OUTLINE DESIGN SPECIFICATIONS GENERAL Design Specification as submitted pursuant to Clause 4 of Annex 1 to the Instructions to Tenderers and all as may be modified in accordance with th
Trang 1Tender Documents
For
Ho Chi Minh City Urban Railway Construction Project
Ben Thanh - Suoi Tien Section (Line 1)
CONTRACT PACKAGE-1B: CIVIL (UNDERGROUND SECTION FROM KM 0+615 TO KM 2+360)
VOLUME 4 – OUTLINE DESIGN SPECIFICATIONS
TABLE OF CONTENTS
GENERAL
DESIGN CRITERIA
Trang 26.4 Transition Curves 6-1
GENERAL REQUIREMENT FOR CIVIL AND ARCHITECTURAL DESIGN
Trang 322.5 Land Subsidence and Ground Movement 22-2
GROUND MOVEMENTS AND BUILDING PROTECTION
Trang 437.2 Types of Construction 37-1
Appendix-2: Typical Building Automation System Control and Monitoring Point Schedule 39-AP2-1
Trang 5OUTLINE DESIGN SPECIFICATIONS
GENERAL
Design Specification (as submitted pursuant to Clause 4 of Annex 1 to the Instructions to Tenderers and all as may be modified in accordance with the provisions of that Annex) provide minimum standards which are to govern the design of the Permanent Works These documents shall be amalgamated to form the Contract Design Specification which will be part
of the Contractor’s Technical Proposals extant at the date of acceptance of Tender
Specifications where appropriate
The topography along the railway alignment and railway alignment are shown on the Layout Drawings attached to the Vol 6 Employer’s Drawings
The existing traffic layouts along the railway alignment are shown, for information only,
on the Traffic Management Drawings attached to the Employer’s Drawings
Trang 62 CODES AND STANDARDS
2.1 Priority of the Codes and Standards
The design and construction of the Permanent Works shall comply with following codes and standards, and the priority of these codes and standards shall be in accordance with the following sequence
Specifications, Outline Construction Specifications and other Contract Documents
with commentary enacted by the Japanese Ministry of Land, Infrastructure, Transportation and Tourism (Ministerial Ordinance, MLITT-J),
DSRSC), Railway Technical Research Institute, Japan (RTRI-J),
(STRASYA), Japan Railway Technical Service (JARTS),
Construction, Transport and Technology Agency,
Society of Heating Air Conditioning and Sanitary Engineering of Japan, and
which have been approved by HPC
In this case the Contractor shall be responsible for getting approval from MOT prior to the submission of Inception Report
The codes and standards shall be current at the time of submission of Tender except where such codes and standards are modified in the Outline Specifications and where the Contractor considers the approved or specified standards to be inappropriate for the Permanent Works Regulations made and requirements issued by the Vietnamese Government and by relevant authorities shall be followed and specified
The codes and standards listed in Appendix 28 to the Employer’s Requirements in Volume 3 were already approved or under approval procedure for the Project The Contractor does not need to get approval from Vietnamese competent organizations for the application of those standards
Trang 72.2 Codes and Standards
and Earth Retaining Structures); DSRSC-FS
Composite structures); DSRSC-SC
Following are the examples of relevant Vietnamese Standards
Trang 83 STRUCTURES AND FACILITIES TO BE DESIGNED AND CONSTRUCTED
The structures and facilities to be designed, constructed, and provided by the Contractor under this Contract are subdivided into followings, Civil Engineering Structures, Building Structures, Architectural Finishes and Electrical and Mechanical Services for Under Ground Stations Outlines are described below
It is to be noted that in addition to the Outlines of structures and facilities described below, the Contractor shall design and construct structural measures to ensure a smooth extension to CP-1a by provision all related necessary bearing structures and interface E&M features at the end wall of the Opera House station The breakthrough and connection works from CP-1a section shall not affect or damage the installed facilities in Opera House Station of CP-1b by vibration, dust etc…
3.1 Civil Engineering Structures
The civil engineering structures to be designed and constructed by the Contractor are subdivided into followings, Underground Stations, Bored Tunnels, Cut & Cover Tunnels, and Open Cut Transition Structure The location of major civil engineering structures are summarized as below
( km2+360) Details of each structure, requirements and specifications for these structures are described
in Clause 35, 36, and 37 in this Outline Design Specifications, and reference drawings are attached as Civil Structure Drawings in the Vol 6 Employer’s Drawings
3.2 Building Structures
