This paper presents a technique to evaluate system and load point reliability indices of power systems considering reactive power shortages due to the failures caused by reactive powe
Trang 1
Abstract— Reactive power plays a significant rule in power
system reliability and security Reactive power is considered as
the network constraint in conventional reliability evaluation
techniques The impact of the failures of reactive power sources
such as synchronous condensers and compensators on system
reliability has not been considered in the existing reliability
techniques This paper presents a technique to evaluate system
and load point reliability indices of power systems considering
reactive power shortages due to the failures caused by reactive
power sources The reliability indices due to the reactive power
shortages are separated from those due to the real power
shortages Two reliability indices related to reactive power
shortage are proposed The IEEE 30-bus system is modified and
analyzed to illustrate the proposed technique The results provide
very important information for system planners and operators
for reactive power management
Index Terms— Reactive power, power system reliability
I INTRODUCTION
he objective of reactive power provision is to maintain
power system reliability and security Reactive power
reserve is a basic requirement for maintaining voltage
stability The adequate reactive power reserve is expected to
maintain system integrity under both normal and post
contingency operation As one of the well established
ancillary services, reactive power support and voltage control
plays a vital role in the operation of both conventional and
restructured power systems The effect of reactive power on
system stability and security has been well investigated
[1]-[8] Large area blackout usually occurs in a heavily loaded
system which does not have adequate local reactive reserves
Heavily loaded systems not only have high reactive power
demand but also high reactive power losses in the lines
During a disturbance, the real power component of line
loadings does not change significantly, whereas the reactive
power flow can change dramatically [1]
The reason is that the voltage drop resulting from a
contingency reduces the reactive power generation from line
charging, thereby increasing reactive power losses Sufficient
reactive reserves should be available to meet the Var changes
following a disturbance How much more reactive power a
power system can deliver depends on the operating condition
The authors are with the School of EEE, Nanyang Technological
University 1 , Singapore (e-mail: epwang@ntu.edu.sg ) and Power Engineering
School, Taiyuan university of Technology 2 , China
and the location of the reserves Many approaches have been developed in reactive power management and monitoring in order to improve the reliability of the system with respect to voltage stability/security problems [1]-[8]
Therefore it is important to consider the impact of reactive power in power system reliability evaluation in order to obtain more accurate reliability indices Reliability evaluation techniques have been well developed [9]-[12] The reactive power is usually considered as the network constraints in those techniques During post contingency load shedding, the network violation is alleviated through the proportional or priority load shedding without considering the rule of reactive power The estimation of post-contingency voltages and reactive power generation and flows was discussed using sensitivities [13] Though employing piecewise linear estimates, the effect of equipment limits on the estimates was captured The effect of shunt capacitor on distribution system
reliability was studied [14] The composite system reliability
was investigated from the standpoint of voltage limits and generator real/reactive power constraints in [15] The expected value of curtailed kWh due to lack of reactive power generation or due to exceeding of voltage limits and the expected value of voltage irregularity were also investigated [15]
However the following problems are either ignored or seldom considered in the existing reliability evaluation techniques Firstly most existing techniques for power system reliability evaluation ignored the impact of the failures of reactive power resources such as synchronous condensers and
various compensators on system reliability Secondly most reliability evaluation techniques concerned more on the
