Managing the Construction Phase A Guide for Project Administration Contents A Guide for Project Administration...1 Contents...1 Introduction to Construction Phase...4 Construction Start
Trang 1Managing the
Construction Phase
A Guide for Project Administration
Contents
A Guide for Project Administration 1
Contents 1
Introduction to Construction Phase 4
Construction Start-Up Activities 5
Approving Contractor Schedules 5
The Construction Schedule 5
The Initial Schedule of Values 7
Conducting the Pre-Construction Meeting 10
Notifying Meeting Participants 10
Setting the Agenda 10
Obtaining and Checking Permits 18
Obtaining a State Building Permit 18
Obtaining an NPDES Permit 31
Daily Activities 32
Weekly Activities 34
Administering Progress Meetings 34
Preparing the Agenda 34
Preparing and Distributing Meeting Minutes 35
About Coordination Meetings 36
Coordination Drawings and Shop Drawings 36
Monthly Activities 37
Approving Contractor Pay Applications 37
Timing 40
Components of the Pay Application 40
Trang 2Reasons to Reject a Pay Application 52
The Final Pay Application 56
Approving Updated Construction Schedules 58
Ongoing Activities 59
Managing Project Changes 59
Reasons for Change 59
Processes for Making Changes 59
Approving Shop Drawings 65
About Shop Drawings 65
Approval Requirements 65
Figures
1 Initial Schedule of Values
2 Pre-Construction Meeting Notification
3 Contractor Information Sheet
4 Ohio Application for Plan Approval
5 Worksheet for Fees to Be Paid
6 Plumbing Fee Schedule
7a–d Contractor Pay Application:
Cover Sheet Contract Cost Breakdown and Partial Payment Sheet Summary of Change Orders Sheet
Schedule of Values
8 Notice of Fixed Retainage Amount
9 Certification of Material Stored At Site
10 Certification of Material Stored Off Site
11 Pay Application Rejection Letter
Charts
Page 2 Revised June 2002Managing the Construction Phase
Trang 3Changes to Managing the Construction Phase
Revision 2, June 2002
Changes made as part of this revision appear with a in the margin
Industrial Compliance’s recommendation that UC applicants use the University’s credit card to pay building permit fees associated with smaller projects
2
Trang 4Introduction to Construction Phase
The construction phase encompasses all activities between the Contractor’s receipt of the Notice to Proceed and the completion of construction (Project acceptance and closeout activities will be covered in a future
communication.) This chapter presents Project Administration’s activities during the construction phase according to their usual timing and frequency:
Trang 5Construction Start-Up Activities
Construction start-up activities for the Associate Architect
or Project Administrator (as applicable for the project) include the following:
from the State, and ensuring that Contractors have obtained any required permits from local authorities
Approving Contractor Schedules
Both the Project Administrator and the Associate (if the project uses an Associate) must review and approve two types of Contractor schedules:
The Construction Schedule
The Lead Contractor must submit an initial Construction Schedule to the Associate Architect (or directly to the Project Administrator, if the project does not use an Associate)
To develop this Construction Schedule, the Lead Contractor must obtain input from all prime Contractors on the project.The Construction Schedule can then be developed to reflectall Contractors’ activities and milestones
All the prime Contractors must sign the Construction Schedule before it is submitted to the Associate or Project Administrator Signatures indicate the Contractors’
agreement that the milestones and contract completion date can be met as shown on the schedule
The initial Construction Schedule must show completion of the contract by the date specified in the Notice to Proceed
Trang 6The Construction Schedule will change as the project movesforward The Lead Contractor must monitor overall
construction progress against the schedule and make revisions as necessary, providing an updated Construction Schedule to the Associate or Project Administrator at least once monthly (see “Approving Updated Construction
Schedules”)
Page 6 Revised June 2002Managing the Construction Phase
Trang 7Requirements for Construction Schedules
The following sections present an overview of requirements for the presentation and content of Construction Schedules.More detailed information can be found in the cited sections
of the University’s Front-End Specifications (General Conditions), which are provided to all Contractors and
Requirements for Construction Schedules are detailed in theproject’s General Conditions (Article 4.3, “Construction Schedule”) The Project Administrator must become familiar with this section of the specifications
The Initial Schedule of Values
The Contract Cost Breakdown and Partial Payment
“Contractor Payment”, of the project’s General Conditions The Schedule of Values sheet is used to break the
Contractor’s project responsibilities into individual, level items of work (Depending on the size of the project, the Construction Schedule may provide further work
high-breakdown.)
