Applied vacuum depressurization shall be 65 kPa minimum measured atmid-depth of the PVD throughout the consolidation period and a minimum of 80 kPa prior to the installation of the fill.
Trang 1CMDRCP / CW2C PACKAGE CW2C KM 18+200 – KM 23+450
SOFT SOIL IMPROVEMENT MEASURES
Trang 2METHOD STATEMENT OF VACUUM
CONSOLIDATION METHOD (V.C.M)
Trang 4Regarding requirements for construction using VCM, reference is made toMOT Decision 384/QD-BGTVT of 7 February 2013 Temporary regulations onvacuum treatment method using membrane method In principleconstruction using VCM should comply with the requirements of Decision
384, however the Contractor is permitted subject to the Engineer’s approval
to apply methods meeting alternative requirements based on the technicalrecommendation of their specialist VCM contractor, or if compliance withDecision 384 would lead to breach by the Contractor of another firm’spatents
Construction of other elements such as PVD installation, sand blanket,construction of embankment, and subgrade preparation shall be inaccordance with the relevant sections of this Specification
Applied vacuum depressurization shall be 65 kPa (minimum) measured atmid-depth of the PVD throughout the consolidation period and a minimum of
80 kPa prior to the installation of the fill The piezometric pressure reductionshall be measured by an electrical piezometer installed within a PVD at mid-depth along with a reference groundwater level measured by an observationwell in a non-improved area An adequate number of vacuum pumps shall beprovided to ensure that there is continuous application of vacuum throughoutthe consolidation period It should be emphasized that continuousdepressurization is essential in controlling the stability of the embankment.Vacuum pressure shall be maintained through the required period day andnight
Vacuum depressurization may and where necessary shall be applied prior
to placing of embankment and surcharge and may and where necessary shall
be applied simultaneously with the loading applied by the weight ofembankment and surcharge fill The height of the surcharge fill, duration ofvacuum application, and duration of surcharging are as shown on theDrawings Unless stated otherwise on the Drawings, or unless agreed
Trang 5CMDRCP / CW2C PACKAGE CW2C KM 18+200 – KM 23+450
otherwise by the Engineer, the duration of vacuum application shall be thetotal duration of the “filling time” (embankment construction time) plus the
“waiting time” (consolidation time) as shown on the Drawings
VCM shall be implemented by zones VCM shall be terminated when thecriteria for acceptance are satisfied for the whole of the relevant zone TheContractor may propose the zoning system
The criteria for acceptance is that the specified piezometric pressurereduction together with the specified height of surcharge fill have beenachieved and maintained for the duration specified on the Drawings for thatzone
Surcharge fill as shown on the drawings shall be placed over the netimprovement area at an acceptable filling rate The side slope shall not begreater than 1 (V): 2 (H) If failure to maintain the required vacuum pressureleads to a requirement to increase the surcharge fill height or filling rate, theContractor is required to provide calculations on stability of the embankmentfor approval by the Engineer
At interfaces between VCM method and non-VCM sections, in principle theVCM treatment should be carried out first, in order that embankmentconstruction and surcharge filling may take place uniformly across thetransition
At the site of pipe or box culverts, the VCM treatment and any surchargingrequired shall be carried out first and settlement criteria achieved prior topipe or box culvert construction, in order that uniform ground improvementcan be achieved over the culvert and its approaches During implementation
of VCM, existing drainage shall be routed in temporary drainage pipesthrough the zone of VCM and fill, or diverted by pumping
1.1 WORK SCOPE
This method statement includes the following work scopes:
(i) PVDs Installation
(ii) Vacuum system installation and trial running
(iii) Placing Geo- membrane and Protecting geotextile
Trang 6cross section drawings are attached to provide general view
2 RELEVANT SPECIFICATIONS, STANDARDS AND DOCUMENTS
RELEVANT SPECIFICATIONS AND STANDARDS
ASTM D 1621 Standard Test Method for Compressive Properties of Rigid Cellular Plastics
ASTM D3776 Standard Test Methods for Mass Per Unit Area (Weight)
of Fabric ASTM D3786 Standard Test Method for
Bursting Strength of Textile
Fabrics—Diaphragm Bursting Strength Tester Method
ASTM D 4491 Standard Test Method for Water Permeability of Geotextiles by the Permittivity method
ASTM D 4533 Test Method for Trapezoid Tearing Strength of
Geotextiles
ASTM D 4632 Test Method for Breaking Load and Elongation of
Geotextiles (Grab Method)
ASTM D 4716 Test Method for Determining the (In-plane) Flow Rate per Unit Width and Hydraulic Transmissivity of a Geosynthetic Using Constant Head