problems caused by real power shortage rather than those caused by reactive power unbalance during post contingency load shedding Thirdly, the reliability indices due to the reactive power shortage were seldom considered separately with those due to the real power losses System operators could not find the information related to the reliability problems caused by reactive power shortage from the existing reliability indices provided by the conventional reliability
evaluation techniques Therefore there is a need to find a
relationship between the reactive power and system reliability with respect to voltage violations and system
reliability
This paper presents a technique to evaluate system and load point reliability of a power system considering reactive power shortage due to failures caused by reactive power sources such as generators, synchronous condensers and
Reliability Assessment of Power Systems
Considering Reactive Power Sources
Peng Wang1,2, Member, IEEE, Wenping Qin2, Xiaoqing Han2, Yi Ding1, Xinghui Du2
T
978-1-4244-4241-6/09/$25.00 ©2009 IEEE
Trang 2compensators The reliability indices due to the reactive
power shortages are separated from those due to the real
power losses The reliability indices related to reactive power
shortages are proposed to provide more information to system
operators and planners The IEEE test system is modified and
analyzed to illustrate the proposed technique
Section II discusses the important characteristics of reactive
power sources and load The real and reactive power models
of generator, transmission line, compensator and load are also
presented The reliability evaluation techniques and load
shedding methods will be discussed and the reliability indices
associated with Var shortage during the post contingency are
proposed in Section III The modified IEEE 30-bus system
has been analyzed using the proposed techniques and the
results are presented in IV Section V concludes the paper
II REACTIVE POWER CHARICTERISTICS AND MODELING
There are three aspects that differentiate reactive power
from active power in power system operation Firstly, it is not
efficient to transfer reactive power over a long distance
because the reactive power loss in transmission system is
significant Reactive power losses are typically about ten
times of the active power losses due to the inductive nature of
transmission lines Therefore it is better to compensate the
reactive power locally Secondly, the main role of reactive
power is to maintain voltage stability/security of power
systems The effect of reactive power on system reliability in
terms of energy not supplied is indirect and should be
calculated based on reactive power shortage and voltage
violation Thirdly, the total reactive power loss in the
transmission network often exceeds the total reactive power
load The reactive power loss changes with system
configuration and operation condition [7]-[8] Reactive power
requirement for releasing voltage violation after a contingency
are heavily dependent on reactive power reserve distributions
in the system In order to determine and re-dispatch real and
reactive power reserve for post contingency restoration, the
models of various real and reactive power sources have to be
studied
A Generator
A generator can provide both capacitive and inductive
reactive power According to a NERC planning standard
guideline [4], reactive capability within 0.9 lagging and 0.95
leading should be available A physical constraint in Var
provision by a generator is its generation capability constraint
which represents the hard physical limitation of a generator's
capability for the simultaneous production of real and reactive
power A typical generation capability curve is shown in Fig
1
The real power output of a generator is usually limited to a
value within the MVA rating by the capability of its prime
mover [16] When real power and terminal voltage of a
generator is fixed, the armature and field winding heating
limits restrict its reactive power output The armature heating
limit is a circle with radius R1 =V t I acentered on the origin
C1(0, 0) and given by the following equation:
2 a t 2
P + ≤ (1)
Fig 1 Typical generation PQ curves
The field heating limit follows a circle with radius
d
i t
E V
R = , centered at
⎟⎟⎠
⎞
⎜⎜⎝
⎛ −
d
2 t 2
X
V , 0
C and given by Equation 2
2
d
i t 2
d
2 t 2
X
E V X
V Q P
⎟⎟⎠
⎞
⎜⎜⎝
⎛
≤
⎟⎟⎠
⎞
⎜⎜⎝
⎛ + + (2)
where Vt is the voltage magnitude at the generator bus, Ia is the steady state armature current, Ei is the excitation voltage magnitude, Xd is the synchronous reactance, P and Q are real
and reactive power output, respectively The machine rating
S R is the intersection point of the two circles The corresponding rated real power output is denoted by PR The