At project startup, each prime Contractor submits a Schedule of Values with only columns 8a–8e completed:
Contractor’s scope
material
The Associate (if applicable) and the Project Administrator must approve the Schedule of Values before the Contractor will be paid The Project Administrator’s and Associate’s signatures confirm their agreement with the Contractor’s cost breakdown for the project
Schedule of Values as part of each scheduled payment request These submittals show the Contractor’s costs for the pay period indicated When approving a pay
application, the Project Administrator (and Associate, if applicable) must confirm the Contractor’s statements
Trang 8regarding the percentage of work that is complete See thesection “Approving Contractor Pay Applications”
Figure 1 on the following page shows a Contractor’s initial Schedule of Values
Page 8 Revised June 2002Managing the Construction Phase
Trang 9Figure 1: Initial Schedule of Values
Trang 10Conducting the Pre-Construction Meeting
Before construction begins, the Project Administrator must schedule and conduct an initial meeting of all prime
Contractors and the Associate Architect (if the project uses
an Associate)
This pre-construction meeting should have the following objectives:
Notifying Meeting Participants
Once a date has been set for the pre-construction meeting, the Project Administrator or a support staff member should prepare a meeting notification and distribute it to all
Contractors and the Associate A template for the construction meeting notification appears on the following page as Figure 2
pre-Setting the Agenda
The sections that follow present typical discussion topics for
a pre-construction meeting Depending on the project, all
or a portion of these topics may need to be included on the agenda The list is not necessarily all-inclusive
Introduction
The meeting can help establish an atmosphere of teamworkand cooperation among the University, Associate, and Contractor personnel who will work on the project The Project Administrator can begin the meeting by having all
Page 10 Revised June 2002Managing the Construction Phase
Trang 11attendees introduce themselves A sign-in sheet should be circulated during the meeting to record attendance
Trang 12Page 12 Revised June 2002Managing the Construction Phase
Figure 2: Pre-Construction Meeting Notification
University of Cincinnati Office of the University Architect Department of Construction Management
PO Box 210181 Cincinnati, Ohio 45221-0181
Preconstruction Meeting Notification
Project Number
Date of Meeting
Location of Meeting
Time of Meeting
Associate
Contact Person & Phone Number
University Contact
Amount of Project $
Type of Construction Project (New, Renovation or Addition)
s:\shareall\forms\cm\pre-con.doc 4/15/96
Trang 13The Project Administrator or Associate should distribute the Contractor Information Sheet (Figure 3) to all Contractors in attendance This form provides a record of telephone
numbers and other contact information for each Contractor working on the project Contractors should be instructed to return their completed forms to the Project Administrator or Associate, as applicable
Project Status
Early in the meeting, the Project Administrator or Associate should review general issues related to project status Among others, these include:
Contractor and Associate responsibilities in this area
Coordination
This topic refers to how Contractors conduct their work whenever an item requires coordination of duties among two or more Contractors Issues to discuss include:
Contractors
documenting minor changes to the work
Trang 14Note: See “Ongoing Activities” for more information about the RFI
process
Page 14 Revised June 2002Managing the Construction Phase
Trang 15Figure 3: Contractor Information Sheet
Trang 16Site Issues
