For those who have diligently worked through the earlier planning processes chapters, you are nearly ready to launch your project. This chapter completes the final two planning tasks that become the master plan for your project - resource and cost scheduling.
Trang 1Reducing Project Duration
Chapter 9
Trang 3Rationale for Reducing Project Duration
Time Is Money: Cost-Time Tradeoffs
Reducing the time of a critical activity usually incurs additional direct costs.
o Cost-time solutions focus on reducing (crashing) activities
on the critical path to shorten overall duration of the project
Reasons for imposed project duration dates:
o Incentive contracts (bonuses for early completion)
Trang 4Options for Accelerating Project
Completion
Adding Resources
Outsourcing Project
Work
Scheduling Overtime
Establishing a Core
Project Team
Do It Twice—Fast
and Correctly
Fast-Tracking
Critical-Chain
Reducing Project Scope
Compromise Quality
Trang 5Explanation of Project Costs
Project Indirect Costs
Costs that cannot be associated with any
particular work package or project activity
o Supervision, administration, consultants, and interest
Costs that vary (increase) with time
o Reducing project time directly reduces indirect costs.
Direct Costs
Normal costs that can be assigned directly to a
specific work package or project activity
Crashing activities increases direct costs
Trang 6Reducing Project Duration to
Reduce Project Cost
Identifying direct costs to reduce project time
Identifying direct costs to reduce project time
Compute total costs for specific durations and compare to benefits of reducing project time.
Compute total costs for specific durations and compare to benefits of reducing project time.
Search critical activities for lowest direct-cost activities to shorten project duration.
Search critical activities for lowest direct-cost activities to shorten project duration.
Gather information about direct and indirect costs of specific project durations
Gather information about direct and indirect costs of specific project durations
Trang 7Project Cost—Duration Graph
FIGURE 9.1
Trang 8Constructing a Project Cost—
Duration Graph
durations.
project durations.
selected project durations.
benefits.
Trang 9Constructing a Project Cost—
Duration Graph
Determining Activities to Shorten
Shorten the activities with the smallest increase in
cost per unit of time.
Assumptions:
o The cost relationship is linear.
complete the activity
possible under realistic conditions
o Slope represents a constant cost per unit of time.
times
Trang 10Activity Graph
Trang 11Cost—Duration Trade-off Example
FIGURE 9.3
Trang 12Cost—Duration Trade-off Example (cont’d)
Trang 13Cost—Duration Trade-off Example (cont’d)
FIGURE 9.4
Trang 14Cost—Duration Trade-off Example (cont’d)
Trang 15Cost—Duration Trade-off Example (cont’d)
FIGURE 9.4 (cont’d)
Trang 16Summary Costs by Duration
Trang 17Project Cost—Duration Graph
FIGURE 9.6
Trang 18Practical Considerations
Trang 19What if Cost, Not Time Is the Issue?
Reduce project scope
Have owner take on more responsibility
Outsourcing project activities or even the
entire project
Brainstorming cost savings options
Trang 20Key Terms
Crash point
Crash time
Direct costs
Fast-tracking
Indirect costs
Outsourcing
Project cost–duration graph