reactive power capability limits of generator can be determined by:
( )
d
2 t 2 2
d
i t
V P X
E V P
⎟⎟⎠
⎞
⎜⎜⎝
⎛
≤ for P<PR (3)
a t max
Q ≤ − for P>PR (4)
In real time operation, actual reactive power reserve Q r
from a generator can be determined using the capability curves as
Q r =Q max( )P −Q current (5)
where Qcurrent is the reactive power dispatched in the normal
operation
In most conventional reliability techniques, constant
maximum and minimum reactive power limits Qmax and Qmin
are used in AC power flow analysis The reactive power model for synchronous condenser is similar to generator In this paper the maximum reactive power provided by a
generator is assumed to be QR when the real power output is
P R
Trang 3B Transmission line
An equivalent π model is used to represent a long line in
Fig 2
Y ’ / 2
Z ’
-Fig 2 Equivalent π model of a transmission line
The real and reactive power losses along a transmission line
depend on line parameters such as series impedance Z’, and
parallel admittance Y’, and bus voltages at the sending and
receiving ends [16] The equations to calculate the real and
reactive power losses for short, medium and long lines can be
found in [16] Heavily loaded transmission lines lead to large
inductive reactive power losses In this case generators and
compensators need to produce sufficient reactive capability to
maintain the reactive power balance and to keep voltages
within the specified limits
C Var Compensators
Compensation devices can provide both capacitive and
inductive reactive power for a power system A reactive
power compensator is usually connected between a bus and
ground There are static and dynamic Var compensators in
power systems A basic dynamic Var generation arrangement
using a fixed capacitor with a thyristor-controlled inductor is
shown in Fig.3 The constant capacitive Var generation QC of
the fixed capacitor is opposite to the variable Var absorption
QL(γ) of the thyristor-controlled inductor to yield the total
variable Var output QT(γ) =QL(γ)-Qc For a specific voltage V,
the required positive or negative QT(γ) can be obtained by
changing turn off angle γ of thysistor It is assumed Var
compensators can provide both capacitive and inductive
reactive power
Fig.3 A typical thyristor-controlled Var compensator and its Q output
D Load
Load at a bus of a bulk power system is the aggregation of
the associated sub-transmission network and various loads
Therefore modeling such an aggregate load requires the
network parameters of sub-transmission system and the
profile of each individual load A typical PV curve is shown in
Fig 4 which addresses the proper voltage profile at a load bus
in a power system [17] It can be seen from the curve that bus
voltage is reduced as load increases The real Pb and reactive
Qb power at point b correspond to values at the low limit of the bus voltage c is the point of system voltage collapse when the reactive power provided by system is less than the
required reactive power Qc to maintain voltage level at Vc The
reactive safety margin can be defined using the curve as:
Q r =Q current −Q b (6)
Fig.4 A typical PV curve at a load bus
III RELIABILITY INDICES AND EVALUATION TECHNIQUE
A Component reliability models
A power system component such as generator, synchronized condenser, transmission line and reactive device can be represented using the two-state reliability model [18]
as shown in Fig 5 The availability A and unavailability U can
be calculated based on failure rate and repair rate using the following equations
Down
μ Fig 5 Two-state model of a component
A
μ λ
μ +
= (7)
U
μ λ
λ +
= (8)
B Basic system reliability indices
Considering an N-component power system, the basic reliability parameters such as the probability p i, departure rate λ , frequency Fi i , the total real power generation capacity
P i and reactive power generation capacity Qi for state i with M
failed components can be determined using the following equations respectively:
∏
∏
= +
=
1
j j N
1 M
p (9)
∑ +∑
= +
N M j
M
j j j i
λ (10)
V
L
SW
I c
I Q
L
C
QL(γ)
QT(γ)
Qc γ
Q
V
P(Q)
O
a
b
c
Pb (Qb)
P current (Q current ) P c (Q c )
Trang 4i
i P
F = λ (11)
∑
=
=Ngi
1
k k
P (12)
∑=
=Nqi
1
k k
Q (13)
where Aj, Uj, λ andj μ are the availability, the unavailability, j
the failure rate and the repair rate of component j respectively,
P k is the available real power capacity of generator k, Qk is
reactive power capacity of compensator or generator k, and
N gi is the total number of generators and N qi is the total
number reactive power sources
