Knowledge of cost behavior allows a man-ager to assess changes in costs that result from changes in activity.. Resource spending is the cost of acquiring the capacity to perform an ac
Trang 1CHAPTER 3 ACTIVITY COST BEHAVIOR QUESTIONS FOR WRITING AND DISCUSSION
1 Knowledge of cost behavior allows a
man-ager to assess changes in costs that result
from changes in activity This allows a
man-ager to assess the effects of choices that
change activity For example, if excess
ca-pacity exists, bids that at least cover variable
costs may be totally appropriate Knowing
what costs are variable and what costs are
fixed can help a manager make better bids
2 The longer the time period, the more likely
that a cost will be variable The short run is a
period of time for which at least one cost is
fixed In the long run, all costs are variable
3 Resource spending is the cost of acquiring
the capacity to perform an activity, whereas
resource usage is the amount of activity
ac-tually used It is possible to use less of the
activity than what is supplied Only the cost
of the activity actually used should be
as-signed to products
4 Flexible resources are those acquired from
outside sources and do not involve any
long-term commitment for any given amount of
resource Thus, the cost of these resources
increases as the demand for them
increas-es, and they are variable costs (varying in
proportion to the associated activity driver)
5 Committed resources are acquired by the
use of either explicit or implicit contracts to
obtain a given quantity of resources,
regard-less of whether the quantity of resource
available is fully used or not For multiperiod
commitments, the cost of these resources
essentially corresponds to committed fixed
costs Other resources acquired in advance
are short term in nature and essentially
cor-respond to discretionary fixed costs
6 Committed fixed costs are those incurred for
the acquisition of long-term activity capacity
and are not subject to change in the short
run Annual resource expenditure is
inde-pendent of actual usage For example, the
cost of a factory building is a committed
fixed cost Discretionary fixed costs are
those incurred for the acquisition of
short-term activity capacity, the levels of which
can be altered quickly In the short run,
re-source expenditure is also independent of actual activity usage An engineer’s salary is
an example of such an expenditure
7 A variable cost increases in direct proportion
to changes in activity usage A one-unit crease in activity usage produces an in- crease in cost A step cost, however, in- creases only as activity usage changes in small blocks or chunks An increase in cost requires an increase in several units of activ- ity When a step cost changes over relatively narrow ranges of activity, it may be more convenient to treat it as a variable cost
in-8 A step cost with narrow steps can be treated
as variable, while one with wide steps is ically treated as fixed
typ-9 An activity rate is the resource expenditure
for an activity divided by the activity’s tical capacity
prac-10 Mixed costs are usually reported in total in
the accounting records How much of the cost is fixed and how much is variable is un- known and must be estimated
11 A scattergraph allows a visual portrayal of
the relationship between cost and activity It reveals to the investigator whether a rela- tionship may exist and, if so, whether a li- near function can be used to approximate the relationship A scattergraph also can as- sist in identifying any outliers
12 Managers can use their knowledge of cost
relationships to estimate fixed and variable components A scattergraph can be used as
an aid in this process From a scattergraph,
a manager can select two points that best represent the relationship These two points can then be used to derive a linear cost for- mula The high-low method tells the manag-
er which two points to select to compute the linear cost formula The selection of these two points is not left to judgment
13 Because the scatterplot method is not
re-stricted to the high and low points, it is ible to select two points that better represent the relationship between activity and costs,
Trang 2poss-producing a better estimate of fixed and
va-riable costs A scattergraph also identifies
outliers that could represent a high or low
point that is an aberration The main
advan-tage of the high-low method is that it
re-moves subjectivity from the choice process
The same line will be produced by two
dif-ferent people
14 Assuming that the scattergraph reveals that
a linear cost function is suitable, then the
method of least squares selects a line that
best fits the data points The method also
provides a measure of goodness of fit so
that the strength of the relationship between
cost and activity can be assessed
15 The best-fitting line is the one that is
“clos-est” to the data points This is usually
meas-ured by the line that has the smallest sum of
squared deviations
16 No The best-fitting line may not explain
much of the total cost variability There must
be a strong relationship as well
17 The coefficient of determination is the
per-centage of total variability in costs explained
by the activity As such, it is a measure of the goodness of fit, the strength of the rela- tionship between cost and activity
18 The correlation coefficient is the square root
of the coefficient of determination The relation coefficient reveals the direction of the relationship in addition to the strength of the relationship
cor-19 If the variation in cost is not well explained
by activity usage (the coefficient of nation is low) as measured by a single driv-
determi-er, then other explanatory variables may be needed to build a good cost formula
20 If the mixed costs are immaterial, then the
method of decomposition is unimportant Furthermore, sometimes managerial judg- ment may be more useful for assigning costs than the use of formal statistical me- thodology
Trang 3EXERCISES 3–1
Trang 4Raw materials cost: Variable cost
Trang 52 Forming machines rental cost is a step cost
Trang 63 Direct labor cost increase = $144,000 – $108,000 = $36,000
Supervision increase = $80,000 – $40,000 = $40,000
3-6
Trang 7the particular action figure being produced; it is a step cost for the production
of action figures in general Other facility costs are strictly fixed
3–9
1 Total maintenance cost = $24,000 + $0.30(200,000) = $84,000
2 Total fixed maintenance cost = $24,000
3 Total variable maintenance cost = $0.30(200,000) = $60,000
4 Total maintenance cost per unit = [$24,000 + $0.30(200,000)]/200,000
= $84,000/200,000
= $0.42
5 Fixed maintenance cost per unit = $24,000/200,000 = $0.12
6 Variable maintenance cost per unit = $0.30
7 Requirements1-6 repeated:
1 Total maintenance cost = $24,000 + $0.30(100,000) = $54,000
2 Total fixed maintenance cost = $24,000
3 Total variable maintenance cost = $0.30(100,000) = $30,000
4 Total maintenance cost per unit = [$24,000 + $0.30(100,000)]/100,000
= $54,000/100,000
= $0.54
5 Fixed maintenance cost per unit = $24,000/100,000 = $0.24
6 Variable maintenance cost per unit = $0.30
Trang 83–10
1 Committed resources: trucks and technicians’ salaries
Flexible resources: supplies, small tools, and fuel
2 Variable activity rate = $420,000/35,000 = $12 per call
Fixed activity rate = $600,000*/40,000** = $15 per call
Total cost of one call = $12 + $15 = $27 per call
**8 × 250 × 20
committed resources = activity used + unused capacity
Note: The analysis is restricted to committed resources, since only these
re-sources will ever have any unused capacity
Trang 9Plan 1 is more cost effective Jana will have some unused capacity (on age, 15 minutes a month), and the overall cost will be lower by $10 per month
*There are a number of ways to illustrate the use of minutes with Plan 1 Here are two possibilities The problem, of course, is that all included monthly minutes are used, and Jana must purchase additional minutes
Plan 2 is now more cost effective, as the monthly cost is $30 Under Plan 1,
additional charge includes the airtime and regional roaming charge.)
