1.5Unpacking the Cabinet Guides you to unpack the cabinet packing box and the board carton.. 1.6Unpacking the Board 1.7Checking the Equipment Guides you to check the cabinet, subracks,
Trang 11 Before You Start 1-1
1.1 About the Equipment 1-2 1.2 Installation Flow 1-4 1.3 Required Documents and Tools 1-6 1.3.1 Required Documents 1-6 1.3.2 Required Tools and Metres 1-6 1.4 Checking Installation Conditions 1-7 1.5 Unpacking the Cabinet 1-7 1.6 Unpacking the Boards 1-11 1.7 Checking the Equipment 1-13
Trang 2Figure 1-1 Architecture of the OptiX OSN 3500 1-3 Figure 1-2 The OptiX OSN 3500 subrack 1-4 Figure 1-3 Installation flow 1-5 Figure 1-4 Straightening the tongues 1-9 Figure 1-5 Removing the cover 1-9 Figure 1-6 Removing the surrounding wooden boards 1-10 Figure 1-7 Board carton 1-12
Trang 3Table 1-1 Technical parameters of the cabinet and the subrack 1-2 Table 1-2 Tools and metres 1-6 Table 1-3 Check items 1-13
Trang 41 Before You Start About This Chapter
Note
Before you install the OptiX OSN 3500, we recommend reading OptiX OSN 3500
Intelligent Optical Transmission System Compliance and Safety Manual This
helps you to ensure a safe and smooth installation
This chapter describes the work you are required to do before you start the installation Turn to the specific section for applicable tasks
The following table lists the contents of this chapter
1.1About the Equipment Describes the cabinet and subrack.
1.2Installation Flow Describes the installation flow.
1.3Required Documents and Tools Describes the required documents, tools
and metres.
1.4Checking Installation Condition Guides you to check the equipment room
environment and grounding conditions 1.5Unpacking the Cabinet Guides you to unpack the cabinet packing
box and the board carton.
1.6Unpacking the Board 1.7Checking the Equipment Guides you to check the cabinet, subracks,
boards, network management computer, and internal cables.
Trang 51.1 About the Equipment
Table 1.1 shows the technical parameters of the cabinet and the subrack
Table 1.1 Technical parameters of the cabinet and the subrack
Cabinet 600 (Width) x 300 (Depth) x 2000 (Height) 55
600 (Width) x 600 (Depth) x 2000 (Height) 79
600 (Width) x 300 (Depth) x 2200 (Height) 60
600 (Width) x 600 (Depth) x 2200 (Height) 84
600 (Width) x 300 (Depth) x 2600 (Height) 70
600 (Width) x 600 (Depth) x 2600 (Height) 94 Subrack 497 (Width) x 295 (Depth) x 722 (Height) 23(no boards)
Note:
All dimensions are in mm The following figure shows the directions of the width, the depth and the height
W
H D
Figure 1.1 shows the architecture of the OptiX OSN 3500 The OptiX OSN 3500 consists of the following parts
Cabinet
Subrack
Power distribution unit
Orderwire phone frame
Cable distribution plate
Fiber spool box
Trang 67 8
1
2
3 4
5
6
8 9
W
H D 7
1 Power distribution unit 2 Side door
3 Cable distribution plate 4 Orderwire phone frame
5 Subrack 6 Cabinet
7 Fiber spool box 8 Plastic panel
9 Front door
Figure 1.1 Architecture of the OptiX OSN 3500
Figure 1.2 shows the OptiX OSN 3500 subrack
Trang 7Fan area
Mounting ear
Fiber routing area
W
H D
Figure 1.2 The OptiX OSN 3500 subrack
1.2 Installation Flow
Correct installation flow is the key for ensuring a smooth, trouble-free installation Figure 1.3 is the installation flow
Trang 8Install cabinet
on antistatic floor ? Yes
Reinforce cabinets See Chapter 5
Install cabinet
on antistatic floor See Chapter 3
Installation preparations See Chapter 1
Install components
Install doors of the cabinet See Chapter 12
Install and route cables See chapter 9
End
Install alarm cables See section 9.3 Install indicator cables See section 9.2
Install E1 cables See section 9.4
Install E3/T3/E4/STM-1 cables Install Ethernet cables See section 9.6 Install clock cables
See section 9.5
See section 9.7 Install network cables See section 9.8
Install cabinet
on cement floor See Chapter 4 NO
Install fiber spool box See chapter 8
Install COA See chapter 7
Install cable distribution
plate See chapter 6
Install and route fibre jumpers See Chapter 10 Install external fibres See section 10.2
Install internal fibres See section 10.3
Install power cables See section 9.1
Install subrack cables See section 9.9
Install orderwire phone See Chapter 11
Remove doors
of the cabinet See Chapter 2
Figure 1.3 Installation flow
Trang 91.3 Required Documents and Tools
The following documents, tools and metres are required for the installation