Site issues include all of the following, as applicable to the project:
planning/notifications
any building once the building’s heating/ventilation/air conditioning [HVAC] system is operational)
Construction Issues
Construction issues include the following:
meetings Contractor superintendents and the Associateare required to attend
Contractors’ employees and subcontractors
information on the regular progress meeting
Contractual Issues
Contractual issues include the following:
of Values
more information on the pay application; see the sections
“Approving Contractor Schedules” and “Approving
Page 16 Revised June 2002Managing the Construction Phase
Trang 17Contractor Pay Applications” for more information on the Schedule of Values
Trang 18Obtaining and Checking Permits
Various state and local permits must be secured in preparation for construction The General Conditions (Front-End Specifications) define the responsibilities of the
Associate, the Project Administrator, and the Contractor regarding permits
If a project uses an Associate Architect, he or she (as the
State building permits and National Pollutant Discharge Elimination System (NPDES) permits, described below On projects not using an Associate, the Project Administrator
secure these permits
The Contractor must obtain any permits required by local jurisdictions, unless the Contract Documents state
otherwise The Contractor also must pay the cost to obtain local permits The Associate or Project Administrator, as applicable, must confirm that the lead Contractor has obtained all permits for which it is responsible
Obtaining a State Building Permit
The project’s Owner (or Owner’s designated agent) must apply for and obtain required general building permits from the State of Ohio State building permits are issued by the Division of Industrial Compliance, Ohio Department of Commerce (the “Division”) The Division prefers that applications be completed by the design professional of record
In most cases, the Division requires the design professional
to submit a permit application and supporting documentation, including three to five complete sets of construction documents The plans must be approved by the Division, and inspections must be passed before a Certificate of Occupancy will be issued
A Certificate of Plan Approval is not required for maintenance or minor repairs
In addition to other construction for which plans must be submitted, the following types of work are not considered minor repairs and require application, approval, and
inspection:
Page 18 Revised June 2002Managing the Construction Phase
Trang 19• The cutting of any bearing or support member
A Division staff member or outside consultant reviews all
applications and submissions for compliance with the Ohio
Basic Building Code (OBBC)
Industrial Compliance Division Locations
The Division of Industrial Compliance has a central location
in Reynoldsburg and regional offices in Chillicothe, Akron, and Toledo Because the Chillicothe regional office has processed many University of Cincinnati permit applications
in the past, designers of record on UC projects may prefer
to use this office
Contact information for the central and regional offices appears below
Reynoldsburg Central Office
6606 Tussing RoadP.O Box 4009Reynoldsburg, Ohio 43068-9009
Phone: (800) 523-3581Fax: (614) 644-3145
Chillicothe Regional Office
20 South Paint StreetChillicothe, Ohio 45601Phone: (800) 686-1582 or (800) 788-8065Fax: (740) 702-1408
Akron Regional Office
161 South High Street, Room 401
Akron, Ohio 44308-1615
Toledo Regional Office
1 Government Center, Suite 1540
Toledo, Ohio 43604
Trang 20The Division of Industrial Compliance has two methods in place for the receipt and processing of building permit applications: the walk-in method and the standard method.