The building structures to be designed and constructed above ground level by the Contractor are subdivided into followings, Entrance Buildings of Station, Emergency Generation Building, Roof of Open Cut Transition Structure, and Ventilation Towers The locations of major building structures are summarized as below
Trang 9(2) Emergency Generation Building
2+360)
Details of each structure, requirements and specifications for these structures are described
in Clause 35, 36, and 37 in this Outline Design Specifications, and reference drawings are attached as Building and Architecture Drawings in the Vol 6 Employer’s Drawings
3.3 Architectural Finishes for Underground Stations
The architectural finishes for underground station to be designed, constructed, and provided
by the Contractor shall include followings, but not be limited to;
Entrances, canopies screens and flat roofs, passageways, commercial areas, concourse (free concourse/ paid concourse), station platform, voids under platform, etc
Stairs, ramps, balustrades, queuing, etc
Station control room, supervisor’s office, cash and ticket handling room, staff room, staff dormitory facilities, staff toilets lockers and showers, station store, cleaner’s store, refuse storage area, etc
Commercial area and kiosk, telephones, first aid, benches, bins, artwork, inferior decoration, etc
Details of requirements and specifications for architectural finishes are described in Clause 38 in this Outline Design Specifications, and reference drawings are attached
as Building and Architecture Drawings in the Vol 6 Employer’s Drawings
Trang 103.4 Electrical & Mechanical Services for Underground Stations and Tunnels
The electrical & mechanical services for underground stations and tunnels to be designed and provided by the Contractor shall include followings, but not be limited to;
Station air conditioning, mechanical ventilation of underground plant rooms, tunnel ventilation system, smoke control and extraction system, etc
sump pumps, fire fighting pumps, jockey pumps, seepage and sewage pump, etc
liquid level controllers, etc
Complete fire suppression system in the station, tunnel and buildings including hydrants, hose reels, fire hose cabinets, fire mains in the tunnel, potable extinguishers, clean gas based flooding system and pipe line network with control valves for hydrants and Fire Department
Uninterruptible Power Supply (UPS) for feeding all emergency loads, complete fire detection and alarm system, etc
softwares
Details of requirements and specifications for electrical and mechanical services are described in Clause 39 in this Outline Design Specifications, and reference drawings are attached as E & M Drawings in the Vol 6 Employer’s Drawings
Trang 11DESIGN CRITERIA
The design life of a structures and equipments is that period for which it is designed to fulfill its intended function when appropriately inspected and maintained in accordance with agreed procedures The assumption of a design life for a structure or equipment does not necessarily mean that the structure will no longer be fit for its purpose at the end of that period Neither will it necessarily continue to be serviceable for that length of time without adequate and regular inspection and maintenance including replacement of spare parts/consumables as well as minor repair and overhaul
Requirements for durability, including choice of materials and detailed design requirements to achieve good durability, are given in Clause 26 of this Outline Design Specifications
The design life of each structure, facilities and systems are defined as follows
The design life of all civil engineering structures is considered a minimum of 100 years unless otherwise specified in these Outline Design Specifications or Outline Construction Specifications In case design life of proposed structures by the Contractor seems insufficient, the Employer’s Representative may reject the Contractor’s proposal
The design life of all building structures is considered a minimum of 50 years unless otherwise specified in these Outline Design Specifications or Outline Construction Specifications In case design life of proposed structures by the Contractor seems insufficient, the Employer’s Representative may reject the Contractor’s proposal
The design life of all facilities, systems and services including Environmental Control Systems, water supply, plumbing and drainage services, fire protection services, electrical works, is considered a minimum of 30 years unless otherwise specified in these Outline Design Specifications or Outline Construction Specifications
Trang 125 RAILWAY DESIGN REQUIREMENTS
5.1 General
and operation of the railway equipment The Contractor of CP-1b shall design and install all related facilities of railway system at the OPH station ready for the extension to CP-1a
