

building occupants to continue working safely Key design

considerations involved reducing C 02, and moisture levels

in the space to acceptable levels by introducing fresh air

through perimeter units The design of the heaters, and

"swan neck" discharge nozzles was also critical to give good

air mixing and air distribution

The designers struggled to balance the design parameters of

heat input, air velocity, noise and power consumption and

cost and eventually arrived at a "best fit" solution

P E R F O R M A N C E After completion of the installation, the performance of the heating system was monitored to assess whether the predicted performance was achieved in practice The results were dramatic

The delivery of air at 45°C to the hangar floor from a height of 23m required a substantial discharge air velocity At part load conditions, when the discharge temperature was lower, the high discharge velocity was not dissipated, so that a very high air movement occurred

at low level It was decided to accept a restricted turndown ratio on the units, typically to a minimum of 80% of full heat output, the fans being controlled

"on/off below this level

The building fabric, and particularly the old hangar doors, were found to allow a considerable amount of cold air to infiltrate into the building As a consequence of the density of this cold infiltration, it tended to collect at low level creating a cold "lake" of air at about 10°C in the first 2m above the hangar floor, the very zone that was required to be heated

Under full load output from the heaters, operating in response to temperature sensors located in the cool occupied zones, the buoyant warm air was found to have lost most of its momentum by the time it arrived at the bottom 2m zone The discharge air suddenly moving in 10°C set, not 20°C ambient air, effectively "bounced" at this 2m level, providing very little heating effect in the occupied zone As a consequence, the whole volume of the hangar was being heated to a temperature of 20-25°C, in order to maintain I0°C in the occupied zone (Figure 6)!

^t^+HMt Low through Roof

, ""1

a Entrained Air item high lev e mixes ' 20*C With raster dBchtrge Air

C R O S S S E C T I O N - C E N T R E SPAN)

Fig 6 Actual Performance

M A I N ACCESS D O O R

Paradoxically, the solution to this problem was to reduce the maximum heat output of the gas heaters, lessening the buoyancy of the supply air, which enabled proper penetration by the supply air into the occupied zone, and good mixing in that space

Trang 4

The modified "swan neck" destratification units were

found to have minimal effect in destratifying the space,

the temperature profiles and airflow patterns being

determined primarily by the velocity and discharge

temperature of air from the direct fired gas heaters

Of course with hindsight the solution should have

included:

(i) an increase the thermal performance of the

doors

(ii) a reduction in the infiltration leakages of the

building

Had it been practical within the constraints of an

operational production facility, the provision of a warm

floor by embedded piping or by overlaid radiant heaters,

may have overcome many of the problems

C A S E S T U D Y N O 2

E X C E L L O N D O N , R O Y A L V I C T O R I A

D O C K

INTRODUCTION

Across the river from the Millennium Dome on the North side of the Thames a New "State of the Art" exhibition centre is about to open Phase 1 of the project will provide 93,500m2 of accommodation including 64,000

m2 of exhibition space split between two halls Each hall

is designed with a minimum clear height of 10m The entire exhibition space is located above a car park A boulevard running the length of the building separates the two column free halls The whole building can operate as a single exhibition space or be sub-divided down into individual halls each of 4000m2 (Figure 7)

Fig 7 Excel Exhibition Centre - London Docklands

VALUE MANAGEMENT

The indoor climate control system was divided according

to the minimum module size A single air-handling unit serves each module and is located at high level within the structural depth of the roof Supply air ductwork from the air-handling unit is distributed at high level (Figure 8) Out door air is drawn in via a 'beehive' air intake the amount being determined either, by Indoor Air Quality (IAQ) as measured by C Oz sensors, or according to the free cooling opportunities As extract air is drawn it passes directly from the space and discharges to out doors

Intake Air Exhaust Air

Supply Air via Long throw Diffisers

EzUbitlonHal]

I Clm

r

Boulevard Supply Air via Long throw Diffisers

EzUbitlonHal]

