1. Trang chủ
  2. » Kinh Tế - Quản Lý

Lecture Modern project management: Chapter 8 - Norman R. Howes

20 52 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 20
Dung lượng 461,4 KB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

For those who have diligently worked through the earlier planning processes chapters, you are nearly ready to launch your project. This chapter completes the final two planning tasks that become the master plan for your project - resource and cost scheduling.

Trang 1

Reducing Project Duration

Chapter 9

Trang 3

Rationale for Reducing Project Duration

 Time Is Money: Cost-Time Tradeoffs

 Reducing the time of a critical activity usually incurs additional direct costs.

o Cost-time solutions focus on reducing (crashing) activities

on the critical path to shorten overall duration of the project

 Reasons for imposed project duration dates:

o Incentive contracts (bonuses for early completion)

Trang 4

Options for Accelerating Project

Completion

 Adding Resources

 Outsourcing Project

Work

 Scheduling Overtime

 Establishing a Core

Project Team

 Do It Twice—Fast

and Correctly

 Fast-Tracking

 Critical-Chain

 Reducing Project Scope

 Compromise Quality

Trang 5

Explanation of Project Costs

 Project Indirect Costs

 Costs that cannot be associated with any

particular work package or project activity

o Supervision, administration, consultants, and interest

 Costs that vary (increase) with time

o Reducing project time directly reduces indirect costs.

 Direct Costs

 Normal costs that can be assigned directly to a

specific work package or project activity

 Crashing activities increases direct costs

Trang 6

Reducing Project Duration to

Reduce Project Cost

Identifying direct costs to reduce project time

Identifying direct costs to reduce project time

Compute total costs for specific durations and compare to benefits of reducing project time.

Compute total costs for specific durations and compare to benefits of reducing project time.

Search critical activities for lowest direct-cost activities to shorten project duration.

Search critical activities for lowest direct-cost activities to shorten project duration.

Gather information about direct and indirect costs of specific project durations

Gather information about direct and indirect costs of specific project durations

Trang 7

Project Cost—Duration Graph

FIGURE 9.1

Trang 8

Constructing a Project Cost—

Duration Graph

durations.

project durations.

selected project durations.

benefits.

Trang 9

Constructing a Project Cost—

Duration Graph

 Determining Activities to Shorten

 Shorten the activities with the smallest increase in

cost per unit of time.

 Assumptions:

o The cost relationship is linear.

complete the activity

possible under realistic conditions

o Slope represents a constant cost per unit of time.

times

Trang 10

Activity Graph

Trang 11

Cost—Duration Trade-off Example

FIGURE 9.3

Trang 12

Cost—Duration Trade-off Example (cont’d)

Trang 13

Cost—Duration Trade-off Example (cont’d)

FIGURE 9.4

Trang 14

Cost—Duration Trade-off Example (cont’d)

Trang 15

Cost—Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Trang 16

Summary Costs by Duration

Trang 17

Project Cost—Duration Graph

FIGURE 9.6

Trang 18

Practical Considerations

Trang 19

What if Cost, Not Time Is the Issue?

Reduce project scope

Have owner take on more responsibility

Outsourcing project activities or even the

entire project

Brainstorming cost savings options

Trang 20

Key Terms

Crash point

Crash time

Direct costs

Fast-tracking

Indirect costs

Outsourcing

Project cost–duration graph

Ngày đăng: 08/02/2020, 20:40