CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work THE SUNCASA PROJECT CDCC JSC CATDONG CONSTRUCTION JOINT STOCK COMPANY METHOD OF STATEMENT FOR BRIC
Trang 1CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
THE SUNCASA PROJECT
CDCC JSC CATDONG CONSTRUCTION JOINT STOCK COMPANY
METHOD OF STATEMENT
FOR BRICK , PLASTERING,CEILING, PAINTING,TILING
DOOR & WINDOOW WORK
CDCC SUBMISSION No SC-002
REVISION No.00 20Dec 2017
Trang 2THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
TABLE OF CONTENTS
1 GENERAL
1.1 Specification/Standard Reference
1 2 Material Supply, Storing and Handling
3 BRICK LAYING AND PALSTERING WORK
Trang 3CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
1.GENERAL
This method statement will cover for all task including Brick , plastering ,ceiling , painting,tiling work of clubhouse and central park & 53 units of terrace house & shop house
1.1 Specification, Standard, Drawing
1 Concrete lintel & stifferner
mix-insitugrade 200MPa Mix design to be submitted for approval
follow TCVN
equivalent , sample to
be submitted for approval
2 BRICK & PLASTERING WORK
Trang 4THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
Minimum mixing period of 1 to 2 minutes after water is added - shall be
checked by QA/QC in timely manner for each mixing place
Mixed mortar shall be used within 60 minutes; Mixed mortar if not used within
60 minutes shall be discarded as “Reject” - shall be checked by QA/QC Mixed mortar is transported by wheelbarrows or other appropriate method The size of gauge box or plastic tank (0.018m3), i.e 01 bag of cement (50kg
or 0.036m3) mixed with 12 gauge box (0.162m3) of sand
Trang 5CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.2 Laying and Jointing
All clay bricks shall be moistened by water before being laid Top of walls, where left off, shall be well wetted before recommencing laying
Trang 6THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
All joints are to be flushed up and grouted mortar in solid as the work
proceeds
Walls shall be constructed up in a uniform manner, no one portion being
raised more than 1 m above another at any time
Before mortar sets, joints shall be tooled by manual / electrical hand tools to required profiles to receive the appropriate finishing
Completed faces shall be left smooth, dense and free from voids and other irregularities
Tools of standad types and designs shall be used for all operations
Joints or edges, which are to receive sealing materials, shall be raked out
before mortar has set, to the required depth, and contact / exposed surfaces left clean and smooth
When cured and before mortar grouting, joints shall be re-inspected and re- pointed as directed with Engineer
During laying, work shall be covered and protected to extend hydration
period without any damage to the work
Trang 7CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.3 Height of Walls
The following walls shall be fully constructed between floor slab and upper level slab unless otherwise indicated on the Drawings:
walls along corridors,
wall surrounding rooms to be covered by gas fire protection system,
wall surrounding rooms not to be provided with suspended ceiling systems,
wall surrounding kitchen or pantry, toilet, shower room and locker room walls
:> The bottom level of top concrete stiffener beam for walls shall be at least 25
mm higher than finished ceiling level
Trang 8THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.4 Openings for Frames
:> Openings for doors, windows, etc., shall be properly marked out and left unbuilt until the frames have been fixed in position
:> Width of opening up to 2000mm
:> Width of opening up to 2000 mm
:> All door frames, window frames and louver frames, plates, etc., shall be bedded in mortar of type M2 specified in Division 20030
:> All frames shall be carefully fixed and stayed in position and shall be
anchored into walls, one end securely to frame, and other end built into joints of masonry Anchors shall be spaced as shown on the drawings
:> In case the width of opening wall greater than 2.7m, it shall be provide
stiffener column as showing on the sketch
Trang 9CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
Trang 10THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.5 Holes, Openings, Mortises, Chases, etc
:> Holes, mortises, chases, grooves, etc., shall be cut or formed as required for all pipes, ducts, cables, beams and the like
:> All supports for pipes or ducts shall be cut and pinned or built-in
Trang 11CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
:> Masonry shall be made good around pipes, ducts, cables, bearers and
supports by building in, grouting and neatly and tightly sealing in either mortar, sealants or fire proof materials
2.6 Reinforcement Columns and Beams
:> Every vertical angle in masonry walls shall be made by constructing a
reinforced concrete stiffener column to the full wall thickness - Tops of all walls shall, according to the details indicated on the Drawings shall always
be finished by constructing a reinforced concrete stiffener beam
:> The height of brick wall must not exceed 3200 mm and the length of brick wall must not exceed 8000 mm If exceed, the brick wall shall be furnished with RC elements And also for every end of brick wall and every joint of brick wall must be furnished with RC elements
Trang 12THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
Trang 13CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.7 Bonding Ends and Heads of Walls
:> Masonry walls abutting concrete or steel columns and beams shall be
adequately tied by the use of 6 mm diameter steel reinforcing bars or approved anchors/bonding ties, built into the concrete and securely fixed to steelwork
:> stacking method
:> Walls shall have bars and anchors / bonding ties every 550 mm vertically at ends - Dowel bars showing on the sketch above are to be alternative to chemical anchor as approved
Trang 14THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
Trang 15CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.9 Completion Requirements
:> Exposed surfaces shall be clean and free from dust, dirt, mortar smears or streaks, broken units, chips, cracks, misaligned or improperly fitted joints, stains, discoloration, or other defects or damage
:> Each partition or screen wall shall be erected straight, plumb, level and
accurately positioned at locations required
Trang 16THE SUNCASA PROJECT
CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
2.10 Anchors / Bonding for Lintel Beam
:> Brick wall T=80
:> Brick wall T=180
Trang 17CDCC JSC - MS002-Brick Plastering Tiling Ceiling Painting Door & windown & door work
Trang 18THE SUNCASA PROJECT MS001-Earthwork & structure work
:> Dowel bars D6 showing on the sketch above are to be alternative to chemical anchor
as approved
:> The alternative size and spacing of rebar for stirrup shall be confirmed as development
of the drawing
:> Width of opening up to 1200mm
:> Reinforcement of rebar