019-026, June 2013 Available online at http://academeresearchjournals.org/journal/ijps ISSN 2331-1827 ©2013 Academe Research JournalsISSN 2331-1827 Full Length Research Paper Power flow
Trang 1International Journal of Physical Sciences Vol 1(2), pp 019-026, June 2013 Available online at http://academeresearchjournals.org/journal/ijps ISSN 2331-1827 ©2013 Academe Research JournalsISSN 2331-1827
Full Length Research Paper
Power flow analysis of Rafah governorate distribution
network using ETAP software
Nadia M Mahdi
Electrical Engineering, Technical Administration, GEDCO Company, Gaza, Palestine
E-mail: engineer_nadia@yahoo.com
Accepted 29 May, 2013
The results of a load flow analysis can be used for operational purposes to evaluate various operating states of an existing system They can also be used in the planning stages to evaluate possible future extension projects This paper discusses the analysis of the power distribution network in Rafah governorate by using ETAP software The aim is to evaluate the technical status of the present medium voltage network (22-kV) The problems and challenges faced by the existing network are analyzed Those problems include the power deficit, high power losses, poor voltage levels and feeders’ overloading Then some solution techniques are suggested considering the system current state and future growth for different scenarios for each problem to obtain a full understanding of the system problems and solutions
Key words: Distribution network, power flow analysis, ETAP
INTRODUCTION
The power-flow analysis of a distribution feeder is similar
to that of an interconnected transmission system
Typically, before starting the power-flow analysis, the
three-phase voltages at the substation and the complex
power of all of the loads and the load model must be
known A load flow study determines the voltage, current,
power and reactive power in various points and branches
of the system under simulated conditions of normal
operation (William, 2002) Load flow studies are essential
in optimizing existing networks, ensuring an economical
and efficient distribution of loads, and plan future
networks (Jan de Kock and Kobus, 2004) The analysis
of a distribution feeder will typically consist of a study of
the feeder under normal steady-state operating
conditions All of the approximate methods of modeling
assume perfectly balanced three-phase systems,
balanced three-phase loads, and perfectly transposed
three-phase line segments (William, 2002)
There are wide ranges of power system analysis
programs available in the world market that perform all
sorts of electrical analyses They range from basic,
commercially packages to large, complex programs
developed for a specific customer (Jan de Kock and
Kobus, 2004) The software used in this paper is ETAP It
is for the design, simulation, and analysis of generation, transmission, and distribution power systems For a power distribution system, it is capable of calculating balanced and unbalanced load-flow This analysis produces detailed reports of system losses, line flows, and voltage at every node The software is capable of recommending optimum capacitor placement, and wire size upgrades (Barn and Jewell, 2005) ETAP Load Flow Analysis module calculates the bus voltages, branch power factors, currents, and power flows throughout the electrical system on both radial and loop systems (ETAP 7.0.0 User Manual, 2009)
As a power distribution system load grows, the system power factor usually declines Load growth and a decrease in power factor leads to a number of challenging problems such as: voltage regulation problems, increased system losses, power factor penalties and reduced system capacity (Holm et al., 2010) The distribution network in Rafah experiences many technical problems which need quick solutions The most pressing problems are high power losses and poor voltage especially at the feeder ends To face these challenges, a power flow study for the distribution network must be carried out to find the suitable technical
Trang 2Figure 1 The main feeders of Rafah Governorate
solutions The main contribution of this paper is that it
evaluated the 22-kV network in Rafah and suggests the
suitable available technical solutions
METHODOLOGY
First of all, the MV grid was analyzed using ETAP
software in a way such that all problems and deficiencies
are investigated clearly and then suitable solutions are
tested by simulation
Description of the existing network
Rafah is a Palestinian city that is located in the south of
Gaza Strip on the border between Egypt and Palestine
Rafah receives power through four feeders operating at
22 kV as shown in Figure 1 (Gaza Electricity Distribution
Corporation [GEDCO], 2010) Three of the feeders are
from Egypt and they enter Rafah from the southern side
The first feeder has a maximum capacity of 5 MW The
second feeder has a maximum capacity of 12 MW, and
it’s divided into two feeders The fourth feeder enters
Rafah from its eastern side and is owned by the Israeli
Electric Company (IEC) All those feeders are governed
by Gaza Electric Distribution Corporation (GEDCO), the
unique electric distribution company in Gaza Strip MV
distribution system is stepped down to 400-V at
distribution transformers Then the power is distributed to
individual consumers via low voltage distribution
networks at 400-V This network serves 22,038
customers which represent 12% of the total customers of