I Clm

r

90m

Fig 8 Excel Exhibition Centre - London Docklands - Diagramatic

Trang 5

The exhibition space required both cooling and heating

The supply air system therefore had to operate to deliver

warm buoyant air to low level during heating, and cool

non-buoyant (heavier) air during cooling The obvious

answer was to vary the trajectory of the supply air

according to the supply air temperature by using

adjustable geometry diffusers This however proved to be

too costly and would probably prove to be unreliable and

an alternative approach was required

The alternative proposal envisaged a fixed airflow

trajectory with long throw nozzles fixed directly into

ductwork and arranged in groups With volume flow rate

and design supply air temperatures, fixed, two variables

remained under the designers control, discharge velocity

and trajectory (Figure 9) Using Computation Fluid

Dynamics combinations of the different parameters were

tested in both heating and cooling modes

Computational Fluid Dynamics, not available at the time

the design of Brabazon Hanger Design was employed to

assess options and performance of the design (Figure 9)

RESULTS

The results from the analysis showed that the cold slab

(due to the unheated car park below) would create a

'lake' of cold air at low level which could be reduced in

depth by increasing the momentum of the supply air, but

could not be completely overcome Once again the

conclusion pointed to the need for a warmed floor which

was beyond the budget (Figure 10)

The CFD modelling images brought instance 'Deja vu' to

the (by now Partner) engineer who years earlier had

experienced the Brabazon hanger or refurbishment and

its outcome

It was recognized that the primary circumstance likely to

occur was that of cooling and so parameters were

selected to satisfy the associated thermal comfort

conditions

Engineering designers learn very early that compromise

will be called for, that compromise often involves

designing to satisfy the primary circumstances When

warmth from exhibits and people will require a cool air

supply from the building systems That lessens the

outstanding probability that when a few people rent a

small amount of the space in colder weather they may

find a bracing experience requiring a pullover Satisfying

the majority that is now called value judgement and is an

essential part of an engineer's experience

Figure L5 (a) Temperature distribution at height of 1 5m

Fig 9 Results - Computational Fluid Dynamics

2 3 B

Winter model, no occupancy Winter model- Low level occupancy

Fig 1 0 Results - Computational Fluid Dynamics

Trang 6

Fig 11 Millennium Stadium Cardiff - Exterior View

C A S E S T U D Y N O 3

T H E M I L L E N N I U M S T A D I U M C A R D I F F

I N T R O D U C T I O N The £120million Millennium Stadium Cardiff has a capacity of 72,500 people and is the first UK arena to have a fully retractable roof It provides a multi-use all weather venue with completely un-restricted views The grass pitch is completely removable allowing the arena to

be put to use as a concert venue The stadium takes the form of a bowl complete with retractable roof This form Fig 12 Millennium Stadium Cardiff - Interior View clearly limits the Natural ventilation and cooling

mechanisms that act around stadia with open corners

The retractable roof (Figure 11 & 12), when closed, created a number of problems that the designers needed

to resolve Firstly the space needed to be ventilated to remove unwanted heated and metabolic pollutants Ventilation was also an important factor in maintaining a healthy grass pitch Secondly it had to be safe, allowing spectators to escape in the event of a fire

