Area load uncertainty, correlation between area loads and generating unit derated states have been considered.. These sensitivity indices can provide information about which tie line or
Trang 1R Billinton Power Systems Research Group University of Saskatchewan Saskatoon, Sask., Canada Department of Electrical mgineering
ABSTRACT: Considerable attention has been devoted to
multi-area generating system reliability assessment in
recent years [l-81 Most of proposed methods are based
on a combination of the generation capacity state
enumeration technique and the network flow (maximum
flowminimum cut) algorithm This paper presents a new
method for multi-area generation system reliability
assessment
It is based on direct sampling of generating unit
states, the clustering technique and the correlative
normal distribution sampling technique of the load
states A linear programming model is used to
minimize the total load curtailment Area load
uncertainty, correlation between area loads and
generating unit derated states have been considered
Incorporation of these factors does not create a
significant increase in computing time Sensitivity
indices of both system and each area to area
generation and tie line capacities can be calculated
These indices provide important information regarding
which tie line or which area generating capacity
should be reinforced from the overall system and each
area point of view Calculation results of a four-area
system are given to demonstrate the effectiveness of
the method
1N Most electric power companies operate as members
of an interconnected power system because of the
mutual benefits associated with interconnected
operation and planning Considerable attention
therefore has been devoted to multi-area system
reliability assessment in recent years (1-81 Most of
proposed methods are based on a combination of the
generation capacity state enumeration technique and
the network flow (maximum flow-minimum cut) algorithm
In order to reduce computational requirements in state
enumeration, some state space decomposition approaches
have been developed [1,3,4] These approaches can
prate effective in decreasing CPU time The
effectiveness of these approaches is reduced, however,
in those cases associated with a large unacceptable
set of states (infeasible range) This can easily
occur in interconnected system studies involving
relatively small individual system reserve margins
where a wide range of units or unit derated state
models are involved In order to limit the number of
states, a large rounding increment is required with
attendent loss of accuracy In order to combat this,
a large unacceptable set may be created Another
92 WM 141-2 PWRS
by the IEEE Power System Engineering Committee of
the IEEE Power Engineering Society for presentation
at the IEEE/PES 1992 Winter Meeting, New York, New
York, January 26 - 30, 1992 Manuscript submitted
August 15, 1991; made available for printing
December 3, 1991
A paper recommended and approved
W Li Area Transmission Planning Department System Planning Division Vancower, B.C., Canada B.C Hydro
problem involving computational effort is haw to deal with the detail associated with the annual load model The clustering technique utilized in Reference 5
provides a powerful approach €or aggregating load points and reducing the computation time It can also
be used to approximately capture the correlation between area loads in a cluster mean value sense This paper presents a new method for multi-area generation system reliability assessment A computer program named MASMOR (Multi-Area System Monte Carlo based Reliability evaluation) has been developed at the University of Saskatchewan based on this method
It has the following features: (1) The method is based
on direct sampling of generating unit states The generation capacity state model is not required and therefore no truncating and rounding errors are created Operational strategies of generating units can also be introduced ( 2 ) Area load uncertainty can
be considered using a normal distribution sampling technique When area load uncertainty is incorporated, correlation between area loads can be simulated more accurately by combining the clustering technique and a correlation sampling technique compared to the single clustering technique ( 3 ) A linear programing model
is used to minimize the total load curtailment while satisfying tie line capacity limits