GEDCO in year 2011 The MV network falls into two
categories: overhead lines and underground cables
It is fairly wide spread in Rafah that a total length of
about 68800 m feeding 133 of distribution transformers Moreover, the overhead lines cover about 93.8% of the overall length of the network This is because the overhead network is much cheaper than the underground network Most of the 22-kV lines are constructed using ACSR 150/25, ACSR 50/8 and ACSR 95/15 conductors
It is important to know that all the previous mentioned data of Rafah network and all work done in this paper represent the network status till the end of 2011
SIMULATION RESULTS AND ANALYSIS
Since all feeders in Rafah city are in radial configuration, then each feeder can be analyzed separately The four feeders are simulated in separate projects Their one-line diagrams are drawn and their parameters are entered into ETAP software Then they are exploited in different study cases to evaluate the performance of the grid The feeders are studied assuming balanced load-flow For each study case, the program produces detailed accounts of system losses, line flows, and voltage at every node or bus These detailed reports are used to investigate all problems and deficiencies of the grid Figure 2 depicts a part of the one-line diagram of the IEC
feeder
The results of load flow module for all feeders are divided into three parts: the first part of the results is concerned with power demand and capacity issues, the second is related to the system losses, while the third part is for voltage magnitude and voltage drop at each node on the feeders
It is found that there is a deficit in the available power
by about 35% Also the grid suffers from phase load imbalance in the LV networks The line current unbalance
Trang 3Int J Phy Sci 021
Figure 2 One-line diagram of the 1st Egyptian Feeder
rate is 7.4% in average to all feeders Moreover, the
percentage voltage drop obtained by power flow solution
drops below 90% of the nominal voltage in the first one
third of the feeders’ length except the second Egyptian
feeder The estimated cost of the resulted average
energy losses reaches 3.3 million NIS for MWH and 5
million NIS for MVAR in year 2011 It is observable that
the percentage of reactive power loss is approximately
about 1.6 times more than the active power loss and this
is due to the nature of the lines which normally have the
value of X/R larger than unity In addition to these
problems, the existing grid has a poor lagging power
factor in all 22-kV feeders which stay in the range of 81 -
84%
SOLUTION TECHNIQUES
After the presentation of all problems and deficiencies of
network, the study addresses and suggests solution
techniques for those problems
Managing the growing power demand
In order to satisfy the ever increasing energy demand,
several actions have to be implemented These actions
have to be carried out in parallel Those actions include
the load balance and upgrading of the supplied power
according to the actual power demand Also it is important to predict the future growth of the power demand to be taken into account in the upgrade and planning of new projects So the forecasted growth in the power demand was evaluated for the coming ten years from 2012 to 2022 The predicted data were evaluated by excel “FORCAST” function which predicts the future values along a linear trend by using the existing values and they are shown in Figure 3 It is perfectly suitable since the existing data have a linear behavior
According to the power demand requirements, it is found that the preferred solution to support the existing load and the future demand growth is to install a new substation in Rafah as an extension to the Egyptian high voltage network The Palestinian Authority of Energy and Natural Resources in Gaza proposed a complete study of
a project to install two new substations in Gaza Strip, one
of them is intended to extend the Egyptian system and rated at 220/22 kV It will have two of three winding
power transformers rated at 60/75 MVA This substation
will feed the southern part of Gaza Strip with the required power demand
Load balancing
A three-phase, four-wire distribution system has been widely used to facilitate low voltage supply to single-
Trang 4Figure 3 Growth of peak power demand in summer
Figure 4 Power demand in balanced and unbalanced loads
phase and three-phase loads This mixed loading in the
secondary distribution system may result in serious
phase unbalance (Nikhil et al., 2011) By calculations, it is
found that the line current unbalance rate in average is
6.37% for the 1st Egyptian feeder, 9.99% for the 2nd
Egyptian feeder, 7.21% for the 3rd Egyptian feeder, and
5.76% for the IEC feeder The line current unbalance rate
(LCUR) is calculated by equation (1) as shown thus:
Max line current deviation from average
Average line currents
(1)
It is noted that the current imbalance exceeds the
standard limit of LCUR which equals 3% at maximum
Figure 4 indicates the capacity release which can be
obtained through balancing loads on the LV network
The figure shows that the load balance can release about 7% of the active and reactive powers
Voltage improvement
Voltage improvement is considered as power quality issue and there are several techniques that can be used
to improve the voltage profile of the feeders The voltage profile is enhanced by three techniques: raising the
