For single projects, we discuss how the resource allocation problem concerns resource leveling to minimize the cost of the resources. But for multiple projects, we learn that the issue is how to allocate limited resources among several projects in order to achieve the objectives of each.
Trang 1Copyright 2015 John Wiley & Sons, Inc.
Chapter 9
Resource
Allocation
Trang 3by spending more money
Trang 4 Crunching a project often introduces
unanticipated problems
Trang 6An Example of TwoTime CPM
Trang 7Activity Slopes—Cost per Period for
Crashing
Trang 8Crashing the Project
Trang 9Seven Day Schedule
Trang 10Six Day Schedule
Trang 11Five Day Schedule
Trang 12Four Day Schedule
Trang 13CostCrash Curve
Trang 14Fasttracking is another way to expedite a project
Trang 15815
Trang 17scope are fixed
Systemconstrained: A project requires a fixed amount of time and resources
Trang 19819
Trang 20Resource A
Trang 21Resource B
Trang 23Large projects with multiple resources are complex to levelize
Trang 24Resource Leveling
Trang 27Constrained Resource Scheduling
Heuristic
Approach An approach, such as a rule of thumb, that yields
a good solution that may
or may not be optimal
Optimization
Approach An approach, such as linear programming, that
yields the one best
solution
Trang 28They are the only feasible methods used
to attack large projects
While not optimal, the schedules are very good
Take the CPM/PERT schedule as a
baseline
Trang 33MultiProject Scheduling and Resource Allocation
Trang 34MultiProject Scheduling and Resource Allocation Continued
However, different projects have different goals so combining may not make sense
Must also tell us if there are resources to tackle the new projects we are
considering
Trang 38This is the amount of work waiting to be
processed because there is a shortage of some resource
Similar to WIP in manufacturing
Holding cost is incurred
Trang 41With multiproject instances a single case must be developed
Connected with dummy activities and/or
pseudoactivities
841
Trang 42Hierarchy of Gantt Charts
Trang 45Do Early Finishes and Late Finishes Cancel Out? So What?
Trang 46independent leads to underestimating the actual amount of time needed to complete the project.
visible to project workers and is often misused.
Trang 49849