3RD LAYER EXCAVATION... B2 SLAB CONSTRUCTION WITH MASS PILECAPS... EXTERNAL WALL WATER PROOFING AND BACKFILL SAND... EXCAVATION FOR ZONE 4ZONE 3 ZONE 2 In the part of zone 4Second excava
Trang 2ZONE 2
ZONE 3ZONE 4
Trang 33RD LAYER EXCAVATION
Trang 4ZONE 3ZONE 2
STEEL SHEET PILE AND H STEEL PILE INSTALLATION
zone 1 construction : 7/15~7/26zone 2 construction : 7/17~7/29
Trang 5zone 2 construction : 7/24~8/2
FIRST LAYER EXCAVATION TO -1.7M
DEADLINE: 7/14/17~8/2/17
Trang 6First layer shoring installation at -1.3mPlatform installation at +0.25m
ZONE 3ZONE 2
INSTALL FIRST LAYER SHORING SYSTEM
zone 3 construction : 7/16~8/4 zone 1 construction : 7/27~8/10zone 2 construction : 7/26~8/9
Trang 7zone 3 construction: 7/26~8/19 zone 1 construction : 8/6~8/20zone 2 construction : 8/5~8/24
SECOND LAYER EXCAVATION TO -4.4M
DEADLINE: 7/26/17~8/24/17
Trang 8Second layer shoring installation at -4.0m
ZONE 3ZONE 2
INSTALL SECOND LAYER SHORING
SYSTEM
zone 3 construction : 8/2~8/2626zone 1 construction : 8/16~8/30zone 2 construction : 8/12~8/31
Trang 9zone 3 construction: 8/12~9/5 zone 1 construction : 8/26~9/9zone 2 construction : 8/22~9/10
THIRD LAYER EXCAVATION TO -6.0M
PILECAP TO -6.45M
DEADLINE: 8/12/17~9/10/17
Trang 10HACK PILE HEAD,ANTI TERMITE ,LEAN CONCRETE,
WATERPROOF FOR SMALL PILECAP
zone 3 construction : 8/17~9/1515zone 1 construction : 8/31~9/19
ZONE 3ZONE 2
LEAN CONCRETE
zone 2 construction : 8/27~9/15
HACK PILE ANTI TERMITE WATERPROOF FOR SMALL PILE CAP
Trang 11SMALL PILECAPS CONSTRUCTION
DEADLINE : 8/22/17~9/27/17
zone 3 construction : 8/22~9/2020zone 1 construction : 9/7~9/26zone 2 construction : 9/3~9/27
SMALL PILECAPS
Trang 12HACK PILE HEAD,ANTI TERMITE ,LEAN CONCRETE,
WATERPROOF FOR BIG PILECAP AND B2 SLAB
zone 3 construction : 8/29~9/2222zone 1 construction : 9/16~10/5
ZONE 3ZONE 2
LEAN CONCRETE
zone 2 construction : 9/10~10/4
HACK PILE ANTI TERMITE WATERPROOF FOR BIG PILECAPS AND B2 SLAB
Trang 13B2 SLAB CONSTRUCTION WITH MASS PILECAPS
Trang 14REMOVE SECOND LAYER SHORING SYSTEM
zone 3 construction : 11/2~11/1111zone 1 construction : 11/5~11/14
ZONE 3ZONE 2
zone 2 construction : 11/9~11/23
Trang 15B2 COLUMN AND SHEAR WALL CONSTRUCTION
DEADLINE : 11/2/17~11/23/17
zone 3 construction : 11/2~11/1111zone 1 construction : 11/5~11/14zone 2 construction : 11/9~11/23
Trang 16B1 SLAB CONSTRUCTION
zone 3 construction : 12/2~12/2121zone 1 construction : 12/5~12/24zone 2 construction : 12/4~12/23
ZONE 3ZONE 2
Trang 17REMOVE FIRST LAYER SHORING SYSTEM
DEADLINE : 12/22/17~1/7/18
zone 3 construction : 12/22~12/3131zone 1 construction : 12/25~1/3zone 2 construction : 12/24~1/7
Trang 18B1 COLUMN AND SHEAR WALL CONSTRUCTION
DEADLINE : 1/1/18~1/27/18
zone 3 construction : 1/1~1/2020zone 1 construction : 1/4~1/23zone 2 construction : 1/8~1/27
ZONE 3ZONE 2
B1 COLUMN AND SHEAR WALL CONSTRUCTION
First excavation to -2.1mZONE 4
Trang 19EXTERNAL WALL WATER PROOFING
AND BACKFILL SAND
Trang 21EXCAVATION FOR ZONE 4
Trang 22EXCAVATION FOR ZONE 4
ZONE 3
ZONE 2 In the part of zone 4Second excavation to
-4.1mZONE 4
Trang 23EXCAVATION FOR ZONE 4
-6.0m
REMOVE SHORING SYSTEM AND FLATFORM