1.3.1 Required Documents
The following documents are required before the installation
Written contracts and equipment configuration tables
Construction files
OptiX OSN 3500 Intelligent Optical Transmission System Installation Manual
1.3.2 Required Tools and Metres
The party specified in the contract shall provide the special tools and instruments; and the installer, the general tools and instruments Test and calibrate all
instruments before use
The installation personnel shall offer the tools and metres required for the installation, which are listed in Table 3.1
Table 3.1 Tools and metres
Measurement and lineation
tools
Long measuring tape
Ruler (1 m)
Gradienter
Marking pen
Powder marker
Pencil
Straight screwdriver
Cross screwdriver
Socket wrench (M5)
Ring spanner (M6)
Double ring spanner
Open-end wrench (10-12 metric)
Multimetre
Meg-ohmmeter
Earth resistance tester
BER tester
Optical power metre
SDH analysis metre
Trang 10Locksmith and drill tools Special tools Auxiliary tools
Sharp-nose pliers
Diagonal pliers
Pincer pliers
Electric hand drill
File
Hand saw
Crowbar
Rubber hammer
Percussion drill
Accessory drill bits
Vacuum cleaner
Electrostatic discharge (ESD) protection glove
ESD wrist strap
Torque spanner
Wire stripper
Cable clamp
Clamp for crystal connector
Wire punch down tool
Optical attenuator
Brush, nippers
Paper knife
Hand bellows
Electric iron
Solder wire
Prong ladder
1.4 Checking Installation Conditions
Before starting installation, make sure that the equipment room, power supply, ground wire, optical cables, and other materials are ready When these installation conditions are confirmed, the installation may begin according to the pre-designed layouts
For detailed requirements and related items, refer to Appendix A "Operation Environment Requirements" and Appendix B "Equipment Grounding"
1.5 Unpacking the Cabinet
Purpose This procedure guides you to unpack the cabinet.
Tools /Materials Spanner
Screwdriver Hammer Ejector lever
Prerequisites The cabinet has been delivered to the installation site.
Required/As
Trang 11Warning
The wooden case is direction-oriented and should not be placed upside down Otherwise, fatal damages would be caused to the product Since the cabinet is rather heavy, erecting the cabinet improperly may cause personal injuries
Caution
During the transportation and handling of products, spare parts or components, make sure to avoid the collision of such things against doors, walls or shelves
Caution
To avoid equipment damage in the course of moving, move the packing box to the equipment room or a place near the equipment room before unpacking
Caution
In the process of transporting, handling and installing the equipment, it is forbidden to reach the uncoated metal surface of equipment parts or components with sweaty or dirty gloves
Caution
When handling the cabinet, both hands should hold on the solid positions such as the base, the upper cable rack or bone frame Do not apply too much force on such positions with poor rigidity as cable support, cable fixing beam, so as to avoid any damage to the cabinet or any accident
Caution
Remove the lining board of the rack at the place where the cabinet is to be
Trang 12Caution
To protect the equipment and find out the cause, place the unpacked equipment indoor Take photos of the site storage environment, the rusted or corroded equipment/packing box/packaging materials Properly keep these photos and store the packing box/packing materials
Step 2 Move the packing box to the equipment room or a place nearby before unpacking
it
Step 3 Check the outer package Stop unpacking immediately, if there is
Serious damage to the outer package
Water on the outside packaging box
Rust/water on the equipment Find out the cause and feed back the information to the local representative office
Step 4 Insert one end of the ejector lever into the hold for the tongue of the wooden case
cover
Step 5 Turn the ejector lever to straighten the tongue See Figure 1.1 Or use a
screwdriver or a hammer to operate the tongue
Spanner Tongue
Woodenboard Steeledge
Figure 1.1 Straightening the tongues Step 6 After straightening all the tongues on the cover, remove the cover See Figure 1.1
Trang 13Figure 1.1 Removing the cover Step 7 Straighten all the tongues that join the wooden boards around the wooden case
Trang 14Step 9 Take the cabinet out of the packing box.