The WEE sensitivity indices of both overall system and each area to area generation and tie line capacities can be calculated using this approach Reference 4 illustrates a procedure which can be utilized to calculate the sensitivity of the overall system An area may represent an individual utility
or even jointly owned generation and therefore area sensitivity indices are potentially useful These sensitivity indices can provide information about which tie line or which area generation capacity should be reinforced from both an overall system and each area point of view,
GFNERATING UNIT STATE SAMPLING The behaviour of each generating unit in each area can be simulated by a uniformly distributed randcnn number sequence in [0,1] In the case of a two state representation, let Si denote the state of the ith generating unit and FORi be its forced outage rate A uniformly distributed random number x is drawn in [Of11 ,
0 (up state) if x 3 FoRi
1 (down state) if 0 4 x < M R i
In the situation in which generating unit derated states are considered, let PDRi be the probability of the derated state of the ith generating unit,
if x 3 PDRi + FoRi
if PDRi 4 x < PDRi + FoRi ( 2 )
The above sampling technique can be easily extended to include multi-derated generating unit states
2 (derated state) if 0 d x < PDRi
Trang 2After all the generating unit states in each area
are determined by sampling, a generation capacity
level for the area can be obtained A similar sampling
technique can be used to select the tie line states in
a multi-area system
LQAD MODEL The load model involves two phases In the first
step, the 8760 hourly load points representing a year
are grouped into several clusters and the mean values
of the load points for each area in each cluster are
obtained by the K-means algorithm In the second step,
the area load uncertainty and correlation can be
incorporated by a normal distribution sampling
technique and a correlation sampling technique
The K-Means Algorithm 191
The K-means algorithm can be stated as follows :
(1) Select initial values of cluster means Mij
where i and j denote cluster i and area j
(2) Calculate Euclidean distances from each
hourly load point to each cluster mean by
(3)
where Dki denotes the Euclidean distance from
the kth load point to the ith cluster mean,
L the kth load value in the jth area and N
is the number of areas
Re-group the pints by assigning them to the
nearest cluster and calculate the new cluster
means by
kj
( 3 )
where Ni is the number of load points in the
ith cluster and IC denotes the set of the
load points in the ith cluster
( 4 ) Repeat steps (2) and (3) until all cluster
The cluster means are then used as the load levels
for each area in each cluster Each load level
represents Ni load points in the relative cluster in a
mean value sense Correlation between mean values of
area load points in each cluster is captured in the
K-mean algorithm Since it reflects correlative
relation between cluster means, the captured
correlation is approximate After reliability indices
for each cluster are calculated, annual reliability
indices can be obtained by weighting the indices for
each cluster by (Ni/8760)
means maintain unchanged between iterations
Area Load Uncertainty And Correlation
Load uncertainty always exists in an actual parer
system and it has long been recognized that load
uncertainty can have a great impact in reliability
evaluation of a single area generation system and a
composite system [lo-111
Load uncertainty can be modeled using a normal
distribution and therefore it is necessary to draw
normally distributed random numbers in order to
simulate area load uncertainty A normal distribution
has two parameters: mean value and standard deviation
The mean values are the cluster means obtained by the
K-mean algorithm and the standard deviation is
assigned according to the perceived load forecast
uncertainty, such as 5% to 10% This paper utilizes the tabulating technique of normal distribution sampling presented in Reference 11 to create normally distributed random numbers
If all the area loads are completely dependent, the cluster means of all the area loads are the same for each cluster In this case, only one normally distributed random number is required for each cluster
in order to determine the load states of all areas If all area loads are not completely dependent but some
are correlated, it is necessary to generate a normally distributed random vector for each cluster, in which each component corresponds to the load state of a particular area and whose components satisfy the correlation between the load points of different areas
