For single projects, we discuss how the resource allocation problem concerns resource leveling to minimize the cost of the resources. But for multiple projects, we learn that the issue is how to allocate limited resources among several projects in order to achieve the objectives of each.

Trang 1

Copyright 2015 John Wiley & Sons, Inc.

Chapter 9

Resource 

Allocation

Trang 3

by spending more money

Trang 4

 Crunching a project often introduces 

unanticipated problems

Trang 6

An Example of Two­Time CPM

Trang 7

Activity Slopes—Cost per Period for 

Crashing

Trang 8

Crashing the Project

Trang 9

Seven Day Schedule

Trang 10

Six Day Schedule

Trang 11

Five Day Schedule

Trang 12

Four Day Schedule

Trang 13

Cost­Crash Curve

Trang 14

Fast­tracking is another way to expedite a project

Trang 15

8­15

Trang 17

scope are fixed

System­constrained: A project requires a fixed amount of time and resources

Trang 19

8­19

Trang 20

Resource A

Trang 21

Resource B

Trang 23

Large projects with multiple resources are complex to levelize

Trang 24

Resource Leveling

Trang 27

Constrained Resource Scheduling

Heuristic

Approach An approach, such as a rule of thumb, that yields

a good solution that may

or may not be optimal

Optimization

Approach An approach, such as linear programming, that

yields the one best

solution

Trang 28

They are the only feasible methods used 

to attack large projects

While not optimal, the schedules are very good

Take the CPM/PERT schedule as a 

baseline

Trang 33

Multi­Project Scheduling and Resource  Allocation

Trang 34

Multi­Project Scheduling and Resource  Allocation  Continued

However, different projects have different goals so combining may not make sense

Must also tell us if there are resources to tackle the new projects we are 

considering

Trang 38

This is the amount of work waiting to be 

processed because there is a shortage of some resource

Similar to WIP in manufacturing

Holding cost is incurred

Trang 41

With multiproject instances a single case must be developed 

Connected with dummy activities and/or 

pseudoactivities

8­41

Trang 42

Hierarchy of Gantt Charts

Trang 45

Do Early Finishes and Late Finishes  Cancel Out? So What? 

Trang 46

independent leads to underestimating the actual amount of time  needed to complete the project.

visible to project workers and is often misused.

Trang 49