trackway basic structure (including a first trackbed concrete in bored tunnel) as indicated in the Employer’s Requirements and in this Outline Design Specifications The design, provision and installation of the second trackbed concrete, trackslabs and trackwork will be undertaken by Contract Package 3 Contractor (CP-3 Contractor) A fundamental obligation of the Contractor is to co-ordinate and co-operate with the CP-3 Contractor so that the design and installation of all components of the railway are compatible
cables, the traction power electrification equipment, electrical cables, electrical and mechanical equipment, telecommunication links, etc that are required for the railway will be undertaken by the CP-3 Contractor Similar co-ordination and co-operation obligations as expressed in Clause 5.1.2 above apply
the CP-3 Contractor The CP-3 Contractor will supply and fit brackets, nuts and bolts and other fixings for the support of its equipment The extent and detail of such provisions are to
be determined by the Contractor making due enquiries, during the design co-ordination period, from the CP-3 Contractor engaged to provide railway operating equipment and to carry out trackwork construction
CP-3 Contractor and with the Employer and for ensuring that the design incorporates such fixings
as are required in order to avoid any necessity for the CP-3 Contractor or the Employer to drill, weld, burn or cut any part of the structure, including tunnel linings, when carrying out installations
The Contractor shall provide permanent survey points and bench marks and shall provide full details of co-ordinates and levels to the CP-3 Contractor
The CP-3 Contractor will carry out the second trackbed concrete for the trackwork In this regard, the Contractor shall incorporate starter bars into, the lower slabs in the cut & cover tunnel section and station, and first trackbed concrete in the bored tunnel section, to facilitate anchorage of the second trackbed concrete The Contractor shall coordinate with the CP-3 Contractor as to the size and location of the starter bars The Contractor shall provide drainage pipes, channels and catch basins in the first trackbed concrete
Trang 135.2 Stray Current Corrosion
Stray current collection matt and stray current monitoring facilities will be designed and provided by the CP-3 Contractor The Contractor shall co-operate with the CP-3 Contractor and install stray current collection matt beneath trackbed concrete
5.3 Rolling Stock and Construction Gauges
equipment to be provided for the railway and outside the Construction Gauge
5.4 Clearance
Structures shall not infringe the Construction Gauge specified in Clause 4 of the Employer's Requirements – Functional and as shown on the Employer’s Drawings See also Clause 5.3 above
Trang 146 RAILWAY ALIGNMENTS
6.1 Criteria
Appendix 1 to Volume 3, Employer’s Requirements
subject to the provisions of the Contract, minor changes to the given vertical alignments may
be made, where clear benefits can be demonstrated, and in order to suit the specific characteristics of his design
to 6.5
Cant Setting Procedure
6.2 Horizontal Alignment
of external restrains may necessitate limited encroachment of curves at station but this shall
be avoided whenever possible Where encroachment is unavoidable, notwithstanding the provisions of Clause 6.2.1 above, the curve radius along a platform shall not be less than 400 meters
straight track between the ends of the curves or of the transitions where these are required shall be not less than 20 meters
6.3 Cant and Speed
Equilibrium cant:
R
V C
2
3
11 ×
=
R = horizontal curve radius in meters
C = equilibrium cant in millimeters
Trang 15Section 6-2 of 3 October 2012
Flowchart of Cant Setting Procedure and Each Contractor’s Responsibility
Note: CP-1 means CP-1b (not included Ben Thanh Station)
Design of Horizontal Alignment (Fixed in the Drawings) CP-3 Design of Train Performance
CP-1 and CP-2 Design of Vertical Alignment (if minor and beneficial)
alignment prepared by CP-1 and CP-2)
Transition Curve Length, and Track Structure
CP-1 and CP-2 Design of Civil Structures with the cant value
prepared by CP-3 (including the review of Horizontal and Vertical
Alignment which may slightly vary according to the revised
transition curve length)
CP-3 Check whether the Run Curve is satisfied with Employer’s Requirement specified in Systems Operation Plan
Employer’s Requirement in Systems Operation
Plan (CP-3 Vol.3 Appendix 14)
- Travel time including dwell time between Ben
Thanh and Suoi Tien Terminal shall be 29
minutes and below
- Minimum headway shall be 2 minutes and 10
seconds
- Above requirements are for local train operation
which stops at every station
Trang 166.3.2 The allowable applied cant shall not be over 150 millimeters
consideration of the two run curves for both of the local train in the initial stage and the express train in the future
designing the actual cant and transition length so that any structure shall not come outside of ROW
incorporating the actual cant and transition length designed by the Contractor of Package 3
6.4 Transition Curves
