Additional Analysis y Central Plant and Distributed SSystems DOBER LIDSKY MATHEY... STEAM ABSORPTION CHILLERS35 PSIG STEAM FROM PLANT MORGAN HALL 446 TON 446 TON ABSORBER 446 TON ABSORBE
Trang 1l Goals
Trang 3l f Current Plant Information
Trang 4Summary of Preliminary Findings
Trang 5d Wind Generation
Trang 7l ( ) Solar (Concentrating)
Trang 8l l Fossil Fuels
Trang 9l Coal ‐ Current
DOBER LIDSKY MATHEY
Trang 10d Wood
Trang 11Additional Analysis y Central Plant and Distributed
SSystems
DOBER LIDSKY MATHEY
Trang 12b Remaining Systems or Combinations
• Fuel sources
– Natural gas
• Biomass generation of gas – Electricity
– Ground water source hybrid system
Trang 13bl h l f Establish Baseline for Comparison
Trang 14l Natural Gas
Trang 15l d Baseline Cost and Scope
Trang 16l b ? Eliminate Steam Turbine Generator?
Trang 17l Evaluation
Trang 18Conclusion: Replace steam chillers with electric centrifugal
Trang 20ELECTRIC CHILLERS V STEAM ABSORPTION CHILLERS
35 PSIG STEAM FROM PLANT
MORGAN HALL
446 TON
446 TON ABSORBER
446 TON ABSORBER
446 TON ABSORBER
446 TON
TO CAMPUS RUBBERMAID
CENTER
CURRENT CHILLER SYSTEM SCHEMATIC
CONDENSATE RETURN CENTER
CURRENT CHILLER SYSTEM SCHEMATIC
Trang 21l d b ( l ) Centralized Microturbines (natural gas)
Trang 22C C O CENTRALIZED MICROTURBINE
NEW NATURAL GAS
NEW BOILER
NEW BOILER
EXISTING BOILER
EXISTING TURBINE
375 KW ELECTRICITY NEW
MICROTURBINE MICROTURBINE
Trang 23l d b Centralized Microturbines
Trang 24into gas
Trang 28b d l Distributed vs. Central Generation
Trang 29l h l b d Solar – Photovoltaics – Distributed
Trang 30l h l b d
Solar – Photovoltaics – Distributed
– 45,000 square feet building– 3 stories
– 15,000 square feet of roof area– 80% of roof covered with PV array = 12,000 square feet array– PV generates about 10 watts/square foot of panel
– This yields a 120 kW system– Approximate installed cost of $6/watt = $720,000– Each installed kW produces about 1,100 kWh/year– 132,000 kWH not purchased from an electric company
Trang 31– 30% Federal Tax Credit– $150,000 State Grant - figured first– Net Cost: $399,000
– ROI of 1.6% per year
within the next three years Assuming incentives are still in place at that
time, this results in an ROI of 4.3%
DOBER LIDSKY MATHEY
Trang 32h l b d Geothermal ‐ Distributed
Trang 33d l ( l ll) Energy Modeling (Taylor Hall)
etc) as in renovating Taylor Hall
approximate size of Taylor Hall
The systems considered were as follows:
DOBER LIDSKY MATHEY
Trang 34SPLIT SYSTEM VAV
THIS IS A REPLACEMENT SYSTEM CONSIDERATION FOR TAYLOR HALL
NEW AIR COOLED CONDENSING UNIT
REFRIGERANT PIPING
EXISTING SUPPLY DUCT SYSTEM
NEW AIR HANDLING UNIT PIPING
NEW TERMINAL BOX (TYPICAL)
SYSTEM SCHEMATIC
* NEW DDC NETWORK INCLUDED
SYSTEM SCHEMATIC
Trang 35BOILER AND CHILLER CONTAINED IN BUILDING
NEW COOLING TOWER
NEW CHILLER
NEW AIR HANDLING UNIT
NEW CONDENSING
BOX (TYPICAL) GAS
SYSTEM SCHEMATIC
* NEW DDC NETWORK INCLUDED
DOBER LIDSKY MATHEY
SYSTEM SCHEMATIC
Trang 36CENTRAL PLANT
TO TERMINAL UNITS
EXISTING HEAT EXCHANGER
HEATING WATER SYSTEM
EXISTING SUPPLY DUCT SYSTEM STEAM
NEW AIR HANDLING UNIT SYSTEM
CWS
NEW TERMINAL BOX (TYPICAL)
Trang 37GROUND WATER SOURCE HEAT PUMP
NEW DEDICATED OUTSIDE AIR OUTSIDE
SYSTEM AIR
REPLACES (E)AHU
EXISTING SUPPLY DUCT SYSTEM
VERTICAL WELL FIELD
MULTIPLE (1 PER TERMINAL BOX), COMPRESSORIZED WATER SOURCE HEAT PUMPS
Trang 39d l l l ll Modeling Results ‐ Taylor Hall
Existing Dx $0 $48 700 * 296 00 *
Existing Dx $0 $48,700 296.00
Split System Dx $1,021,000 $45,100 0.4% 284.00 4.0 Boiler/Chiller $1,150,000 $44,590 3.2% 250.80 15.3 Central Plant** $1,290,000 $47,440 0.5% 264.09 10.8 GWSHP $1,480,000 $25,300 5.1% 91.23 69.2 GWSHP Hybrid $1,239,000 $26,410 10.2% 76.64 74.1
• The hybrid system provides a 28.2% reduction in CO2 emissions and an 8.6% ROI.
* This system is the baseline comparison.
** System includes 500 feet distribution pipe and a portion of the plant cost.
*** ROI based on change over Split System Dx upgrade price, but current energy cost.
DOBER LIDSKY MATHEY
Trang 40f ld ld ( f ) Greenfield Building (44,000 square feet)
Dx System $1 012 000 $43 100 * 284 *
Dx System $1,012,000 $43,100 284
Boiler/Chiller $1,232,000 $44,590 0.2% 251 11.7 Central Plant** $1,408,000 $47,440 -0.6% 264 7.0 GWSHP $1,320,000 $25,300 6.4% 91 67.9 GWSHP $1,320,000 $26,410 6.1% 77 73.0
Trang 42Mi bi Di ib d
Microturbines Distributed
conversion efficiency, includes maintenance cost increase
geothermal system
Trang 43Conclusions and Recommendations
– Natural gas conversion from coal– Replace steam absorption chillers with high efficiency electric
– Ground water source heat pumps in a hybrid system
– If building has a large 'base' heat load and geothermal is not feasible, microturbines should be reviewed
– Pursue identifying local waste streams
– Install a digester to “offset” carbon footprint
DOBER LIDSKY MATHEY