Step 10 Remove the plastic packing of the cabinet and erect the cabinet
Note
At least three persons are required to erect the cabinet: one person to hold the cabinet bottom, and two persons to lift the top of the cabinet and make the cabinet vertical
Step 11 Compare the equipment inside with the packing list If there are any differences,
notify the local customer service center
End
Trang 151.6 Unpacking the Boards
Purpose This procedure guides you to unpack the boards from the
board carton.
Tools /Materials ESD wrist strap or ESD glove
Diagonal pliers Paper knife
Prerequisites The board carton has been delivered to the installation site.
Required/As needed Required if the boards are placed in a separate carton for
shipment (for example, in the case of capacity expansion).
Caution
Each board is packed in both a plastic bag and an ESD bag Keep the bags properly They can be used later for keeping the boards or packing the damaged boards returned for repair
Caution
The ambient temperature and humidity may have an impact on the boards In each ESD-preventive bag there is a small bag of desiccant, which shall not be thrown away
Caution
Wait for at least 30 minutes before unpacking if the board is just moved from a cold, dry place to a warm, damp place Otherwise, the moisture condenses on the board surface and damages the components
Caution
Trang 16Step 12 Cut the straps with diagonal pliers and use a paper knife to split the tape along the
seam between the cover and the box body See Figure 1.1
Caution
Do not cut too deep into the carton with the paper knife Otherwise, the knife might scratch the articles inside
Strap Carton label
Pressure-sensitive adhesive tape Foam plate
Label on the board box
ESD bag Board
Board box
Board box
Figure 1.1 Board carton
Step 13 Open the carton and check whether the number and type of the boards are
consistent with that marked on the carton label
Step 14 Confirm that there is no evident damage on the board package
Step 15 Wear a securely grounded ESD wrist strap then open the board box and take the
board out of the ESD bag
1 Hold the bottom of the ESD bag with your left hand
2 Take the board out of the bag gently by its front panel with your right hand
3 Do not touch any electronic component on the board surface to avoid damage
4 Keep the bags properly
Step 16 Check whether any board is physically damaged If any board damage is found,
contact Huawei If not, put the board back into the board box and put the box in the place specified by the customer
If you are going to install the board right after unpacking, place the board on
an antistatic surface to discharge the static electricity
Trang 17original materials and place them at a cool dry place without direct sunshine
or strong electromagnetic radiation
End 1.7 Checking the Equipment
Check the cabinet, subrack, boards, network management computer and internal cables before the equipment installation Table 1.1 lists the check items
Note
The internal cables including subrack power cables and cabinet indicator cables have been installed properly before delivery
If any item in the following table fails to meet the requirement, contact Huawei in time
Table 1.1 Check items
Cabinet and subrack
Appearance Neat, no scratch or disrepair, no loosened
components.
Inside part No foreign matter or water stain.
Internal cables
Neatly bundled No cable is scattered, loosened, or damaged.
Silkscreen Clear Boards Appearance Neat, no scratch or disrepair, no loosened
components.
Quantity Consistent with that on the delivery list.
Software Corresponding configuration software is complete Internal cables Appearance Wiring is complete, reasonable and neat.
Connectors Firm, correct, and no float insertion.