Which of the following is their most likely reason for testing?. Because we have already found many defects in subsystem C, we should concentrate testing resources n Subsystem A.. Contra
Trang 1Question 1
Correct
Mark 1.00 out of
1.00
Question 2
Correct
Mark 1.00 out of
1.00
Started on Saturday, 1 September 2018, 7:58 AM
State Finished Completed on Saturday, 1 September 2018, 8:05 AM
Time taken 6 mins 43 secs
Marks 40.00/40.00 Grade 10.00 out of 10.00 (100%)
Independent Verification & Validation is
Select one:
a Done by the Developer
b Done By Management
c Done by the Test Engineers
d Done by an Entity Outside the Project's sphere of influence
A company recently purchased a commercial off - the - shelf application to automate their bill paying process They now plan to run an acceptance test against prior to putting it into production
Which of the following is their most likely reason for testing?
Select one:
a To detect bugs in the application
b To train the users
c To gather evidence for a lawsuit
d To build confidence in the application
Kiem thu phan mem_
2018_2019_HKI_Sang_Thu6
Trang 2Question 3
Correct
Mark 1.00 out of
1.00
Question 4
Correct
Mark 1.00 out of
1.00
Question 5
Correct
Mark 1.00 out of
1.00
As a test leader you are collecting measures about defects You recognize that after the first test cycle, covering all requirements - subsystem C has a defect density that is 150% higher than the average Subsystem A on the other hand has a defect density that is 60% lower than the
average
Select one:
a We should try to equalize the amount of testing over all modules to ensure that we test all subsystems evenly
b Observed defect density does not allow any conclusions about the amount
of additional testing
c It is probable that subsystem C has still more hidden defects Therefore we need to test subsystem C in more detail
d Because we have already found many defects in subsystem C, we should concentrate testing resources n Subsystem A
Amount of testing performed will not depend on
Q 330: Amount of testing performed will not depend on
A Risks involved
B Contractual requirements
C Legal requirements
D Test data.
Select one:
a Test data
b Legal requirements
c Risks involved
d Contractual requirements
What is the difference between testing software developed by contractor outside your country, versus testing software developed by a contractor within your country?
Select one:
a Relinquishments of control
b Does not meet people needs
c Cultural difference
d Loss of control over reallocation of resources
Trang 3Question 6
Correct
Mark 1.00 out of
1.00
Question 7
Correct
Mark 1.00 out of
1.00
Question 8
Correct
Mark 1.00 out of
1.00
Question 9
Correct
Mark 1.00 out of
1.00
Testing is not done to Select one:
a Check user friendliness
b Improve software accuracy
c Find faults
d Improve Quality
Which of the problems below BEST characterize a result of software failure?
Select one:
a Lack of methodology
b Damaged reputation
c Regulatory compliance
d Inadequate training
Faults found by users are due to:
Select one:
a Poor quality software
b Poor software and poor testing
c Insufficient time for testing
d Bad luck
Which factors contribute to humans making mistakes that can lead to faulty software?
I Setting aggressive schedule
II Integrating complex systems III Allocating adequate resources
IV Failing to control changes
Select one:
a I, II and IV are true; III is false
b II and IV are true; I and III are false
c I and II are true; III and IV are false
d I, II and III are true; IV is false
Trang 4Question 10
Correct
Mark 1.00 out of
1.00
Question 11
Correct
Mark 1.00 out of
1.00
Question 12
Correct
Mark 1.00 out of
1.00
Question 13
Correct
Mark 1.00 out of
1.00
Which, in general, is the least required skill of a good tester?
Select one:
a Being diplomatic
b Able to write software
c Having good attention to detail
d Able to be relied on
For software to be reliable it must:
Select one:
a Never fail under any circumstances
b Be easy to maintain
c Be written according to coding standards
d Be unlikely to cause a failure
When reporting faults found to developers, testers should be Select one:
a All of the above
b As polite, constructive and helpful as possible
c Diplomatic, sensitive to the way they may react to criticism
d Firm about insisting that a bug is not a "feature" if it should be fixed
What is the process of analyzing and removing causes of failures in software?
Select one:
a Verification
b Testing
c Validation
d Debugging
Trang 5Question 14
Correct
Mark 1.00 out of
1.00
Question 15
Correct
Mark 1.00 out of
1.00
Question 16
Correct
Mark 1.00 out of
1.00
Question 17
Correct
Mark 1.00 out of
1.00
Which is not the testing objective?
Select one:
a Preventing defects
b Debugging defects
c Finding defects
d Gaining confidence about the level of quality and providing information
Testing should be stopped when:
Select one:
a All faults have been fixed correctly
b Time has run out
c All the planned tests have been run
d It depends on the risks for the system being tested
Which defects are OFTEN much cheaper to remove?
Select one:
a Minor defects that were found by users
b Defects that were detected early
c Defects in infrequently used functionality
d Usability defects found by customers
A test team consistently finds between 90% and 95% of the defects present in the system under test While the test manager understands that this is a good defect-detection percentage for her test team and industry, senior management and executives remain disappointed in the test group, saying that the test team misses too many bugs Given that the users are generally happy with the system and that the failures which have occurred have generally been low impact, which
of the following testing principles is most likely to help the test manager explain to these managers and executives why some defects are likely to be missed?
Select one:
a Pesticide paradox
b Exhaustive testing is impossible
c Absence-of-errors fallacy
d Defect clustering
Trang 6Question 18
Correct
Mark 1.00 out of
1.00
Question 19
Correct
Mark 1.00 out of
1.00
Question 20
Correct
Mark 1.00 out of
1.00
Important consequences of the impossibility of complete testing are (Choose one or more answers):
Select one or more:
a We have no definite stopping point for testing, which makes it easier for some managers to argue for very little testing
b We have no easy answer for what testing tasks should always be required, because every task takes time that could be spent on other high importance tasks
c We can never be certain that the program is bug free
d All of the above
When should we stop our testing?
