Sales and Operations Planning Some organizations use the term sales operations and planning rather than aggregate planning Sales and operation planning Intermediate-range planning d
Trang 1Aggregate Planning and Master Scheduling
Chapter 11
McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc All rights reserved.
Trang 2Chapter 11: Learning Objectives
You should be able to:
1. Explain what aggregate planning is and how it is useful
2. Identify the variables decision makers have to work with in aggregate planning and some of the
possible strategies they can use
3. Describe some of the graphical and quantitative techniques planners use
4. Prepare aggregate plans and compute their costs
5. Describe the master scheduling process and explain its importance
Trang 4Sales and Operations Planning
Some organizations use the term sales operations and planning
rather than aggregate planning
Sales and operation planning
Intermediate-range planning decisions to balance supply and demand, integrating
financial and operations planning
Since the plan affects functions throughout the organization, it is typically prepared with
inputs from sales, finance, and operations
Trang 5Overview of Planning Levels
Trang 6The Planning Sequence
Trang 7Why Use Aggregate Planning
Why do organizations need to do aggregate planning?
Planning
It takes time to implement plans
Strategic
Aggregation is important because it is not possible to predict with accuracy the timing and
volume of demand for individual items
It is connected to the budgeting process
It can help synchronize flow throughout the supply chain; it affects costs, equipment utilization;
employment levels; and customer satisfaction
Trang 8firm’s non-operations personnel
Aggregate units of output per month
Dollar value of total monthly output
Total output by factory
Measures that relate to capacity such as labor hours
Trang 9Dealing with Variation
Most organizations use rolling 3, 6, 9 and 12 month forecasts
Forecasts are updated periodically, rather than relying on a once-a-year forecast
or expected supply and to develop revised plans
Trang 10Dealing with Variation
Strategies to counter variation:
Maintain a certain amount of excess capacity to handle increases in demand
Maintain a degree of flexibility in dealing with changes
Hiring temporary workers
Using overtime
Wait as long as possible before committing to a certain level of supply capacity
Schedule products or services with known demands first
Wait to schedule other products until their demands become less uncertain
Trang 11Forecast of aggregate demand for the intermediate
range
Develop a general plan to meet demand requirements
Update the aggregate plan periodically (e.g., monthly)
Overview of Aggregate Planning
Trang 12Demand and Supply
Aggregate planners are concerned with the
Demand quantity
If demand exceeds capacity, attempt to achieve balance by altering capacity, demand, or
both
Timing of demand
Even if demand and capacity are approximately equal, planners still often have to deal with
uneven demand within the planning period
Trang 13Aggregate Planning Inputs
Trang 14Aggregate Planning Outputs
Total cost of a plan
Trang 15Aggregate Planning Strategies
Trang 16Demand Options
Pricing
Used to shift demand from peak to off-peak periods
Price elasticity is important
Promotion
Advertising and other forms of promotion
Back orders
Orders are taken in one period and deliveries
promised for a later period
Trang 18Aggregate Planning Pure Strategies
Maintaining a steady rate of regular-time output while meeting variations in
demand by a combination of options:
inventories, overtime, part-time workers, subcontracting, and back orders
expected demand for that period.
Trang 19Uneven Demand and Two Strategies:
Trang 20Chase Approach
planning horizon
Investment in inventory is low
Labor utilization in high
The cost of adjusting output rates and/or workforce levels
Trang 22Techniques for Aggregate Planning
General procedure:
1. Determine demand for each period
2. Determine capacities for each period
3. Identify company or departmental policies that are pertinent
4. Determine unit costs
5. Develop alternative plans and costs
6. Select the plan that best satisfies objectives Otherwise return to step 5
Trang 23Trial-and-Error Techniques
Trial-and-error approaches consist of developing simple table or graphs that enable
planners to visually compare projected demand requirements with existing capacity
Alternatives are compared based on their total costs
Disadvantage of such an approach is that it does not necessarily result in an optimal
aggregate plan
Trang 24Trial-and-Error Technique Assumptions
1. The regular output capacity is the same in all periods
2. Cost is a linear function composed of unit cost and number of units
3. Plans are feasible
4. All costs are associated with a decision option can be represented by a lump sum
5. Cost figures can be reasonably estimated and are constant for the planning period
6. Inventories are built up and drawn down at a uniform rate throughout each period
7. Backlogs are treated as if they exist the entire period
Trang 25Cumulative Graph
Trang 26Mathematical Techniques
Simulation models
acceptable solutions to problems
Trang 27Aggregate Planning in Services
Hospitals:
Aggregate planning used to allocate funds, staff, and supplies to meet the demands of patients for their
medical services
Airlines:
Aggregate planning in this environment is complex due to the number of factors involved
Capacity decisions must take into account the percentage of seats to be allocated to various fare classes in
order to maximize profit or yield
Restaurants:
Aggregate planning in high-volume businesses is directed toward smoothing the service rate, determining
workforce size, and managing demand to match a fixed capacity
Can use inventory; however, it is perishable
Trang 28Aggregate Planning in Services
The resulting plan in services is a time-phased projection of service staff
requirements
Aggregate planning in manufacturing and services is similar, but there are some key
differences related to:
1. Demand for service can be difficult to predict
2. Capacity availability can be difficult to predict
3. Labor flexibility can be an advantage in services
4. Services occur when they are rendered
Trang 29Aggregate Plan
Aggregate Plan
Disaggregation
Master Schedule
Master Schedule
Trang 30Disaggregating the Aggregate Plan
Master schedule:
Trang 31Master Scheduling
The heart of production planning and control
It determines the quantity needed to meet demand from all sources
Provides senior management with the ability to determine whether the business plan and its
strategic objectives will be achieved
Trang 32The Master Scheduler
The master scheduler’s duties:
Providing delivery dates for orders
Evaluating the impact of production or delivery delays
Revising master schedule when necessary because of insufficient supplies or capacity
Bring instances of insufficient capacity to the attention of relevant personnel so they
can participate in resolving conflicts
Trang 33Time Fences
Period
“frozen”
(firm or fixed)
“slushy”
somewhat firm
“liquid”
(open)
1 2 3 4 5 6 7 8 9
Trang 34The Master Scheduling Process
Master Production Schedule
Trang 35Master Scheduling Process
The master production schedule (MPS) is one of the primary outputs of the
master scheduling process
Once a tentative MPS has been developed, it must be validated
Rough cut capacity planning (RCCP) is a tool used in the validation process
Approximate balancing of capacity and demand to test the feasibility of a master schedule
Involves checking the capacities of production and warehouse facilities, labor, and vendors to
ensure no gross deficiencies exist that will render the MPS unworkable
Trang 36MPS – Forecasts and Customer Orders
Trang 37MPS – Projected On Hand
Trang 38Determining MPS and
Projected On Hand
Week
Inventory from Previous Week Requirements
Inventory before MPS
(70) MPS
Projected Inventory
Trang 39Adding MPS and Projected On Hand
to the MPS
Trang 40Available-to-Promise