C Load point and system reliability indices
Two conventional annualized reliability indices of the
expected load curtailment (ELC) and the expected energy not
supplied (EENS) can be calculated using the proposed
technique The EENS due to the real power shortage (EENSP)
and reactive power shortage (EENSQ) are separately
calculated The expected MVarh shortage (EVarS)
considering the failures of reactive power sources and the
expected Var not supplied EVNS are defined to provide more
reliability information for system planners and operators The
annualized reliability indices for annual constant load can be
calculated using the following equations:
∑
=NC
1
F LC ELC (14)
∑
=NC
1
EENS (15)
=NC
1
EENS (16)
∑
=NC
1
EVNS (17)
8760 p VarS EVarS NC
1
i Qi× i×
=∑= (18)
where NC is the total number of considered contingencies,
Pi
LC and LC Qiare the real power load curtailment due to real
power and reactive power shortage for state i respectively,
Qi
QC are the reactive power load curtailment due to reactive
power shortage for state i , VarS Qi is the Var shortage which
cause the voltage drop, and LC i =LC Pi +LC Qi
D Load shedding
Network violations for a contingency can be released using
load shedding and real and reactive power re-dispatch Load
shedding technique is more complicated when considering
both real and reactive power shortage In real time operation,
different power systems may have different load curtailment
strategies such as proportional, priority and wheeling load
shedding, and the corresponding direct load control
equipments are required for the implementation of those
strategies, which should and can be considered in reliability
evaluation A two step curtailment strategy is presented in this
section to illustrate load shedding with considering reactive
power shortage For each contingency state, the corresponding total real power available capacity is firstly compared with the total real power demand (load plus estimated transmission loss) If the total real power capacity is less than total real power demand, the real and related reactive power of the load
at each bus in the system is curtailed using the proportional load shedding technique After the load shedding due to the real power shortage, AC power flow is performed to check network violations and generation adequacy If the total real power generation is sufficient for the total demand and the voltage violations exist, the violations are due to reactive power shortage Because the reactive power cannot be delivered efficiently through a long distance due to the transmission loss, the reactive power is usually compensated locally Therefore the load shedding related to the reactive power shortage should be in the local buses with the low voltage, which is different with the load shedding approach due to the real power shortage In this technique, the load shedding due to reactive power shortage is usually performed
at the nodes with voltage violation If the voltage violation still exists after the load shedding at those buses, the load shedding is expanded to the surrounding nodes
E Determination of reactive power shortage
In order to determine reactive power shortage under a contingency state, reactive power is injected step by step at the node with the low voltage to raise the voltage When the voltage reaches its low limit, the corresponding reactive
power injected is the reactive power shortage VarSQi in
equation (18)
F Procedure of reliability evaluation
Based on the proposed models, equations and techniques, the procedure of the AC power flow based reliability evaluation considering reactive power include the following steps:
Step1: Input basic network data, load data, generation data, and basic reliability data
Step2: Determine system state using contingency analysis and
calculate basis system reliability indices for state i
Step3: Calculate total system real and reactive power capacity
P i and Qi respectively
Step4: If Pi is less than the total real power demand, cut real
and reactive load proportionally at each load bus and update
EENS P, EVNSQ and ELC Otherwise go to next step
Step5: Determine line overflow violations using AC power flow analysis
Step6: If there is the line overflow, gradually cut the load at the ending bus of the line and go to Step5 Otherwise update
EENS P , EVNSQ and ELC, and go to next step
Step7: Determine voltage violations using AC power flow analysis Go to next step if there is voltage violation Otherwise go to Step14
Step8: If the real power capacity is sufficient, gradually increase reactive power injection at the node with low voltage Step9: Perform AC power flow analysis Go to Step8 if there
