1. Trang chủ
  2. » Kinh Doanh - Tiếp Thị

Operations management 12th stevenson ch07 learning curves

25 93 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 25
Dung lượng 1,65 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Interesting Characteristics of Learning The learning effect is predictable  Every doubling of repetitions results in a constant percentage decrease in the time per repetition... Learn

Trang 1

Learning Curves

Supplement 7

McGraw-Hill/Irwin

Trang 2

Supplement 7: Learning Objectives

You should be able to:

Trang 3

Learning Curves

Learning curve

 The degree of improvement is a function of the task being done

Short, routine tasks will show modest improvement relatively quickly

Longer, more complex tasks will show improvement over a longer interval

Trang 4

Learning

Trang 5

The Learning Effect

Effort expended prior to the start of work

 Changes made after production has begun

Changes in work methods

Changes in tooling and equipment

 Managerial factors

Improvements in planning, scheduling, motivation, and control

Trang 6

Interesting Characteristics of Learning

 The learning effect is predictable

 Every doubling of repetitions results in a constant percentage decrease in the

time per repetition

Trang 7

Learning Curves: On a Log-Log Graph

Trang 8

Learning Percentage

90% learning percent means 10% decrease in unit time with

each doubling of repetition

80% learning percent means 20% decrease in unit time with

each doubling of repetition

Question: What does 100% learning percent imply?

Trang 9

7

8 5.12 (.8)(6.4) = (.8)(.8)(.8)(10) = (.8) 3 (10) 1.28 9

Trang 10

Learning Illustrated

 Each time cumulative output doubles, the time per unit for that amount should be approximately

equal to the previous time multiplied by the learning percentage

 If the first unit of a process took 100 hours and the learning rate is 90%:

Unit Unit Time (hours)

Trang 11

Unit Times: Formula Approach

logarithm natural

for the stands

ln

percentage rate

learning

2 ln

ln

unit first

for Time

unit

th for

Time

where

1 1

T

n T

n T

T

n

b n

Trang 12

Example: Formula Approach

 If the learning rate is 90, and the first unit took 100 hours to complete, how

long would it take to complete the 25th unit?

hours 3068

61

25 100

25

100

15200

2 ln

90 ln 25

Trang 13

Unit Times: Learning Factor Approach

 The learning factor approach uses a table that shows two things for selected

learning percentages:

complete a given number of units.

Trang 14

Example: Learning Factor Approach

 If the learning rate is 90, and the first unit took 100 hours to complete, how

long would it take to complete the 25th unit?

 How long would it take to complete the first 25 units?

hours 3

61

613

771 ,

1

713

7 1

Trang 15

Learning Curves Example S-2

A contract calls for the production of 20 jets The initial unit

required 400 days of direct labor The learning percent is 80%

Trang 16

Learning Curves Example S-2

Q1: Calculate the time of the 5th unit

b = ln(.8) / ln(2) = -.3219

n b = 5 (-.3219) = 5956

T5 = (400)(.5956) = 238.24

Trang 17

Learning Curves Example S-2

Q1: Calculate the time of the 5th unit

using the learning Curve Coefficients table (7S-1, page 346)

n b = 596 (Unit Time for 85% and n = 5)

T 5 = (400)(.596) = 238.4

Trang 18

Unit Time

Total Time

Unit Time

Total Time

Unit Time

Total Time

Unit Time

Total Time

Unit Time

Total Time

Trang 19

Learning Curves Example S-2

Q2 – Expected time for the 20th jet

T20 = (400) X (.381) = 152.4 labor days

Q3 – Expected total time for all 20 jets

T1-20 = (400) X (10.485) = 4,194 labor days

Q4 – Average time per jet:

Average time = 4,194/20 = 209.7 labor days

Trang 20

Learning Curves Example

Given T2 = 10 and 80% learning percent, find the expected time for the 5th unit

T2 = 10 = T1 X (.8)

T1 = 10 / 8 = 12.5

T5 = 12.5 X 0.596 = 7.45

Trang 21

Learning Curve Applications

Useful application areas:

Trang 22

Cautions and Criticisms

1 Learning rates may differ from organization to organization and by type of work

Base learning rates on empirical studies rather than assumptions where possible

2 Projections based on learning curves should be regarded as approximations of actual

times

3 Because time estimates are based on the first unit, care should be taken to ensure

that the time is valid

4 It is possible that at some point the curve might level off or even tip upward

Trang 23

Cautions and Criticisms

5 Some of the improvements may be more apparent than real: improvements in times

may be caused by increases in indirect labor costs

6 In mass production situations, learning curves may be of initial use in predicting how

long it will take before the process stabilizes

 The concept does not usually apply because improvement in time per unit is almost imperceptible

Trang 24

Cautions and Criticisms

7 Users of learning curves fail to include carryover effects from previous experiences

8 Shorter product life cycles, flexible manufacturing, and cross-functional workers can

affect the ways in which learning curves may be applied

Trang 25

Operations Strategy

Learning curves have strategic implications for:

 As volume increases, operations is able to move quickly down the learning curve

Reduced cost  improved competitive advantage

 Can lead to more realistic time estimates, thus leading to more accurate capacity needs

assessment

Ngày đăng: 14/02/2019, 11:02

w