Petroleum Engineering 405 Drilling Engineering * Well Drilling Engineering Directional Drilling Dr DO QUANG KHANH * Directional Drilling When is it used? Type I Wells Type II Wells Type III Wells Dire[.]
Trang 1Well Drilling Engineering
Directional Drilling
Dr DO QUANG KHANH
Trang 2 Type III Wells
Directional Well Planning & Design
Survey Calculation Methods
Build and Hold Build-Hold and Drop Continuous Build
KOP EOC
Trang 3Read ADE Ch.8 (Reference)
Trang 55
Trang 6Max Horiz Depart.
?
Trang 77
Trang 1010
Trang 12Type I Type II Type III
Build
and Hold Build-Hold and Drop Continuous Build
KOP EOC
Trang 1318 r
Trang 1414
Trang 15Fig 8.11
4 2
1 3
Trang 164 2
1 3
Trang 17N18E
N55W S20W
S23E
Azimuth Angle
Trang 1818
Trang 19Example 1: Design of Directional Well
Design a directional well with the following
restrictions:
• Total horizontal departure = 4,500 ft
• True vertical depth (TVD) = 12,500 ft
• Depth to kickoff point (KOP) = 2,500 ft
• Rate of build of hole angle = 1.5 deg/100 ft
• Type I well (build and hold)
Trang 20Example 1: Design of Directional Well
(i) What is the maximum hole angle
required.
(ii) What is the total measured depth (MD)?
(MD = well depth measured
along the wellbore,
Trang 21* The actual well path hardly ever coincides with
the planned trajectory
* Important: Hit target within specified radius
Trang 2323
Trang 24(20)