1. Trang chủ
  2. » Ngoại Ngữ

AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS

37 117 0
Tài liệu đã được kiểm tra trùng lặp

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 37
Dung lượng 4,12 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

SCHEDULING- Methodologies• Two of the most common methodologies: – Bar Charts – Critical Path • ADM: Arrow Diagramming Method • PDM: Precedence Diagramming Method • Both scheduling metho

Trang 1

AMERICAN SPORTS BUILDERS ASSOCIATION

CRITICAL PATH METHODSCHEDULING FOR SUCCESS

December 6-8, 2008 New Orleans, Louisiana

Presented By: Bill Pronevitch

Trang 2

SCHEDULING- Is It Necessary?

• Effective Project Management involves

coordinating activities such as:

– Planning

– Organizing

– Controlling Time (scheduling)

– Cost

• The “Scheduling” process forces people to:

– Quantify their effort in discrete terms

– Place tasks in proper relationships

Trang 3

SCHEDULING- Methodologies

• Two of the most common methodologies:

– Bar Charts

– Critical Path

• ADM: Arrow Diagramming Method

• PDM: Precedence Diagramming Method

• Both scheduling methods are widely used for:

– Controlling

– Making optimal use of project time

Trang 4

SCHEDULING- Bar Charts

• Bar Charts (also called “Gantt Charts”) are

primarily for controlling Time elements:

– Analyze/ specify the basic approach to be used

– Segment the work into a reasonable number of

activities that can be scheduled

– Estimate the time required to perform each activity (i.e.- activity duration)

– Place activities in “time-order” (logic)

– Adjust the chart until the specified completion date, if

Trang 5

SCHEDULING- Bar Chart

•All Activities and Status on a Single

Chart

Trang 6

SCHEDULING- Bar Charts

• Benefits:

– Plan, Schedule, and Progress on a single chart – A simple, understandable way to schedule small projects or undertakings

• Disadvantages:

– Activity-limited, can’t handle complex projects

– Doesn’t show logic ties (activity relationships)

– Insufficient detail to enable timely detection of schedule slippages on long duration activities

Trang 7

SCHEDULING: Critical Path

• The Critical Path Method (CPM) was designed

for and is useful on projects where the duration

of each activity can be with

reasonable certainty

- it predicts project overall completion

- it identifies the (critical) activities that control the overall length of the project

• CPM is widely used in: process industries

construction and plant outages/ shutdowns

Trang 8

SCHEDULING: Critical Path

• Benefits:

– Determines shortest project completion time– Identifies “critical” activities – that can not be

slipped or delayed (i.e.- “TOTAL FLOAT”)

– Shows allowable slippage for “non-critical”

activities (i.e.- “FREE FLOAT”)

• Disadvantages:

– Large number of activities required

– Difficult to read, understand, and maintain

Trang 9

SCHEDULING: CPM/ADM

• ADM (Arrow Diagramming Method):

– Arrow (line): represents an Activity

– Tail (of arrow): shows an Activity’s start

– Head (of arrow): shows an Activity’s finish– Node (or event): shown at each end

• The “Activity Number” consists of Head and Tail numbers, commonly referred to

as I-J nodes (i.e.- “I-J Method” of CPM)

Trang 10

Install Pump

Assign

Crew

(Dummy Activity – shows relationship, zero duration)

Trang 11

SCHEDULING: CPM/ADM

• Benefits:

– Allows use of “Dummy Activities” which:

• Have a “ZERO” time duration

• Can be used to show additional relationships

• Disadvantages:

– An Activity’s “Predecessor” must be complete

before the Activity can start!