adjoining straight, between the different radii of a compound curve and at the adjoining ends
of circular curves forming reverse curves
L R
π π
π
2 2 1
Trang 17where L = length of transition
In other words, above limits shall be described as the rolling speed of the car within the transition curve which shall be subjected to:
the acceleration of the over centrifugal force within the transition curve shall be not greater than 0.029 g/sec
between the two parts of the curve The length of such a transition shall be equal to the difference between the required transition lengths at each end of the curve
6.5 Vertical Alignment
transitions is avoided Where such coincidence is unavoidable the largest practicable vertical curve radius shall be employed
less than 10 ‰ the vertical curve may be omitted
curve radius subject to the following limit:
Trang 186.6 Gradients
the curve restriction The curve restriction shall be defined as follows:
6.7 Levels
Level Datum of Vietnam (Hon Dau Datum)
6.8 Points and Crossing Work
movement joint
point-and-crossing works or point-and-point-and-crossing work and horizontal transition
be reduced in the following manner;
beginning of next switch rail
7 meters
beginning of next switch rail which is placed in face
Trang 196.9 Distance between Track Centers
expanded by considering the throw of railcar Distance between track centers shall be changed within the horizontal transition according to the curve radius as listed below:
Trang 21DESIGN LOADINGS
12.1 General
The railway loading applied to structures on the Project shall generally be in accordance with
Design Standards for Railway Structures and Commentary (Concrete Structures);
DSRSC-CS except as detailed below
12.2 Nominal Loads
12.2.1 Static Loading: The nominal loading for the design of members shall comprise fully loaded
trains with individual cars each having four axles, the loads and axle spacing are shown in Fig
12.2.1 Coupled cars shall be applied to the structure so as to give the most adverse effect
on the element being considered Note that the loading due to Rolling Stock may be modified,
therefore the Contractor shall confirm the finalized Rolling Stock with CP-3 Contractor prior to
commencement of the Technical Design
16t 16t 16t 16t 16t 16t 16t 16t
2100 2100 2100 2100
to 2500 to 2500 to 2500 to 2500
13800 6200 13800 6200 13800
20000 20000 20000
Fig 12.2.1 Nominal Train Load 12.2.2 Fatigue Loading: The nominal loading for the design of members shall comprise fully loaded
trains with individual cars each having four axles, the loads and axle spacing are shown in Fig
12.2.1 The fatigue design shall be in accordance with Clause 7.3 of DSRSC-CS
12.2.3 Dynamic Loading: The static loading given in Clauses 12.2.1 above shall be multiplied by an
appropriate dynamic factor as detailed in Clause 4.4.4 of DSRSC-CS
12.2.4 Longitudinal Braking and Traction Loads: Longitudinal loads from braking and traction shall
be in accordance with Clause 4.4.7 of DSRSC-CS
Trang 2212.2.5 Long Rail Longitudinal Loads Longitudinal loads from Long Rail shall be in accordance with
Clause 4.4.10 of DSRSC-CS
12.2.6 Centrifugal load The centrifugal load shall be calculated in accordance with Clause 4.4.5 of
DSRSC-CS The following maximum speeds on curves shall be considered:
Trang 2313 Not Used
Trang 2415 SEISMIC LOADING
15.1 General
Design Standards for Railway Structures and Commentary (Seismic Design), 2008, RTRI presents basic concepts for Seismic design of underground structures, such as Cut and Cover Tunnels The behavior of underground structures like cut and cover tunnels subjected
to earthquake motion is strongly influenced by the behavior of the surrounding soil
The Seismic Deformation Method, which compute the dynamic behavior of surrounding soil and then applies statically the outcome displacement to the structure through the subgrade reaction, shall be used
15.2 Method of Seismic Analysis
The member damage level and stability level are taken as indices for evaluating the seismic performance of cut and cover tunnels The following shall be applied to the verification of the seismic performance of cut and cover tunnels
The Level 1 earthquake motion has a probability of occurring several times within the service period the structure in the vicinity of Ho Chi Minh City
The acceleration coefficient “A” shall be decided in accordance with TCXDVN 375:
2006
At this performance level, function of structure is retained without conducting repair after an earthquake and no excessive displacement occurs
Member damage level 1 should be satisfied for each of the structural members to ensure seismic performance I against Level-1 earthquakes
Set within the displacement of the longitudinal reinforcement yield point, this is a level
at which no damage occur and no repair is required after an earthquake
Though the stability level need not be verified in general, the stability (settlement or uplift) of the structure should be verified when ground liquefaction is expected to occur