ASTM D4751 Standard Test Method for Determining Apparent OpeningSize of a Geotextile
ASTM D 4833 Test Method for Index Puncture Resistance of
Geotextiles, Geomembranes, and Related Products
ASTM D 5101 Measuring the Soil-Geotextile System Clogging Potential(By the Gradient Ratio)
ASTM D 5321 Standard Test Method for Determining the Coefficient of Soil and Geosynthetic or Geosynthetic and Geosynthetic Friction by the Direct Shear Method
ASTM D 5567 Hydraulic Conductivity Ratio (HCR) Testing of
Soil/Geotextile Systems
MOT Decision 384/QD-BGTVT of 7 February 2013 Temporary
regulations on vacuum treatment method using membrane method
Trang 7Environment & Safety Engineer
Project Manager
Construction Manager Site Engineer
QC Manager
Team for VCM work
Team for PVD work
Trang 8Construction preparation
Set up filtration and main pipeLaying geotextile (first layer) and geo-membrane (2 layers)
Set monitoring equipment
Drainage ditch constructionInstall PVD
Set outerway of vacuum and bury geo-membrane
Laying the second geotextile layer
Trang 9Marking of PVD
Trial penetration of PVD
Mass construction of PVD installation
CMDRCP / CW2C PACKAGE CW2C KM 18+200 – KM 23+450
separated by tags or signs
- Miscellaneous materials such as hardware and welding supplies shall
be stored in the warehouses and managed by a material staff
- Machine, equipment and material should be ensured in good qualityand supply on time
(2) Installation of Prefabricated Vertical Drains (PVDs)
The construction flow of PVD is shown as below:
Prefabricated vertical drains (PVDs) shall be installedthroughout the soft soil layers; Table 4.1 shows the main properties of PVDmaterial to be used
Trang 10Table 4.1 Required characteritics of PVD matterial according to
“Technical specification for soil
improvement-Technical design documents”
Properties Test
Designati
on
Requireme nts
Less than 75 Less than 75
Grab Tensile Strength, kN
Catalogue of PVD material shall be submitted for approval beforepurchasing and supplying for installation in soil improvement areas withspacing and penetration depth according to the Technical Design
Technical requirements for PVD installation
PVD material shall be stored in the warehouses to protect from rains,sunshine and ruins PVDs with any defects are strictly not allowed to use
Extension of PVD shall be implemented by opening the filter cover andoverlapping (≥300 mm) the core, then wrap and staple to ends
Tags shall be used to locate the installation points
PVD installation is presented as below:
- Use ruler or marked line to measure the spacing and points with deviation
of ±100 mm
Trang 11- PVDs shall be installed by static pressing or vibration method
- After completion, self-confirmation shall be executed Once confirmed, thework is reported to the Supervisors
Marking of Vertical Drain
After coordination survey work, the all vertical drain points will bedemarcated using bamboo chopsticks and any other materials to mark thepoints Tolerance shall be within 100 mm at this moment The horizontal andvertical tolerance is 5%; the depth tolerance is 1%
Trial Penetration of Vertical Drain: Calibrate monitoring unit
Mobilize Vertical Drain Rig to the marking location Then, set
up the Plastic Band Drain to the Rig
Then, Vertical Drain will bepulling out from the casing pipe and marking each one (1) meter for checkingthe monitoring unit
After the marking, band drain will be re rolled for their installation
Then, trial penetration work will be done slowly to check and adjustmonitoring unit and actual penetration depth (calibration)
Trang 12After the calibration of monitoring unit, we will continue trial penetration
to check the treatment thickness
Then, the vertical drain length will be recorded and submitted forapproval
Besides, trial PVD installation will be carried out at outside of treatmentarea for inspection by the Engineer
Vertical Drain Arrangement
All vertical drain shall be recorded to designated record formatand submit these record with summary
Mandrel : A mandrel (dimensions: 140x70x10mm), which is pushed
downwards into the weak subsoil
Set Anchor Plate : Set anchor plate (140x85mm) to band drain and
reinsert to the casing pipe
Splicing
Splicing of the PVD shall be done by stapling with proper workmanshipensuring the structural and hydraulic continuity of the drain At the splice thejacket of the upper part of the drain shall be external to the lower portion Amaximum of one splice per drain will be permitted without specific permissionfrom the Engineer
The jacket and core shall be overlapped a minimum of 300 mm at any splice
Trang 13CMDRCP / CW2C PACKAGE CW2C KM 18+200 – KM 23+450
Cut and Record
When casing pipe will be set back to original position, the plastic banddrain shall be cut by knife Vertical Drain shall be remained at least 300 mmfrom the platform
Then, Anchor plate shall be arranged again