Trang 7

The arena was conceived as being Naturally Cooled and

Ventilated using the vomitory passage ways and a

high-level louvre system as air paths Numerous different

scenarios were considered using Computational Fluid

Dynamics (CFD) The Criteria set for the Stadium was

for all occupied areas to remain below 28°C at design

summer conditions (26°C) The effect of different sized

openings, their number and location were investigated

The initial analysis assumed a worst-case scenario of

stack driven ventilation only without wind assistance

The analysis showed the need for two sets of parallel

louvres running at high level , one at the junction

between the retractable roof and the fixed roof and the

around the back of the upper tier seating Temperatures at

high level varied only slightly between the various

options (Figure 13) The arrangement operated primarily

using Natural buoyancy effects and, when available,

wind pressure to drive air through the arena The smoke

extract fans are made available to guarantee a minimum

volume of fresh air movement through the arena

CFD modelling showed that the combination of vomitary

and high level openings produced acceptable conditions

with the roof closed even without the beneficial effects of

wind or with the fans running

& P A R T N E R S

26 0

Cardiff Millennium Stadium

Fig 13 Results - Ventilation and Cooling CFD Results

FIRE The fire engineering for public arenas is vitally important The objective was to determine whether, in the event of a fire, there would be sufficient time for the audience to escape This time for full evacuation from the arena was calculated as 12 minutes taking into account detection, investigation, action and evacuation times In addition a smoke temperature limit of 200°C and a visibility distance of 25m to a reflective sign were adopted, as design criteria

Being primarily a sports stadium the potential fire load was minimal It was considered that a pop concert with a stage located at one end of the pitch was the worst case scenario The effect of the operation of the mechanical extract system was investigated using Warrington's Fire Research CFX CFD software

The results highlighted two important factors Firstly that the depth of the smoke was worst at the end of the stadium closest to the fire (Figure 14) The time available for escape in these areas did not meet the design criteria and people could not be located in these areas

Secondly the operation of the fans provided an additional

2 minutes escape time extending the period to 14 minutes for the topmost seats The extract temperature of the smoke was estimated as being between 39°C and 43°C, well within the operational capability of the fans (Figure 15)

Time: + 1 2 minutes

0 0 0 0 0

Fig 15 Computational Fluid Dynamics - fire/smoke - fans operational

Fig 14 Computational Fluid Dynamics - fire/smoke - no fans

Trang 8

C A S E S T U D Y N O 4

H O U S E O F R E P R E S E N T A T I V E S ,

B R A S I L I A N C O N G R E S S B U I L D I N G S ,

B R A S I L I A , B R A S I L

In late 1997 Hoare Lea & Partners Research and

Development group were asked to offer advice on the

problem of acute 'Sick Building Syndrome' in the House

of Representatives at the Brasilian Congress The

particular Building, is that pictured and constructed in

the 1960's to designs by the renowned Architect Oscar

Niemeyer (Figure 16)

Fig 16 House of Representatives, Congress Building, Brasilia

-Exterior View

The House of Representatives is one of two chambers

(plenaria) in the Congress building complex and it measures

some 30 m in diameter and 15m high The plenaria has

capacity for up to 550 people made up both of Representatives

and a smaller number of journalists A raked gallery for

'spectators' overlooks the chamber, encompassing 3/4 of the

high level perimeter, but this is isolated from the chamber by a

glass screen (Figure 17 & 18)

Fig 18 House of Representatives, Congress Building, Brasilia -Interior View towards Podium

The building had been reported as 'sick', indeed a Government Minister had passed away it was said,

"because of the amount of his time he had spent in the building" An initial visit and inspection of the air supply system indicated that the system was clearly at the end of it's serviceable life It also had some inherent design problems most notably the absence of any system of air extraction other than by tortuous route out of the chamber via the main entrance doors which had to be left open (Figure 19)

Fig 19 House of Representatives, Congress Building, Brasilia -Schematic representation of existing ventilation and cooling system

Hoare Lea and Partners were asked to put forward a scheme which after much consideration was based on Displacement Ventilation principles Unlike the first two case studies displacement ventilation is a system that relies upon natural forces to function Cool fresh air is introduced at low level and is drawn towards any heat source where is warms and is 'displaced' to high level taking with it unwanted heat and pollutants The polluted air can be extracted and thrown away having first passed through heat exchangers

Trang 9

Two alternative schemes were studied and each was

modelled using Computational Fluid Dynamics The

favoured scheme envisaged the installation of a

compartmented raised floor through which air would be

delivered to air terminals integrated into the seat The

floor would double as a conduit for power and data

cabling (Figure 20)