in the same cluster The correlation can be expressed
by a correlation coefficient The correlation matrix corresponding to the ith cluster can be calculated as follows
According to the statistical definitions of variance, the covariance and the correlation coefficient, the elements of the correlation matrix corresponding to area n and area m for the ith cluster
is
The covariance matrix C corresponding to the correlation matrix p can be obtained by
2'
where U is the standard deviation for the ith area load dertainty usually, the same standard deviation
is assumed for all area loads In this case, Equation
(6) is simply written as
2
After the covariance matrix C between area loads for each cluster is obtained, a load correlation sampling technique [ll] can be used to simulate area load uncertainty and correlation The basic steps are summarized in the following:
(1) Calculate the area load covariance matrix according to Equations ( 5 ) and (6) from information obtained by the K-means algorithm
(2) Draw a N dimensional normally distributed random vector G whose components are independent of each other and each component has a mean of zero and a variance of unity, where N is the number of areas
Calculate the low triangular matrix A by the following equations
( 3 )
c,
II
2 4 i-1 k-1 Aii 0 (Cii - L Aik)
Trang 3j-1
k-1
Aij * (Cij - E Aik Ajk)/Ajj
( 4 ) Create a N dimension correlative normally
distributed random vector R by
where B is a mean value vector whose
components are the cluster means Both area
load uncertainty and the correlation defined
by matrix C are included in the random vector
R
LINEAR PROGRAMMING MODEL FOR MULTI-AREA SYSTEMS
After the area generation capacity levels, area
load states and tie line states are selected by the
described sampling techniques: it is necessary to
evaluate the reliability indices of the selected
multi-area system state All areas can be divided into
two sets of supporting and supported areas In the
supporting set, the available area generation capacity
is larger than the area load A "generator variable"
is defined for each area in the supporting set The
u p r limit of each "generator variable" is the
difference between the available area generation
capacity and the area load In the supported set, the
available area generation capacity is smaller than the
area load A "required load" is defined for each area
in the supported set, which equals the difference
between the area load and the available area
generation capacity A "fictitious generator variable"
is also defined for each area in the supported set
When the "required load" at each area can not be
completely satisfied due to the insufficient total
available generation capacity in the supporting set
generator variables" can provide the unsatisfied parts
of the "required load" such that power balance in each
area is always guaranteed Essentially, the
"fictitious generator variables" are load curtailment
variables in the supported areas and therefore the
upper limit of each "fictitious generator variable" is
assigned as the relative "required load"
The "generator variables", the "fictitious
generator variables", the "required loads" and tie
lines constitute a new small "generation-transmission"
system The basic objective is to minimize the total
load curtailment while satisfying the power balance at
each node (area) and upper limits of the tie line
capacities, the "generator variables" and the
"fictitious generator variables" The following
linear programming model can be used for this purpose:
i m
s.t E TP + GPi = 0
j +i 3
E TP + GFi = DPi (i€ND)
j +i 3
where GPi and GFi denote the "generator variables" and
the "fictitious generator variables" at the ith node
respectively; j+i'* indicates that j belongs to the
line set in which all lines are connected to node i;
TP is the tie line power on line j and it is positive
when entering into node i and negative when issuing I
from node i; DPi is the "required load" at the ith node; SPi is the upper limit of the ith "generator variable"; is the capacity limit of the jth tie
line; NG, ND and NT are the sets of the "generator variables", the "fictitious generator variables" and tie lines respectively; ai is the weighting factor for the ith "fictitious generator variable"