is voltage violation Otherwise update EVarS and go to next
Trang 5step
Step10: Remove the reactive power injected at Step8
Step11: Gradually cut the load at the bus with low voltage
Step12: Perform AC power flow and check the voltage
violations
Step13: Go to Step11 if there is voltage violation Otherwise
update EENSQ , EVNS Q and ELC and go to Step14
Step14: If all contingencies are considered go to next step
Otherwise go to Step2 for next state
Step15: Calculate system reliability indices
IV SYSTEM STUDIES
The IEEE 30-bus system [19] as shown in Fig 6 is analyzed
to illustrate the proposed technique The system is selected
due to its requirements of the reactive power compensation
caused by special radial configuration from two generation
stations to the remote load centers
Fig 6 The single line diagram of IEEE 30-bus system
There are two generation buses in the system Generation
bus 1 consists of 4×60MW units Generation bus 2 consists of
3×40MW units In order to illustrate the effect of reactive
power reserve on system reliability, the system has been
modified The reactive power limits of the generators, synchronous condensers and static Var compensators have been changed The reactive power limits and the reliability parameters for each generator and condenser are shown in Table A1 The reliability parameters of the transmission lines are shown in Table A2 Annual constant load is used in analysis The real and reactive power load is bundled together using fixed power factor, which means that real and reactive power must be curtailed at the same percentage during the real or reactive power shortage
The failures up to second order have been considered in the
analysis The proposed annual load point and system EENSP,
EENS Q and ELC have been calculated and the results are
shown in Table 1 It can be seen from Table 1 that load point
at bus 26 has highest EENSP followed by the load point at bus
5 The highest EENSP at bus 26 is because of the single
transmission line connected to the bus and the high
probability of the first order failure The higher EENSP at bus
5 is due to the highest load for the second order failure
Unlike EENSP the load point at bus 29 has highest EENSQ
followed by the load point at bus 30 This is because the long transmission line from reactive power compensators to the
two buses The results also show that the system EENSQ caused by the voltage violation is about 28 percent of EENSP
due to real power shortage and should be considered in reliability evaluation
Bus # EENS P
(MWh/yr)
EENS Q
(MWh/yr)
ELC
(MW/yr)
5 139311.10 92880.21 23155.98
12 15307.69 5663.05 1751.07
17 16085.15 1987.96 1999.76
21 48446.32 7938.02 8470.37
26 1124030.00 34429.42 147960.80
29 11319.81 182601.40 25045.13
30 49995.85 105795.30 22653.80 System 1606505.00 453599.00 249534.50
The proposed annual load point and system EVNSQ and
EVarS are also calculated and the results are shown in Table 2
The EVarS results show that the voltage violations caused
by Var shortage can be released using the reactive power injection at those nodes instead of shedding the load
Therefore EVarS provide the system operator with very
important information for post contingency restoration Both
Trang 6real and reactive power shortage will cause the reactive power
curtailments because real and reactive power loads are
bundled by the fixed power factor
Bus # EVNS Q
(Mvarh)/yr
EVarS
(Mvarh)/yr
5 46832.64 73617.88
7 19520.02 9238.56
8 54565.78 10443.33
12 14042.91 6356.84
14 3046.91 2009.08
17 11647.11 2373.76
19 6642.29 560.42
20 1149.61 15.31
21 36085.98 9261.80
23 3216.00 587.33
24 9707.84 764.81
26 761273.60 39626.82
29 72720.46 199034.20
30 27924.83 90334.29 System 1101236.00 444224.40
V CONCLUSIONS
This paper presents a technique to evaluate system and load
point reliability of power systems considering reactive power
shortage due to failures caused by reactive power sources
such as synchronous condensers and compensators The
reliability indices due to the reactive power shortage are
separated from those due to the real power shortage The
reactive power shortage is calculated through the reactive
power injection at the nodes with low voltage The IEEE
30-bus system is modified and analyzed to illustrate the proposed
technique The results provide very important information and
different ways for system operator to alleviate the network
violations and for system planner to determine the optimal
location for installing new reactive power compensators
VI REFERENCES [1] B Leonardi, V Ajjarapu, “Investigation of various generator reactive