On the other hand, verification of the Seismic Performance II is not required in Ho Chi Minh City because of the low level of earthquake motion
Trang 25be assessed in accordance with followings;
Differential settlement between adjacent line structures shall be evaluated and due allowance incorporated into the size of the structures and detailing of joints to ensure that the Construction Gauge is not infringed within the design life
The differential movements, including relative rotation, between structures calculated to take place after track laying has been carried out shall not exceed the requirements of the track design
Trang 2617 LIVE LOADS IN STATIONS
Circulation space within:-
Aux Services Transformers
equipment to be used
resulting from the method and route to be taken for the installation and subsequent
Trang 27removal and replacement of the various items of plant and equipment
Trang 28GENERAL REQUIREMENT FOR CIVIL AND ARCHITECTURAL
DESIGN
the full length of the railway structures in accordance with following principals
train operation is to drive the train to the platform of the next station
passenger shall be escaped from the end door of the rolling stock and walk on the track to the next station
by trespassers, vandals and road vehicles
Contractor is as follows:
“The track structure shall comprise non-ballasted track for underground/elevated sections and stations except the SUOI TIEN TERMINAL Station (ballasted track) Ballasted track is adopted on Depot Access Line, in SUOI TIEN TERMINAL Station area and in Depot area And a directly fixed to concrete/steel structures will be introduced in accordance with the final design selected for the Depot facilities The non-ballasted track structure for underground section shall be adopted between 0k-105 m to 2k200 m, the non-ballasted track structure for elevated section shall be adopted between 2k200 m to 18 k570 m, the main line ballasted track structure for SUOI TIEN TERMINAL Station shall be adopted between 18 k570 m to 19 k110 m , and the ballasted track structure for Depot Access Line shall be adopted between 19 k110 m to Depot.”
The Contractor shall coordinate with CP-3 Contractor and finalize the exact chainage stipulated above
Trang 2919 GEOTECHNICAL WORKS
embankments and earth retaining structures
geotechnical parameters of the sub-surface strata along the route for his design
Investigation Report prepared at Pre-Tender stage
capable of supporting vegetation and shall be stabilized where necessary In particular, soil slopes shall be hydro seeded or turfed
differential settlement of road surfaces around underground works
Trang 3020 UTILITIES
For handling of utility facilities within the ROW, please refer to Employer’s Requirements – Construction, Sub-Clause 7 : Handling of Utility Facilities
Trang 3121 ACCESS FOR INSPECTION AND MAINTENANCE
all elements of structures, facilities, and equipments
equipments for the inspection and maintenance
passenger, security measure i.e., door, fence, key and lock system shall be designed and provided
Trang 3222 ENVIRONMENTAL REQUIREMENTS
22.1 General
The Contractor shall note the requirements of Appendix 12 and 13 in Volume 3 the Employer’s Requirements in respect of the Environmental Protection Requirements to be applied to the Works The outline of environmental requirements for the Design Phase is described as below
22.2 Air
The design of the Permanent and Temporary Works shall be such that minimize the dust or gas emission which cause the air pollution due to construction and operation of the railway, and shall comply in full with the following requirements:
emissions in the Design Phase including the location of facility or equipment which become emission sources
depot with consideration of transportation routes and flow to prevent concentration or
to minimize the exhausted gas from vehicles
22.3 Noise and Vibration
The design of the Permanent and Temporary Works shall be such that minimize the noise and vibration emission due to construction and operation of the railway, and shall comply in full with the following requirements:
the radiation of noise due to vibration caused by the passage of trains Particular attention shall be paid to the minimization of noise at the low end of the acoustic frequency spectrum
and designed to satisfy TCVN 5949-1998 or be below the environmental baseline data (defined as the data during no operation of tunnel and station ventilation system)
at open cut transition structure
“With a 3 car train moving on level, tangent, at –grade, unti-vibration sleeper concrete bed track with clean, smooth rails at all speeds from 0 to 110 km/hr, and whilst accelerating or braking, with all vehicle systems operating simultaneously under normal conditions, the noise level measured on either side, at 25 m from track centerline at a height of 1200 mm above ground level shall not exceed 70 dBA.”