There is a wide variety of possible supporting policies in multi-area generation system reliability assessment One of advantages of a linear programming model such as that described is that variable supporting policies can be easily incorporated Four supporting policies of priority order, priority order plus path order, shortest distance and proportional principle have been incorporated into the "OR computer program A priority order supporting policy
is used in this paper This can be considered by assigning different values of weighting factors ai The supported area with the first priority has a maximum value of ail the supported area in the next priority has a second maximum value of ai, etc These values of ai are specified in terms of their relative magnitudes and therefore it is easy to select these values
Another advantage of the linear programming model
is that the LOEE sensitivity indices of both system and area to area generations and tie line capacities can be calculated It should be noted that it is not possible to obtain the area sensitivity indices merely
by using the concept of dual variables Calculation of the area sensitivity indices can be explained intuitively as follows For a standard linear programming problem
min cTx
s.t AX = b
x 3 0 its optimal and feasible solution can be expressed by
X,, = B b where B is the optimal basis at the optimal and feasible solution and is the basic variable subvector B will maintainkchanged if the right-hand term b has a sufficiently small change Therefore
(18) this means
J
where ~i~ is an element of B - ~
Equation (19) indicates that the elements in the optimal basis are the sensitivities of the basic variables to the elements in the right-hand term of constraints Area sensitivity indices to area generations and tie line capacities can be therefore obtained by solving the linear programming model expressed by Equations (12) - (17)
CASE STUDIES The Test System
The four-area system shown in Figure 1 is considered as the test system
Trang 4Figure 1 The four-area generation system
Area 1 is the basic IEEE Reliability Test System
(RTS) [12] The annual peak load of the RTS is 2850 FlW
and its generator data (32 generating units) can be
found in Reference 12 Area 2, 3 and 4 are three
modified RTS's The modifications are as follows:
Area 2: Three 197 MW generators are removed and the
annual peak load is reduced to 2280 MW
Area 3: One 800 MW generator with FOR=O.18 is added
and the annual peak load is increased to
3575 Mw
Area 4: One 800 MW generator with FOR=O.18 and one
600 MW generator with FOR=0.15 are added
and the annual peak load is increased to
4180 MW
The tie line data are given in Table 1
Table 1 The Tie Line Data
From Area No I Capacity ( M W ) I FOR 1
1 - 3 I 200 I 0.0005 1
_ _ _ I
The annual load curve data for the RTS (8736
hourly load points in percentage of the annual peak
load) are given in Reference 12 When the area loads
are considered to be completely dependent, the same
annual load curve data of the RTS are applied to the
four areas When correlation between area loads (non-
completely dependent) is considered, the area load
curve in Area 1 remains unchanged and the area load
curves in Area 2, 3 and 4 were obtained by displacing
the hourly load values of Area 2 ahead by four hours,
those of Area 3 ahead by two hours and those of Area 4
backwards by two hours respectively
In order to include generating unit derated
states, the 350 MW and the two 400 Mw generators were
derated to 50% capacity with the derated state
probabilities given in Reference 10 The state
probabilities of the derated models are such that the
derating-adjusted two-state model data is identical to
that given in Reference 12
The specified supported priority order is : Area 4
-Area 3 -Area 2 -Area 1
LOLE And LOEE Indices
Eight cases were studied The convergence criterion of the simulation is that the coefficient of variation for the system LOEE is less than 0.05 The studies were done on a computer VAX-6330 The results for these studies are shown in Tables 2-5
completely dependent area loads, no load uncertainty and no generating unit derated states
Case 2: correlation between area loads, no load
uncertainty and no generating unit derated states
Case 3: completely dependent area loads, load
uncertainty (5% standard deviation) and
no generating unit derated states Case 4: correlation between area loads, load
uncertainty (5% standard deviation) and
no generating unit derated states Cases 5 to 8 basically correspond to Cases 1 to 4
respectively with the difference that derated states
of 50% capacity for the 350 MW and the two 400 MW
generators in each area are included
Case 1:
Table 2 LOLE Indices for Cases 1 to 4 (in hrsmac)