– Neither the Activity’s “arrow length” or “arrow

direction” have any meaning

Trang 12

SCHEDULING: CPM/PDM

• PDM (Precedence Diagramming Method):

– Box/ Node: represents an Activity

– Line/ Arrow: represents a Precedence – with time and direction properties

• Precedence consist of two parts:

– “Relationship”: a Predecessor or Successor

– “Lag”: the (positive or negative) number of work

periods by which a specified Activity will be delayed (assumed to be “0” if not specified)

Trang 13

Pump Installation Completed

Trang 14

SCHEDULING: CPM/PDM

• Types of Relationships, Lags (aa,n):

– FS, 0: Finish-to-Start, With “0 units” of delay – FF, 7: Finish-to-Finish, with “7 units” of delay – SS, 5: Start-to-Start, with “5 units” of delay

– SF, 0: Start-to-Finish, with “0 units” of delay

Trang 15

Start –to- Finish

Finish -to- Finish Finish –to- Start

Start –to- Start

(FS,0)

(FF,5)

(SS,4) (SF,0)

Trang 16

SCHEDULING: CPM/PDM

• “6” Major Types of Constraints

– Start On: a mandatory date

– Start No Earlier Than*: can start “later”

– Start No Later Than*: can start “earlier”

– Finish On: a mandatory date

– Finish No Earlier Than*: can finish “later” – Finish No Later Than*: can finish “earlier”

* NOTE: Schedule logic drives “earlier” and

“later” start and finish dates

Trang 17

activities can never begin nor end)

– Must be eliminated prior to calculating the

schedule (i.e.- running a time analysis)

Trang 18

SCHEDULING- Hammock

PDM: Hammock (Summary) Activity

D

Trang 20

SCHEDULING – PDM/ CALC’S

• Once a network has been created and the durations estimated for each activity, both the “Total Time” to reach project

completion and each activity’s “individual” start and finish times, can be calculated

– Manual computation is easy and logical (but tedious & time-consuming on large projects)

• Forward Pass: calculates early start/finish, (ES/EF)

Trang 21

SCHEDULING – CALC’S

• FORWARD PASS:

– Calculates “Earliest Start” and “Earliest

Finish” times, observing the following rules:

• Assign an “ES” time to the first activity

• Other activities start as soon as their

“predecessor” relationships have been satisfied

• Equations:

– ES = EF (Pred.) + 1 – EF = ES + Duration - 1

Trang 22

SCHEDULING – CALC’S

• BACKWARD PASS:

– Calculates “Latest Start” and “Latest Finish” times, observing the following rules:

• Assign an “EF” time to the last activity.

• All activities finish as soon as their “Successor” relationships have been satisfied.

• Equations:

– LF = LS (Succ.) – 1 – LS = LF – Duration + 1

Trang 23

SCHEDULING – CALC’S

• PDM ACTIVITY NOTATION:

– Activity Number: unique number to an activity

– Duration: number of “work periods” assigned

– ES & EF: calculated in Forward Pass

– LS & LF: calculated in Backward Pass

Trang 27

10

1

5 5

20 6

5 24

40 6

14

19

30 5

5 9

Legend Activity ID ES

Trang 30

What is the Scheduling Process?

Report/ Status

Scheduling

Planning

Trang 31

IDENTIFY MILESTONES

• Project Start

• Project Phase Start and Finishes

• Equipment and/ or Long Lead Item

Delivery

• Project Finish

Trang 32

DEVELOP ACTIVITY LIST

(EXAMPLE: HOUSE CONSTURCTION)

Trang 33

ASSIGN DURATION TO ACTIVITES

(EXAMPLE: HOUSE CONSTRUCTION)

Trang 34

SEQUENCE ACTIVITIES

ASK THREE QUESTIONS!

• What activity must come before this one?

• What activity must come after this one?

• What activities can I perform at the same time?

Trang 35

REVIEW AND FINALIZE

• Review Relationships

• Review and Finalize Durations

• Review Resource Usage

• Review and Finalize Project End Date

– Does this achieve the desired date?

– If it does not… What is the plan NOW?!?

Trang 37

SCHEDULING- CONCLUSION

• Planning and scheduling functions are

usually performed iteratively in order to

provide for accomplishing all required

tasks within the specified time frames

• Both Critical Path Methods (ADM & PDM) create networks showing activity durations and total time for project completion

• “Failing to Plan is Planning to Fail”, hence

“Plan the Work, Work the Plan”

Ngày đăng: 06/06/2018, 20:14

TÀI LIỆU CÙNG NGƯỜI DÙNG

TÀI LIỆU LIÊN QUAN

w