3RD LAYER EXCAVATION... B2 SLAB CONSTRUCTION WITH MASS PILECAPS... EXTERNAL WALL WATER PROOFING AND BACKFILL SAND... EXCAVATION FOR ZONE 4ZONE 3 ZONE 2 In the part of zone 4Second excava

Trang 2

ZONE 2

ZONE 3ZONE 4

Trang 3

3RD LAYER EXCAVATION

Trang 4

ZONE 3ZONE 2

STEEL SHEET PILE AND H STEEL PILE INSTALLATION

zone 1 construction : 7/15~7/26zone 2 construction : 7/17~7/29

Trang 5

zone 2 construction : 7/24~8/2

FIRST LAYER EXCAVATION TO -1.7M

DEADLINE: 7/14/17~8/2/17

Trang 6

First layer shoring installation at -1.3mPlatform installation at +0.25m

ZONE 3ZONE 2

INSTALL FIRST LAYER SHORING SYSTEM

zone 3 construction : 7/16~8/4 zone 1 construction : 7/27~8/10zone 2 construction : 7/26~8/9

Trang 7

zone 3 construction: 7/26~8/19 zone 1 construction : 8/6~8/20zone 2 construction : 8/5~8/24

SECOND LAYER EXCAVATION TO -4.4M

DEADLINE: 7/26/17~8/24/17

Trang 8

Second layer shoring installation at -4.0m

ZONE 3ZONE 2

INSTALL SECOND LAYER SHORING

SYSTEM

zone 3 construction : 8/2~8/2626zone 1 construction : 8/16~8/30zone 2 construction : 8/12~8/31

Trang 9

zone 3 construction: 8/12~9/5 zone 1 construction : 8/26~9/9zone 2 construction : 8/22~9/10

THIRD LAYER EXCAVATION TO -6.0M

PILECAP TO -6.45M

DEADLINE: 8/12/17~9/10/17

Trang 10

HACK PILE HEAD,ANTI TERMITE ,LEAN CONCRETE,

WATERPROOF FOR SMALL PILECAP

zone 3 construction : 8/17~9/1515zone 1 construction : 8/31~9/19

ZONE 3ZONE 2

LEAN CONCRETE

zone 2 construction : 8/27~9/15

HACK PILE ANTI TERMITE WATERPROOF FOR SMALL PILE CAP

Trang 11

SMALL PILECAPS CONSTRUCTION

DEADLINE : 8/22/17~9/27/17

zone 3 construction : 8/22~9/2020zone 1 construction : 9/7~9/26zone 2 construction : 9/3~9/27

SMALL PILECAPS

Trang 12

HACK PILE HEAD,ANTI TERMITE ,LEAN CONCRETE,

WATERPROOF FOR BIG PILECAP AND B2 SLAB

zone 3 construction : 8/29~9/2222zone 1 construction : 9/16~10/5

ZONE 3ZONE 2

LEAN CONCRETE

zone 2 construction : 9/10~10/4

HACK PILE ANTI TERMITE WATERPROOF FOR BIG PILECAPS AND B2 SLAB

Trang 13

B2 SLAB CONSTRUCTION WITH MASS PILECAPS

Trang 14

REMOVE SECOND LAYER SHORING SYSTEM

zone 3 construction : 11/2~11/1111zone 1 construction : 11/5~11/14

ZONE 3ZONE 2

zone 2 construction : 11/9~11/23

Trang 15

B2 COLUMN AND SHEAR WALL CONSTRUCTION

DEADLINE : 11/2/17~11/23/17

zone 3 construction : 11/2~11/1111zone 1 construction : 11/5~11/14zone 2 construction : 11/9~11/23

Trang 16

B1 SLAB CONSTRUCTION

zone 3 construction : 12/2~12/2121zone 1 construction : 12/5~12/24zone 2 construction : 12/4~12/23

ZONE 3ZONE 2

Trang 17

REMOVE FIRST LAYER SHORING SYSTEM

DEADLINE : 12/22/17~1/7/18

zone 3 construction : 12/22~12/3131zone 1 construction : 12/25~1/3zone 2 construction : 12/24~1/7

Trang 18

B1 COLUMN AND SHEAR WALL CONSTRUCTION

DEADLINE : 1/1/18~1/27/18

zone 3 construction : 1/1~1/2020zone 1 construction : 1/4~1/23zone 2 construction : 1/8~1/27

ZONE 3ZONE 2

B1 COLUMN AND SHEAR WALL CONSTRUCTION

First excavation to -2.1mZONE 4

Trang 19

EXTERNAL WALL WATER PROOFING

AND BACKFILL SAND

Trang 21

EXCAVATION FOR ZONE 4

Trang 22

EXCAVATION FOR ZONE 4

ZONE 3

ZONE 2 In the part of zone 4Second excavation to

-4.1mZONE 4

Trang 23

EXCAVATION FOR ZONE 4

-6.0m

REMOVE SHORING SYSTEM AND FLATFORM