I Case 1 I Case 2 I Case 3 I Case 4 I
I
I
I Area 1 I 0.51999 I 0.18562 I 1.50711 I 0.56825 I
1 Area 2 I 0.65723 1 0.28788 I 1.29675 1 0.54931 1
I Area 3 1 4.67838 I 3.25331 I 6.82495 I 4.67462 I
1 Area 4 1 6.71499 1 5.64925 I 9.92413 1 8.16069 1
1 System 9.04900 I 17.12834 I 13.33456 I
I(minutes) 1 2.43 1 3.42 1 2.28 I 3.62 1
I I I
I 11.69466 I
I ( (I ( -_ I - I I
Table 3 W E E Indices for Cases 1 to 4 (in HWhmar)
I I Case 1 1 Case 2 I Case 3 I Case 4 1
I Area 1 I 48.533301 11.275011 212.627901 61.233461
I Area 2 I 73.920731 18.025581 162.838291 32.225051
I Area 3 I 736.581121 388.3348111222.51611I 648.877621
I Area 4 )1309.93604~1064.93188~1972.32385~1501.68359~
I System ~2168.97144~1482.5677513570.30713~2244.02026~
_l-l _
Table 4 LOLE Indices for Cases 5 to 8 (in hrsmar)
I Case 5 1 Case 0 i Case 7 I Case 8 1
I
I Area 1 I 0.16263 1 0.04125 1 0.80329 I 0.27450 I
1 Area 2 I 0.54225 I 0.28788 I 1.08667 I 0.45581 1
1 Area 3 I 2.15711 1 1.08688 I 3.77542 I 2.21619 1
I Area 4 1 3.17558 1 2.49638 I 5.13854 I 4.34513 I
1 System I 5.73323 I 3.85050 I 9.31079 I 6.97538 I
((minutes) I 3.26 I 5.35 I 3.03 1 5.37 I
I CPU tlme 1 I
-
Table 5 LOEE Indices for Cases 5 to 8 (in MWhmar)
I
I -
1 Area 1
1 Area 2
I Area 3
I Area 4
I System
Case 5 I Case 6 1 Case 7 I case 8 I
18.53292) 2.434861 115.816981 26.667501 53.778731 18.941401 133.968721 29.95026) 298.260931 106.248811 608.011411 262.732941 532.648561 391.914% l1010.176451 694.656491 903.221311 519.53979~1867.97363~1014.00714~
-
-
Trang 5It can be seen from these results that the indices
in the cases of completely dependent area loads are
larger than those in the cases of correlation between
area loads under the same other conditions that load
uncertainty and/or generating unit derated states are
considered or not considered Area load uncertainty
can have a great inpact on the calculated reliability
indices and always provides a more pessimistic
appraisal of multi-area system reliability
Utilization of derated state models for large capacity
generating units provides more optimistic estimation
of multi-area system reliability compared to the
utilization of a derating-adjusted testate model It
is therefore advisable to consider all the factors
existing in an actual power system such as correlation
between area loads, area load uncertainty and
generating unit derated states in multi-area system
reliability evaluation
In the results shown in Tables 2-5, there is an
apparent anomaly in the comparison between Case 2 and
Case 6 These two cases are identical except for the
fact that Case 6 includes the derated state models
The LOLE and LOEE in Area 2 do not decrease, as one
might expect, in Case 6 when compared with Case 2
This is due to the fact that Area 2 has a relatively
large reserve of 23.4% (compared to Area 4 with
14.9%) The effect of including a derated state model
in this case is relatively small and is masked by the
residual uncertainty associated with Monte Carlo
simulation
Sensitivity Indices
The method presented in this paper has been used
to calculate both system and area LOEE sensitivity
indices to area generations and tie line capacities in
various cases Additional CPU time is required when
the sensitivity indices are calculated The WEE
sensitivity indices for Cases 1 to 4 are listed in
Tables 6 to 9 It should be noted that Area No or system in the first column corresponds to incremental
variations of LOEE in the sensitivity indices while
Area No or Line No in the first row corresponds to incremental variations of area generations or tie line capacities
It can be seen from these results that although the values of the sensitivity indices are different in the various cases considering completely dependent area loads or correlation between area loads, area load uncertainty or no load uncertainty and generating unit derated states or derating-adjusted two-state models of generating units, their ranking orders in these cases are basically the same On the other hand, the ranking orders of the sensitivity indices for the overall system and each area are different From the overall system point of view, the best choice is to reinforce Tie-line 4, followed by Tie-line 6 and the
generating capacity in Area 4 From an Area 4 point of view, the best choice is to reinforce the generating capacity in Area 4, followed by Tie-lines 6 and 2 From an Area 3 point of view, the best choice is to
reinforce the generating capacity in Area 3, followed