Trang 5Int J Phy Sci 023
Figure 5 Voltage profiles of the 1st Egyptian Feeder
Figure 6 Voltage profiles of the 2nd Egyptian Feeder
sending end voltage, changing the tap settings of the
distribution transformers, and the last method is
accomplished by installation of capacitor banks
Approach 1: Raising the voltage at the feeder
sending-end
The most intuitive way in voltage improvement is to raise
the voltage at the sending end node Even though the
voltage control is done only from the substations, this
method is implemented based upon request from
technical department of Rafah branch Figures 5 to 7
show the improvement of the voltage profiles considering
both the peak and average loading cases
Since the IEC feeder suffers more voltage drop than
Egyptian feeders due to higher loading and longer length,
it is raised to 23 kV as a suitable value for the feeder to
operate within the allowable range of voltage in peak and
off-peak loading The effect of raising the sending-end
voltage is presented in Figure 8
This improvement is achieved at the expense of higher current and power demand, so this approach must be applied carefully
Approach 2: Adjustment of transformers’ tap setting
Another method that can be used to enhance the voltage levels along the feeders in the LV side is to readjust the transformers’ tap changer The transformers’ tap changer
is on high tension side and can be stepped to +1×2.5% or
to -3×2.5% Since the nominal value of the system is 22
kV, then each step can raise or lower the voltage rating
by 0.55 kV The tap changer must be adjusted to suitable
settings to suit both light and heavy loading cases The
1st Egyptian feeder is tested for this method in summer loading case and the voltage profile along the LV nodes
is shown in Figure 9 The tap changers of all transformers connected to LV nodes that experience voltage drop below 90% of the nominal value are adjusted to -3×2.5% position of their tap changers
Trang 6Figure 7 Voltage profiles of the 3rd Egyptian Feeder
Figure 8 Improvement of voltage profile on IEC feeder
Figure 9 Voltage profile variations by adjusting transformer’s tap-changer settings
Trang 7Int J Phy Sci 025
Figure 10 Voltage improvement by capacitors’ placement
Table 1 Capacitor banks and power carrying capability
Before adding capacitors After adding capacitors Capacity
release (MVA)
Sending
end PF%
Average Loading 20.5 kV Sending
end PF%
Average Loading 20.5 kV
Peak Load
Avg
Load
MW Mvar MW
Loss
Mvar Loss MW Mvar
MW Loss
Mvar Loss
83.39 6.43 4.25 0.188 0.387 96.17 6.58 1.87 0.153 0.324 1.044 0.86
Approach 3: Installation of capacitor banks
Placement of capacitors has been considered mainly to
enhance the line voltage levels above 90% of the nominal
voltage, power factor correction, and losses reduction
Power factor correction permits additional loads to be
served by the existing system In case if the transformers
or cables get overloaded, improving the power factor will
be the most economical way to reduce the current and
therefore eliminate overload condition This can be
clearly investigated by Equations 2 and 3 (Osama and
Ahmad, 2011):
initial
final
PF
PF
new
new
S
I
3V
(2)
initial
final
PF
PF
new
new
S
I
3V
(3)
Distribution losses in a facility can be reduced by addition
of capacitors as clearly investigated by Equation (4) (Osama and Ahmad, 2011):
2 initial final
PF
PF
(4) (4)
After installing the capacitor banks, the feeder was tested for a combination of different operating scenarios including under voltage of the sending end, overvoltage
of the sending end both at minimum and maximum loading cases The load flow simulation indicates that the capacitors operate with its full rating without leading to under voltage or overvoltage conditions and this is what
we are searching for Figure 10 shows the enhancement
of the voltage profile after installing the capacitor banks regarding different cases of the sending end voltage at the average loading condition
Trang 8the fifth year, the pure profit starts assuming that the
energy price is fixed at 0.28 NIS for 1 KWH and summer
loading
Conclusion
Power flow analysis is an essential step for operational
purposes to evaluate various operating states of an
existing system Also it is necessary for enhancement
and development projects By using ETAP load flow
program, it is found that the MV network in Rafah
experiences many technical problems including: deficit in
the available power, poor power factor, low voltage levels
and power losses Based on the obtained results, some
technical solutions are suggested to help in the network
improvement The solutions are tested by simulation The
proposed solutions were suggested considering the
financial investment cost and profits such that the
solutions are acceptable from the economic view ETAP
shows powerful functionalities in load flow analysis field
Thus it is strongly recommended to be available for
usage in the technical administration of GEDCO
– A Case Study Online Journal on Power and Energy Engineering (OJPEE), 2: 1
Holm RMU, Chopade PV, Prornod J (2010) Optimal Placement of Capacitor for Power Loss Reduction Using ETAP Software ICSES' 10 International Conference on Science Engineering & Spirituality Studies and Documentation Branch in Technical Administration of Gaza Electricity Distribution Corporation GEDCO (2010)
William HK (2002) Distribution System Modeling and Analysis CRC Press LLC, 39: 269