Select one:
a The answer depends on the experience & maturity of your developers
b This question is difficult to answer
c The answer should be standardized for the software development industry
d The answer depends on the contract with the client, special requirements if any & risks your organization is willing to take
"How much testing is enough?"
Select one:
a The answer depends on the risk for your industry, contract and special requirements
b This answer depends on the maturity of your developers
c This question is easy to answer
d This question is impossible to answer
Trang 7Question 21
Correct
Mark 1.00 out of
1.00
Question 22
Correct
Mark 1.00 out of
1.00
Question 23
Correct
Mark 1.00 out of
1.00
Question 24
Correct
Mark 1.00 out of
1.00
Failure is _
Select one:
a Incorrect program behavior due to a fault in the program
b Bug found after product Release
c Bug found during Design phase
d Bug found before product Release
Which of these are objectives for software testing?
Select one:
a Eliminate every error prior to release
b Uncover software errors
c Determine the productivity of programmers
d Eliminate the need for future program maintenance
indicates how important it is to fix the bug and when it should be fixed
Select one:
a Severity
b None of the above
c All of the above
d Priority
One key reason why developers have difficulty testing their own work is Select one:
a Lack of technical documentation
b Lack of training
c Lack of test tools on the market for developers
d Lack of Objectivity
Trang 8Question 25
Correct
Mark 1.00 out of
1.00
Question 26
Correct
Mark 1.00 out of
1.00
Question 27
Correct
Mark 1.00 out of
1.00
Question 28
Correct
Mark 1.00 out of
1.00
Which is the best definition of complete testing:
Select one:
a You have reached the scheduled ship date
b You have tested every statement, branch, and combination of branches in the program
c You have completed every test in the test plan
d You have discovered every bug in the program
Which of the following requirements is testable?
Select one:
a The safety-critical parts of the system shall contain 0 faults
b The system shall be built to be portable
c The system shall be user friendly
d The response time shall be less than one second for the specified design load
Deciding How much testing is enough should take into account :
i Level of Risk including Technical and Business product and project risk
ii Project constraints such as time and budget iii Size of Testing Team
iv Size of the Development Team
Select one:
a ii,iii,iv are true and i is false
b i,,iv are true and ii is false
c i,ii,iii are true and iv is false
d i,ii are true and iii,iv are false
Who would USUALLY perform debugging activities?
Select one:
a Testers
b Analysts
c Developers
d Incident Managers
Trang 9Question 29
Correct
Mark 1.00 out of
1.00
Question 30
Correct
Mark 1.00 out of
1.00
Question 31
Correct
Mark 1.00 out of
1.00
Question 32
Correct
Mark 1.00 out of
1.00
According to the ISTQB Glossary, the word "bug" is synomous with which of the following words? Select one:
a Incident
b Error
c Mistake
d Defect
When do you stop testing?
Select one:
a When the test completion criteria are met
b When all high and medium priority tests are complete
c When all statements have been executed
d When the specified number of faults are found
When what is visible to end-users is a deviation from the specific or expected behavior, this is called:
Select one:
a A defect
b A failure
c A fault
d A mistake
e An error
Majority of system errors occurs in the _ phase Select one:
a Analysis and Design Phase
b Development Phase
c Testing Phase
Trang 10Question 33
Correct
Mark 1.00 out of
1.00
Question 34
Correct
Mark 1.00 out of
1.00
Question 35
Correct
Mark 1.00 out of
1.00
Question 36
Correct
Mark 1.00 out of
1.00
The cost of fixing a fault:
Select one:
a Can never be determined
b Decreases as we move the product towards live use
c Increases as we move the product towards live use
d Is not important
e Is more expensive if found in requirements than functional design
When to stop Testing?
Select one:
a Stop when scheduled time for testing expires
b Stop when all the test cases execute with detecting few errors
c Stop if 75% of the pre-defined number of errors is detected
d None above
Which is not a testing principle?
Select one:
a Exhaustive testing
b Pesticide paradox
c Early testing
d Defect clustering
Below is a list of problems that can be observed during testing or operation Which is MOST likely a failure?
Select one:
a The computation algorithm used the wrong input variables
b The product crashed when the user selected an option in a dialog box
c One source code file included in the build was the wrong version
d The developer misinterpreted the requirement for the algorithm
Trang 11Question 37
Correct
Mark 1.00 out of
1.00
Question 38
Correct
Mark 1.00 out of
1.00
Question 39
Correct
Mark 1.00 out of
1.00
Exhaustive Testing is
Select one:
a Is practically possible
b Is impractical and impossible
c Is impractical but possible
d Is always possible
Benefits of Independent Testing
Select one:
a Independent Testers can test better than developers
b Independent testers see other and different defects and are unbiased
c Independent Testers cannot identify defects
d Independent testers are much more qualified than Developers
Validation involves which of the following
i Helps to check the Quality of the Built Product
ii Helps to check that we have built the right product
iii Helps in developing the product
iv Monitoring tool wastage and obsoleteness
Select one:
a Options i,ii,iii,iv are true
b i,ii,iii are true and iv is false
c ii is true and i,iii,iv are false
d iii is true and i,ii,iv are false
Trang 12Question 40
Correct
Mark 1.00 out of
1.00
◄ Slides
Learning Outcomes ►
Which of the following is a KEY task of a tester?
Select one:
a Writing a test strategy for the project
b Deciding what should be automated
c Reviewing tests developed by others
d Writing test summary reports
Return to: Week 1