Walk-In Application Method
Under certain circumstances, the designer of record may hand-deliver a permit application to a Division office, have the application reviewed while he or she waits, and leave that day with a building permit
To qualify for the walk-in method, a project’s construction documents must consist of no more than eight pages Permit applications for longer, more complex projects must
be processed by the standard method
Walk-in applications must be submitted by the designer of record
Standard Application Method
With the standard method, the application and supporting information can be either hand-carried or mailed to any Division office Initial review takes between 2 and 4 weeks;
if the reviewer has questions, additional time may be needed to resolve these questions before the permit is granted
Applying for the Permit
The Ohio Application for Plan Approval (Figure 4) can be obtained from any of the Division offices It can also be downloaded from the Division’s web site
(http://www.com.state.oh.us/odoc/dic/dicform.htm)
Determining Fee Amounts
Before filling out the permit application, the applicant must calculate the amount of the fee(s) required to file it The Division’s “Worksheet for Fees to Be Paid” (Figure 5) helps applicants determine the applicable fee amount The
Page 20 Revised June 2002Managing the Construction Phase
Trang 21worksheet is page 2 of the Application for Plan Approval and
is available at
http://www.com.state.oh.us/odoc/dic/dicform.htm It should
be completed and returned with the application
If the project includes plumbing work, additional fees will bedue, and two extra sets of Construction Documents are required Plumbing fees are determined by the number of fixtures that will be installed The Division’s “Plumbing Fee Schedule” (Figure 6) helps applicants calculate plumbing fees The worksheet is available at
http://www.com.state.oh.us/odoc/dic/dicform.htm It should
be completed and returned with the application
Trang 22Page 22 Revised June 2002Managing the Construction Phase
Figure 4: Ohio Application for Plan Approval
Trang 23Figure 5: Worksheet for Fees to Be Paid
Trang 24Page 24 Revised June 2002Managing the Construction Phase
Figure 6: Plumbing Fee Schedule
Trang 25Note: The Division allows fees to be paid by check (made payable
to Treasurer, State of Ohio), cash, credit card, or intrastate transfer voucher (ISTV) The ISTV is the University’s
promise to pay its fees When the University pays fees by ISTV, the Division office generates an invoice for the
amount due UC Capital Finance completes the account coding for the ISTV and forwards it to State Accounting for processing
The Division recommends that UC applicants use the University’s credit card to pay fees associated with smaller projects
Completing the Permit Application
After completing the applicable fee worksheets, follow theseinstructions to complete the Application for Plan Approval:
1 Under SCOPE OF PROJECT, check all boxes that apply to the project If applicable, include the number of boilers and/or elevator units that will be installed in the building
2 Enter the county where the project is located
3 Check Yes if the project is located in an incorporated area or No if it is not
4 Check Yes if you have contacted a local flood plain administrator about the project or No if you have not
5 Enter the total number of pages included in the project’s Construction Documents
6 In the Nature of Project box, check New, Alteration, Addition,
or Change of Occupancy, as appropriate
Basic Building Code when determining the nature of the project
7 If the project has been granted a building permit previously, enter the permit number
8 To complete item 8:
project is being administered by the Office of the State Architect (SAO), enter both the State project number and the University project number If the
2
Trang 26project is being administered locally, enter the University project number
Page 26 Revised June 2002Managing the Construction Phase
Trang 279 Enter University of Cincinnati as project owner and include the mailing address and phone numbers for the
Department of Construction Management:
University Hall, 6th Floor
51 Goodman DriveCincinnati, OH 45219Phone: (513) 556-5200Fax: (513) 556-4885
correspondence with the Division
designer of record (Architect, Engineer, or Certified Sprinkler/Alarm Designer, as applicable)
complete address, and phone numbers of the designer of record
designer of record as identified in item 10, enter the name, address, and phone numbers of the submitter
current use group
project
information on use groups
project, including costs for the services of the Associate (if applicable) and all Construction Contractors
in the project
Trang 2820 Enter the number of alarms to be installed
for Fees to Be Paid (Figure 5) and the Plumbing Fee Schedule (Figure 6)
card, or ISTV
enter the five-digit number found on the order;
otherwise, enter N/A and proceed to item 24
name in the blank provided
Attaching Submittals
The permit application must be accompanied by three complete sets of Construction Documents; two additional sets must be submitted if a plumbing permit is required Plans must bear the seal of an Ohio Registered
Architect/Engineer or Certified Design Professional on each page The title sheet must be signed by the designer of record and embossed with his or her seal
The Division has published a list of submittals that are typically required with a permit application The list is not all-inclusive, nor will every project require every item on thelist The exact submittals required will vary depending on the nature of the project The checklist is intended to help design professionals submit more complete applications and thereby avoid delays