Schematic of Proposed New

Displacement Ventilation for

dulled AHeattng Water from Existing Central Plant

-Fig 20 Schematic of proposed new displacement ventilation

The alternative method was to introduce the air around the

perimeter of the space a scheme that would have required

only a small raised platform

The size of the space highlights another inherent problem of

large spaces not so far mentioned, that of locating control

sensors This problem exists irrespective of the parameter

being measured

Ideally the sensor should be located at regular intervals

within the occupied zone, but without a surface on which to

mount the sensor an alternative strategy is required The

walls around the chamber offered possible locations but were

rejected due to their variable surface temperature and

unrepresentative location

The main concern was the IAQ within the space and the

main pollution sources both of heat, chemical and biological

contamination were the occupants themselves The quantity

of air could therefore be varied according to the number of

occupants within the space Whilst C 02 sensors are regarded

as a good measure of IAQ when people are the main

pollutant source, they were considered to be too much of an

on-going maintenance item requiring regular re-calibration

Two alternative strategies were conceived The first was the

inclusion of a variable volume damper within the

construction of the seat itself This would enable the

associated diffuser to deliver fresh air only when the seat was

occupied A background supply would be guaranteed

through other diffusers The alternative was simply to count,

electronically the number of people within the space and

then deliver an appropriate volume of fresh air This would

rely upon the characteristic of displacement ventilation for

the air to be drawn to the heat sources within the room Both

these options would have resulted in energy and C 02

consumption reductions

Ka.-il.aii loi'iKc&t - under Lest tolut>

• • i ->' - of Temper&l'j'e tl)

Fig 21 C F D Results - Velocity Vectors - Temperature Supply

Riri/'iian Conor Case 2 S

Vekioty Victors Gotwrt C> Vckc-oty Magn-tuOo (nvs)

RMHAJNS 4.2 pa to i :

Thu Apr te-W8 ;

Fig 22 C F D Results - Velocity Vectors - Perimeter Supply

Rrf.7t»u*nCuiiti(e** C&ce 2»

Vei»:*v Victors Ccwaoa Dv V**fflv Magirtudo (m/s) Cioss section at tortus • 20m

eiuonfUNS 4.2 0(1 he) Thu Ap» 16 -aSK) Fluefil inc

Fig 23 CFD Results - Velocity Vectors - Perimeter Supply

B 'tU 'haii Cu tyieu Cass 1

••'-•>:•< V6CKHSCokxM r e • "

Cress free non at racJus - 25nt

E H«1H : NS4.2(3J M»2.W unstMQY

Fn Apt 17 1998 Hurt I K ,

Trang 10

RESULTS

The results confirmed the design supply air volume was sufficient to maintain thermal conditions within acceptable limits in both cases (Figure 21) It did however identify that the alternative perimeter supply solution generated a 'dough-nut' vortex which had the effect of driving high level polluted air to low level back down into the occupied zone This was due to three factors Firstly the massing of heat sources created a coalescence of individual plumes which rose to high level Secondly the thermally cool surfaces of the glass divide between the gallery and plenaria generated a down flow of air Thirdly the rising plumes of air drew air from the perimeter supply points The combination of these three characteristics generated the vortex (Figure 22 & 23) In contrast the favoured option with the supply air introduced on a seat by seat basis showed a less vigorous air movement with a general, albeit un-steady drift of air flow to high level (Figure 24)

The project proposals await approval and finance from the government which, unlike our own, of whatever party, is very concerned not to spend money on it's own accommodation whilst there are calls for money from its populace

CONCLUSION

Wide span structures enclosing large volume high spaces present the Building Engineer with significant challenges The Building Environmental Engineer seeks

to control the conditions within the occupied space with the minimum of 'environmental impact' Numerous different scenarios often need to be considered The function of the space along with cost restrictions often force the Professional Engineer to design systems that fight the basic laws of physics and to seek compromises

in performance The advent of CFD has given the Engineer an invaluable tool enabling the prediction of the performance and comparison of different engineering systems Despite the rapid growth in computer power we are still limited to making only global assessments of large spaces

Ngày đăng: 09/06/2015, 17:22

TỪ KHÓA LIÊN QUAN

🧩 Sản phẩm bạn có thể quan tâm