At the same time, the length of each vertical drain shall be recorded tothe monitoring format Total vertical drain length will be calculated each day,cumulated and presented every day as a daily progress report
(3) Setup Horizontal Drain
Placement of horizontal drain
- One main pipe will be placed along the centre line of road Other subpipes will be placed overlap the row of PVD with spacing as shown inworking drawing The distance between boundary of treatment and the end
of pipe that is 10 – 15cm
- Position of the filter pipes Use shovels to excavate ditches The ditchescan be rectangular cross-section (15-20 cm wide and 15 cm deep) ortriangular cross-section (15 opening and 20 cm deep)
- Install pipes into the ditches, which are connected by four-way joint tofilter pipes Recheck the performance of the pipes before the placement,e.g., the ruins of the filter, the broken of the pipes
- The connection joints shall be wrapped and wired by geotextiles toprevent from the intrusion of sand particles
- PVD will be rolled around the filter pipe and then belted by plastic belt
- Fill sand into the ditches after completion of placement pipes
- The main pipe are connected to the UPVC pipe without holes by three –way joint and connected to the pump, placing along the road
Attention
- The excavation depth of the ditches shall be guaranteed
- Check the appearance and ruin of the filter membrane and pipe body
Trang 14- The joints shall be firmly connected to the filters and wrapped bygeotextiles.
Trang 15
Transported geomembrane to siteLaying the first geotextile layer
Laying first layer of geomembraneCheck and patch first layer of geomembraneLaying second layer of geomembraneCheck and patch second layer of geomembrane
Bury geomembraneLaying the second geotextile layerInstallation vacuum system
CMDRCP / CW2C PACKAGE CW2C KM 18+200 – KM 23+450
(4) Placement of Geomembrance
Trang 16 The installation of Geo-membrane must meet the following
requirements
Geo-membrane is keyed into anchor trenches which are filled with clay groutfor air tightness Geo-membrane should be sustainable, flexible and anti-punch airtight materials
Prior to the placement of the geo-membranes, the jobsite shall be leveled andcleared Rigid and sharp materials (e.g., gravels and chunks) shall be cleared.Meanwhile, a protection layer of non-fabric geotextile shall be placed below thegeo-membranes
The size of the geo-membranes shall be pre-determined in accordance with thetreatment scope by manufacturer The size shall also account for theembedment into the cut-off wall An overlapping between 02 sheets ofgeomembrane is joined by glue, it shall not be less than 20 cm During the test
of the vacuum preloading, the overlapping shall be carefully inspected
The geo-membranes strips shall be firstly mobilized by excavators to the center
of the jobsite and unpacked two-ways During mobilization, the geo-membranesshall not be ruined by the excavators
The placement of the geo-membranes shall proceed daytime with less thanforce 5 wind power
Two geo-membranes are placed independently Each placement will be followed
by careful checks and repairs of ruins After installation of geomembrane, sandbags shall be put on geomembrane
In the course of geo-membranes placement, the persons shall wear soft shoes.Each placement will be followed by careful checks and repairs of ruins oropenings
In the course of geo-membranes placement, the geo-membranes shall not bepulled excessively A length of geo-membrane shall be reserved at the sides ofeach treatment unit
An opening can be repaired using a small size geo-membrane Firstly, clear thesurface of the opening and the geo-membrane Then, daub the binder aroundthe opening When the binder is felt non-cohesive, place the small geo-membrane onto the opening, without leaving air bubbles between the contactsurfaces
When position the settlement measurements on the geo-membranes,geotextiles, soft mats or geo-membranes shall be placed beneath themeasurements Weight shall also be placed on the base
Check the geo-membranes very carefully prior to the vacuum operation Assessthe leaking potentials based on the vacuum meter, vision and hearing Any
Trang 17CMDRCP / CW2C PACKAGE CW2C KM 18+200 – KM 23+450
opening or ruin shall be repaired immediately
Geo-membranes shall be backed up on-site for at least operations of two units.When ruins or vacuum leaking is identified after surcharge is loaded, it is hard
to correctly identify the points of ruins
- Gloves shall be worn to prevent from ruins
- Geo-membranes binding works shall be completed by skilled persons
- Geo-membranes shall be embedded into the impervious soil for at least
50 cm
- Miscellaneous materials shall be immediately cleared from the ditches
Edge Treatment
After the Airtight sheet arrangement, Edge Treatment shall be executed
by Excavator for excavation and backfilling work
Airtight sheet shall be embedded into the cohesive material at least 50
cm to prevent air leak