The table on the following pages presents the Division’s checklist of submittals
Page 28 Revised June 2002Managing the Construction Phase
Trang 29Item Description and Details
and building code analysis
proposed building, and all other structures, with dimensions and distances
details, with all required material specifications and soils analysis/load bearing capacity Design soils bearing pressure more than 3,000 psf requires asoil test borings report
with materials and dimensions Indicateall required fire resistance rated walls and details Include locations of
required fire extinguishers and ADAAG requirements
Exterior
Sections and Details Coordinate with floor plan and elevations, with UL Design Reference
numbers for required fire resistance rated walls and doors and ADAAG requirement details
Room Finish and Door Schedule Coordinate with floor plan and elevations Indicate all required fire
resistance ratings for doors and hardware schedules, door dimensions for egress requirements, and ADAAG requirements
Structural/Roof Framing Plan Framing layout with dimensions, details, notes, etc Truss Diagram/Pre-
Engineered Building shop drawings Design load tables including snow load, basic wind speed, seismic load, and other live loads/dead loads
plan, waste vent isometric, pipe sizes, material specifications, notes, etc
Trang 30Item Description and Details
Submit two extra sets of plans for the plumbing portion
sizes, equipment/duct material specifications, all required exhaust fans with capabilities
Model Energy
diagram, conduit and wiring sizes, grounding, etc Electrical Power Plan/Lighting Plan with panel schedules,circuiting coordination, symbols legend,exit/egress lighting with backup power Automatic
Sprinkler System Plan
System layout, riser diagram, and hydraulic calculations
Fire Alarm System Plan System layout, type of system sequence of operation, device
specifications, and backup power supply
Fire Extinguishers Coordinate with floor plan and equipment specifications
Other Means of Fire Protection System Plan
Type of system, system layout, system riser diagram, and device
specifications
Commercial Kitchen Hood and Kitchen Hood Fire Suppression System
Submit shop drawings and manufacturer’s specifications along with the appropriate BBS checklist
Responsibilities of the Permit Holder
1 The approved plumbing drawing and permit must be on the job site for the inspector
2 The permit holder must call the Columbus Dispatcher 800-822-3208) to request an inspection
(1-Page 30 Revised June 2002Managing the Construction Phase
Trang 313 The inspector will call the phone number on the dispatched itinerary and schedule a date and time for the inspection.
4 The inspector has 4 working days to make the inspectionbefore work can proceed
5 No part of the plumbing or drainage system shall be covered without the inspector’s approval
6 The permit holder must have work ready and follow the testing procedure in the State-approved Code Book
7 All added fixtures must be paid for before the job can be completed
Obtaining an NPDES Permit
The Associate must apply for and obtain an NPDES general permit from the Ohio Environmental Protection Agency This application (called a Notice of Intent, or NOI) must be submitted at least 45 days before construction begins The NOI form and instructions for completing it are available for download at the Ohio EPA’s website,
http://www.epa.state.oh.us/ An application fee is required
As part of the application process, the Associate must prepare a stormwater pollution prevention plan that provides for control of sediment and erosion at the project site
the Project Administrator must review the application with the University’s Department of Environmental Health and
Trang 32Daily Activities
Once construction is under way, a main responsibility for the Project Administrator/Associate is to monitor progress The Project Administrator or Associate (as applicable) keepstrack of progress by maintaining a regular presence at the construction site and keeping a written record of activities Site monitoring and written records serve to confirm that work is progressing satisfactorily (i.e., as required by the Contract Documents)
Obligations of the Associate Architect regarding construction monitoring and minimum time to be spent at the site are established in the ProfessionalDesign Services Agreement executed between the University and the Associate (a sample agreement is found on the University Architect Division website, http://www.uc.edu/architect/documents/aeagree.pdf) and
in the Associate’s Technical Proposal to the University
When a project uses an Associate, the Associate also must maintain regular contact with the Project Administrator (usually daily contact) to review construction progress and activities This communication can occur as a scheduled or unscheduled meeting or even by telephone
The Associate must submit written progress reports to the Project Administrator at the interval established in the Professional Design Services Agreement (usually monthly) Acceptable format and content for these reports should be agreed to between the University and the Associate
serve to keep all parties informed of progress See
“Administering Progress Meetings”
When a project does not use an Associate, the Project Administrator acts as Associate for the project and performsthe construction monitoring duties that otherwise would be held by an Associate
Page 32 Revised June 2002Managing the Construction Phase