Trang 3322.4 Water
The design of the Permanent Works shall include wastewater treatment to discharge the wastewater into existing water courses or sewerage systems due to operation of the railway, and shall comply in full with the following requirements:
Standard (TCVN 5945-2005, Level ‘A’)
system or design the collection system to existing sewerage system
wastewater arising from site office, canteen or toilet facilities constructed by the Contractor into sewers after obtaining prior approval of agency controlling the system
A wastewater drainage system shall be provided to drain wastewater into the sewerage system
The Contractor shall take measures to prevent discharge of oil and grease during spillage from reaching drainage system
22.5 Land Subsidence and Ground Movement
The Contractor shall design and construct all structures and facilities including temporary structures, such that minimize the land subsidence and ground movement, and shall comply
in full with the following requirement:
structures in accordance with Clause 28 of these Outline Design Specifications
22.6 Waste
The design of the Permanent Works shall include waste storage, collection and handling in the stations to handover to the existing waste treatment and disposal system
Trang 3423 AESTHETIC REQUIREMENTS
station shall be appropriate for a modern mass transit facility As a major and highly visible public facility, the impression it may make to the public and on the environment along its routes will influence the design
methods Architectural and interior treatments shall reflect the overall make-up of the station and assist passengers in finding their way through the facility
international modern design This includes the stations elevated and underground, the pedestrian bridges and the entrances from the sidewalks
Trang 3524 Not Used
Trang 3625 SECURITY REQUIREMENTS
provided to against the unauthorized access to the various parts of the Permanent and Temporary Works
System by CP-3 Contractor The Contractor shall co-ordinate and co-operate with the CP-3 Contractor so that the design and installation of key system are compatible
Trang 3726 DURABILITY AND MAINTENANCE
materials, that the structure shall remain in a serviceable condition over its life, with due regard to its location and the environmental and climatic conditions prevailing In particular, only materials and details having a proven record of durability in similar conditions shall be used
facilities, and equipments in accordance with Clause 21 of this Outline Design Specifications
suitable materials which will reduce weathering and staining as far as possible Structures shall be detailed so as to shed surface water in such a way that ponding and streaking do not occur and details which encourage the accumulation of debris shall be avoided Details shall
be designed for ease of maintenance
engineering structures and building structures including any surfacing and protective paint systems for steelwork together with any mechanical and electrical equipment installed The Manual shall detail all requirements for the inspection and maintenance of these structures compatible with their required life
Requirement-Functional
Trang 3827 REINSTATEMENT OF ROADS
same standard and same form as the existing road, to the satisfaction of the Authorities responsible for the road
Trang 39GROUND MOVEMENTS AND BUILDING PROTECTION
28.1 Ground Movement Analysis Report
28.1.1 The Contractor shall prepare a “Ground Movement Analysis Report” to document the
assessment of expected ground movement and the response of the adjacent structures by the execution of his Works along the route The report shall be submitted to the Employer’s Representative for consent within 60 days after the Commencement Date and include the followings but not be limited;
the Works
foundations
showing predicted settlement contours and the expected response of adjacent structures
These allowable values shall be in accordance with these Outline Design Specifications and shall be need to be agreed by the Employer’s Representative In addition to these allowable values, lower “action level” values, which define when contingency actions are to be taken, shall be agreed
installation, calibration and running of the instrumentation system
Table 28.1 Recommended allowable value
Trang 4028.2 Utilities Subsidence Report
28.2.1 The Contractor shall prepare a “Utilities Subsidence Report” to document the response of the
adjacent utilities by the execution of his Works along the route The report shall be submitted
to the Employer’s Representative for consent within 60 days after the Commencement Date and the coverage shall be similar to that for structures in the “Ground Movement Analysis Report” In addition the Contractor shall include the followings;
by the Works The Contractor shall establish, based on the advice of the relevant Utility Agencies, allowable limits for settlement, horizontal movement and distortion for each utility
be caused by the Works
protecting utilities
shall be deemed as critical because of potential interruption These utilities shall be identified in the Report
28.3 Preventive and Corrective Measures
28.3.1 All preventive measures to minimize ground movement shall be designed and carried out by
the Contractor The Contractor shall also propose contingency plans and implement these when the measured ground movements exceed the agreed level or indicate that final long term ground movement will exceed the allowable values established in the Ground Movement Analysis Report
28.3.2 When the Contractor proposes the ground treatment as a preventive measures to ground
movement the method of treatment shall be submitted to the Employer’s Representative for consent The ground treatment works shall conform to Clause 158 and 159 of Standard Specification for Cut and Cover Tunneling – 2006: JSCE
28.4 Monitoring
28.4.1 General