by Tie-lines 3 and 5 From an Area 2 point of view, the best choice is to reinforce the generating capacity in Area 2, followed by Tie-lines 1 and 3
From an Area 1 point of view, the best choice is to reinforce the generating capacity in Area 1, followed
by Tie-lines 1 and 2 Increasing the generating
capacity of each area naturally has the greatest impact on improving the reliability of each area itself It is interesting to note that for the overall system, the first choice should be to reinforce two tie lines instead of increasing the generating capacity of the multi-area system
coNcLusIoNs
A new method for multi-area generation system Table 6 UXE Sensitivity Indices of System and Area to Area Generation and Tie Line Capacities in Case 1 (in rwh/year,+w)
I I Area 1 I Area 2 I Area 3 I Area 4 1 Line 1 I Line 2 I Line 3 I Line 4 I Line 5 I Line 6 I
I Area 1 I -0.51542 I -0.01747 I -0.10483 I -0.06989 I -0.34070 I -0.20966 I -0.08736 1 -0.00874 I -0.14851 1 -0.04368 1
I Area 2 I -0.00874 I -0.65520 1 -0.02621 1 -0.10483 I -0.55910 I -0.07862 I -0.55910 1 -0.06989 I -0.00874 I -0.45427 1
1 Area 3 1 -0.17472 1 -0.04368 I -4.67376 1 -0.54163 I -0.04368 1 -0.31450 1 -4.45536 j -3.69533 1 -4.17581 I -0.46301 I
I Area 4 I -0.06989 I -0.03494 I -0.06989 I -6.70925 I -0.06989 I -6.40349 I -0.11357 I -6.12394 I -0.00000 1 -6.61315 I
I S p t a I -0.76877 1 -0.75130 I -4.87469 I -7.42560 I -1.01338 I -7.00627 I -5.21539 I -9.89789 I -4.33306 I -7.57411 I
Table 7 UXE Sensitivity Indices of System and Area to Area Generation and Tie Line Capacities in Case 2 (in Whhear/llW)
I I Area 1 I Area 2 1 Area 3 1 Area 4 I Line 1 1 Line 2 I Line 3 I Line 4 I Line 5 1 Line 6 I
I Area 1 I -0.18346 1 -0.00000 I -0.06115 I -0.03494 1 -0.18346 I -0.07862 I -0.06115 I -0.01747 I -0.06115 I -0.03494 I
I Area 2 I -0.00000 I -0.27955 1 -0.00000 1 -0.03494 I -0.26208 I -0.03494 I -0.26208 I -0.03494 I -0.00000 I -0.21840 I
I Area 3 1 -0.09610 I -0.00000 I -3.24979 I -0.28829 I -0.00000 I -0.19219 1 -3.23232 1 -2.76931 1 -3.04886 1 -0.28829 1
I Area 4 I -0.03494 I -0.00000 I -0.00000 I -5.64346 I -0.00000 I -5.52115 1 -0.03494 I -5.46000 I -0.00000 1 -5.62598 I
I System I -0.31450 I -0.27955 1 -3.31094 I -6.00163 1 -0.44554 1 -5.82691 1 -3.59050 I -8.28173 I -3.11002 1 -6.16762 I
Table 8 UlEE Sensitivity Indices of System and Area to Area Generation and Tie Line Capacities in Case 3 (in twh/year/?w)
I I Area 1 1 Area 2
1-1 Area 1 I -1.50259 I -0.13104
1 Area 2 I -0.05242 1 -1.29293
I Area 3 I -0.45427 I -0.21840
I Area 4 1 -0.41059 I -0.33197
1 System I -2.41987 I -1.97434
Area 3 I Area 4 I Line 1
-0.31450 I -0.29702 I -0.86486 -0.13978 1 -0.28829 1 -0.83866 -6.82282 I -1.15315 1 -0.09610 -0.23587 I -9.92410 1 -0.17472 -7.51296 1-11.66256 1 -1.97434
Line i I Line 3 I Line 4 I Line 5
-0.47174 I -0.16598 I -0.12230 I -0.45427 -0.20093 I -0.76877 I -0.20966 1 -0.04368 -0.57658 I -5.87059 I -4.73491 I -5.36390 -8.80589 I -0.21840 I -8.63117 I -0.03494 -10.05514 1 -7.02374 1-13.69805 1 -5.89680
Line 6 I
-0.17472 I
-0.52416 I
-0.81245 I
-9.20774 I
-10.71907 1
I
Table 9 LOEE Sensitivity Indices of System and Area to Area Generation and Tie Line Capacities in Case 4 (in twh/year/W)
I I Area 1 I Area 2 1 Area 3 1 Area 4 1 Line 1 1 Line 2 1 Line 3 1 Line 4 I Line 5 1 Line 6 1
I Area 1 I -0.56784 I -0.00000 J -0.13104 1 -0.03494 I -0.53290 I -0.31450 I -0.13104 I -0.11357 I -0.34944 I -0.03494 I
I Area 2 I -0.00000 I -0.54163 I -0.02621 I -0.10483 I -0.54163 I -0.10483 I -0.48922 I -0.07862 1 -0.02621 1 -0.37565 I
I Area 3 I -0.02621 I -0.00000 I -4.67376 I -0.19219 I -0.00000 1 -0.16598 I -4.50778 I -4.20202 I -4.48157 I -0.19219 I
1 Area 4 1 -0.05242 1 -0.02621 1 -0.02621 I -8.15942 I -0.02621 I -7.79251 1 -0.05242 1 -7.82746 I -0.00000 I -8.07206 I
I Sytm I -0.64646 1 -0.56784 I -4.85722 I -8.49139 I -1.10074 1 -8.37782 1 -5.18045 1-12.22166 I -4.85722 I -8.67485 I
Trang 6reliability assessment is presented in this paper
This method is based on direct sampling of generating
unit states, the clustering technique and the
correlative normal distribution sampling technique of
load states and a linear programming model to minimize
the total load curtailment Area load uncertainty,
correlation between area loads and generating unit
derated states have been considered Incorporation of
these factors does not create a significant increase
in computing time Sensitivity indices of both system
and each area to area generations and tie line
capacities can be calculated These indices provide
information on which tie line or generating capacity