power reserve (GRPR) definitions for online voltage stability/security
assessment”, Proc of IEEE PES General Meeting, Jul 2008
[2] I El-Samahy, K Bhattacharya, C Caizares, M F Anjos, Jiuping Pan, “A
Procurement Market Model for Reactive Power Services Considering
System Security”, IEEE Trans on Power Systems, vol 23, no 1, pp.137–
149, Feb 2008
[3] T Plavsic, I Kuzle, “Zonal reactive power market model based n optimal
voltage scheduling”, AFRICON 2007, pp 1–7, Sept 2007
[4] N Yorino, M Eghbal, E.E El-Araby, Y Zoka, “Dynamic Security
Constrained VAR Planning for Competitive Environments”, Power and
Energy Society General Meeting - Conversion and Delivery of Electrical Energy in the 21st Century, 2008 IEEE, pp 1–8, Jul 2008
[5] F Dong, B H Chowdhury, M L Crow, L Acar, “Improving voltage
stability by reactive power reserve management”, IEEE Trans on Power
Systems, vol 20, no 1, pp 338–345, Feb 2005
[6] S K Parida, S N Singh, S C Srivastava, “Voltage security constrained
localized reactive power market”, 2006 IEEE, Power India Conference,
pp 6, Apr 2006
[7] S Hao, A Papalexopoulos, “Reactive power pricing and management”,
IEEE Trans on Power Systems, vol 12, no 1, pp 95– 104, Feb 1997
[8] A Rajabi, H Monsef, “Valuation of dynamic reactive power based on
probability aspects of power system”, Universities Power Engineering
Conference, UPEC 2007 42nd International, pp 1169–1174, Sept 2007
[9] R N Allan, R Billinton, A M Breipohl, and C H Grigg, “Bibliography
on the Application of Probability Methods in Power System Reliability
Evaluation: 1987-1991”, IEEE Trans on Power Systems, vol 9, no 1, pp
41–49, Feb 1994
[10] R N Allan, R Billinton, A M Breipohl, and C H Grigg, “Bibliography
on the Application of Probability Methods in Power System Reliability
Evaluation”, IEEE Trans on Power Systems, vol 14, no 1, pp 51–57,
Feb 1999
[11] R Billinton, M Fotuhi-Firuzabad, and L, Bertling, , “Bibliography on the Application of Probability Methods in Power System Reliability Evaluation1996-1999”, IEEE Trans on Power Systems, vol 16, no 4,
pp 595–602, Nov 2001
[12] Y Ding, P Wang, “Reliability and price risk assessment of a restructured
power system with hybrid market structure”, IEEE Trans on Power
Systems, vol 21, no 1, pp 108–116, Feb 2006
[13] P A Ruiz, P W Sauer, “Voltage and Reactive Power Estimation for
Contingency Analysis Using Sensitivities”, IEEE Trans on Power
Systems, vol 22, no 2, pp 639–647, May 2007
[14] A A Sallam, M Desouky, H Desouky, “Shunt capacitor effect on
electrical distribution system reliability,” IEEE Trans on Reliability, vol
43, no 1, pp 170–176, Mar 1994
[15] P L Noferi, L Paris, “Effects of voltage and reactive power constraints
on power system reliability”, IEEE Trans on Power Apparatus and
Systems, vol 94, no 2, pp 482–490, Mar 1975
[16] J J Grainger, W D Stevenson, Jr Power system analysis New York:
McGraw-Hill, 1994
[17] V C Thierry, V Costas, Voltage Stability of Electric Power Systems, Boston/London/Dordrecht: Kluwer Academic Publishers, 1998
[18] R Billinton, R N Allan, Reliability Evaluation of Power Systems, 2nd
ed., New York and London: Plenum Press, 1996
[19] O Alsac, B Stott, “Optimal Load Flow with Steady State Security”, IEEE
Trans on Power Apparatus and Systems, vol 93, no 3, pp 745-751,
May 1974
Appendix
Compensator
Trang 7T ABLE A2
1 2 1 876
1 3 1 876
2 4 1 876
3 4 1 876
2 5 1 876
2 6 1 876
4 6 1 876
5 7 1 876
6 7 1 876
6 8 1 876
6 9 1 876
6 10 1 876
9 11 1 876
9 10 1 876
4 12 1 876
12 13 1 876
12 14 1.5 876
12 15 1.5 876
12 16 1.5 876
14 15 1.5 876
16 17 1.5 876
15 18 1.5 876
18 19 1.5 876
19 20 1.5 876
10 20 1.5 876
10 17 5 876
10 21 5 876
10 22 5 876
21 22 5 876
15 23 5 876
22 24 1.5 876
23 24 1.5 876
24 25 1.5 876
25 26 5 876
25 27 5 876
28 27 1.5 876
27 29 5 876
27 30 5 876
29 30 5 876
6 28 1 876
Peng Wang (M’00) received his B.Sc degree from Xian Jiaotong University,
China, in 1978, the M Sc degree from Taiyuan University of Technology,
China, in 1987, and the M Sc and Ph.D degrees from the University of
Saskatchewan, Canada, in 1995 and 1998, respectively Currently, he is an
associate professor of Nanyang Technological University, Singapore
Qin Wenping received her B.S (1995) and M.S (2001) degrees in College of
Electrical & Power Engineering of Taiyuan University of Technology (TUT),
Taiyuan, China (e-mail: qinwenping@tyut.edu.cn) Currently, she is a lecturer in
TUT and a visiting scholar in Nanyang Technological University, Singapore
Her research interests include power system reliability analysis, security assessment, stability analysis and protection