in which area should be reinforced first from the
overall system and each area point of view
The calculated results for a specific four-area
system indicate that considering correlation between
area loads and generating unit derated states can
produce an optimistic appraisal of multi-area
generation system adequacy while considering area load
uncertainty can provide a pessimistic appraisal The
actual factors which exist in an actual power system,
therefore, should be incorporated in a multi-area
generation system reliability assessment Although
consideration of these factors can lead to different
values for the sensitivity indices, their ranking
orders are basically the same
The ranking orders of the sensitivity indices for
the overall system and each area are, however,
different which indicates that a compromise between
areas and the overall system is required when
selecting a reinforcement plan based on the
sensitivity indices
REFERENCES
D.P Clancy, G Gross and F.F Wu, "Probabilistic
Flows for Reliability Evaluation of Multi-Area
Power System Interconnections" , Electric Power
and Energy Systems, Vol 5, No 2, p101-114,
April 1983
R Billinton and R.N Allan, "Reliability
Evaluation of Power systems", Plenum Press, 1984
F.N Lee, "Multi-Area Reliability - A New
Approach", IEEE Transactions on Power Systems,
G.C Olivera, S.H.F Cunha and M.V.F Pereira, "A
Direct Method for Multi-Area Reliability
Evaluation", IEEE Transactions on Power
C Singh and A Lago-Gonzalez, "Improved
figoritinns for Multi-Area Reliability Evaluation
Using the Decomposition-Simulation Approach" ,
IEEE Transaction on power Systems, vol 4, No 1,
Feb 1989, p321-328
C Singh, A.D Patton, A Lago-Gonzalez, A.R
VOJdani, G Gross, F.F WU and N.J Balu,
"Operating Considerations in Reliability Modeling
of Interconnected Systems - An Analytical
Approach", IEEE Transactions on Power Systems,
Vol PWRS-2, NO 4 , p848-855, NOV 1987
Systems, Vol PWRS-2, NO 4, ~934-942, NOV 1987
Vol 3, No 3, Aug 1988, ~1119-1127
A Lago-Gonzalez and C Singh, "The Extended Decomposition-Simulation Approach for Multi-Area Reliability Calculations", IEEE Transactions
on Power Systems, Vol 5, No 3, Aug 1990
R Billinton and L Gan, "A Monte Carlo Simulation Model for Adequacy Assessment of Multi-Area Generating Systems", Proceedings of
Probabilistic Methods Applied to Electric Power Systems, IEE, London, 3-5 July, 1991
M.S Aldenderfer and R.K Blashfield, "Cluster
Analysis", Newbury Park, Sage Publications, 1984
[IO] R.N Allan, R Billinton and N.M.K AWel-Gawad,
"The IEEE Reliability Test System - Extension
to and Evaluation of the Generating System", IEEE Transactions on Power Systems, PWR-1, No 4,
1111 Li Wenywn and R Billinton, "Effect of Bus Load Uncertainty and Correlation in Composite System
Adequacy Evaluation" , IEEEDES 1991 Winter Meeting, 91-75-0, PWRS, New York, Feb 3-7,
1991
[I21 IEEE Conunittee Report, "IEEE Reliability Test
Nov 1986, pl-7
System", IEEE Transactions on PAS, Vol 98; 1979,
~2047-2054
BIOGRAPHIES
Billinton (F, 1978) came to Canada from Eng?a in 1952 Obtained B.Sc and M.Sc Degrees from the University of Manitoba and Ph.D and D.Sc Degrees from the University of Saskatchewan Worked for Manitoba Hydro in the System Planning and Production Divisions Joined the University of Saskatchewan in
1964 Formerly Head of the Department of Electrical Engineering Presently C.J MacKenzie Professor of Engineering and Associate Dean, Graduate Studies, Research and Extension of the College of Engineering Author of papers on Power System Analysis, Stability, Economic System Operation and Reliability Author or co-author of seven books on reliability Fellow of the IEEE, the EIC and the Royal Society of Canada and a Professional Engineer in the Province of Saskatchewan
G r a & t d TsingHua University Obtained M.Sc and Ph.D Degrees from Chongqing University Worked for the North-East Power Company of China in the Technical and Equipment Division and at the Electricit6 de France in the Research and Development Division, Chongqing University and University of Saskatchewan in the Electrical Engineering Department
He is-presently with the System Planning Division of B.C Hydro
Author of papers on Secure and Economic Operation, Optimization Techniques, Power System Planning and
Reliability Author of a book on secure and economic operation of power systems Senior member of the IEFZ and member of the Chinese Society of Electrical mgineering and the Sociitk des Electriciens et des Electroniciens de France