Trang 11This is a mixed cost
4 Total cost = $80,000 + $500(Number of opening shows)
Using the high point:
Fixed cost = $2,790 – $0.43(3,100) = $1,457
OR
Using the low point:
Fixed cost = $1,758 – $0.43(700) = $1,457
3 Total tanning service cost = $1,457 + $0.43 × Number of appointments
4 Total predicted cost for September = $1,457 + $0.43(2,500) = $2,532
Trang 12Total fixed cost for September = $1,457
Total predicted variable cost = $0.43(2,500) = $1,075
num-2 Total cost of tanning services = $1,290 + $0.45 × Number of appointments
3 Total predicted cost for September = $1,290 + $0.45(2,500) = $2,415
Trang 13Cost = $2,350 + $4 (oil changes)
Predicted cost for January = $2,350 + $4(1,000) = $6,350
Trang 14Rounding the coefficients:
This says that 97 percent of the variability in the cost of providing oil changes
is explained by the number of oil changes performed
4 The least-squares method is better because it uses all eight data points
in-stead of just two
Trang 16Rounding the coefficients:
This says that 93 percent of the variability in the cost of moving materials is
explained by the number of moves
4 Normally, we would prefer the least-squares method since the data appear to
be linear However, the third observation may be an outlier If the third
The new cost formula would be
Cost = $1,411 + $17.28 (moves)
The higher fixed cost is much more in keeping with what we observed with
the scatterplot in requirement 1
Trang 173–17
1 Maintenance cost = $5,750 + $16X
2 Maintenance cost = $5,750 + $16(650) = $5,750 + $10,400 = $16,150
percent The relationship appears strong but perhaps could be improved by searching for another explanatory variable Leaving about 20 percent of the variability unexplained may produce less than satisfactory predictions
4 Maintenance cost = 12($5,750) + $16(8,400) = $69,000 + $134,400 = $203,400
Note: The fixed cost from the regression results is the fixed cost for the
month (since monthly data were used to estimate the equation) However, the question asks for the cost for the year Therefore, the fixed cost from the re- gression equation must be multiplied by 12
Trang 18de-3–19
1 Warranty repair cost = $2,000 + $60(number of defects) - $10(inspection
hours)
2 Warranty repair cost = $2,000 + $60(100) – $10(150) = $6,500
3 The number of defects is positively correlated with warranty repair costs spection hours are negatively correlated with warranty repair costs
In-4 In this equation, the independent variables—number of defects and tion hours—account for 88 percent of the variability in warranty repair costs
inspec-It seems that analysts have identified some very good drivers for warranty pair costs
Trang 19
PROBLEMS 3-20
a Variable cost
b Committed fixed cost
c Discretionary fixed cost
d Discretionary fixed cost
e Discretionary fixed cost
f Variable cost
g Variable cost
h Discretionary fixed cost
i Discretionary fixed cost
j Committed fixed cost
Yes, the relationship appears to be reasonably linear
2 Using the high-low method:
Variable receiving cost = ($27,000 – $15,000)/(1,700 – 700) = $12
Fixed receiving cost = $15,000 – $12(700) = $6,600
Predicted cost for 1,475 receiving orders:
Receiving cost = $6,600 + $12(1,475) = $24,300
3 Receiving cost for the quarter = 3($6,600) + $12(4,650)
Trang 21be dropped Then, data from the 11 remaining months could be used to develop a cost formula for receiving cost
Trang 223 Results for the method of least squares after dropping month 11
Coeffi-Standard Error t Stat P-value Lower 95%
Upper 95%
Lower 95.0%
Upper 95.0%
Intercept 3168.56 2565.262 1.23518 0.248035 -2634.47 8971.589 -2634.47 8971.589
X Variable 1 15.17946 2.051314 7.399872 4.1E-05 10.53906 19.81986 10.53906 19.81986
Receiving cost = $3,168.56 + $15.18 × Number of receiving orders
Predicted receiving cost for a month
= $3,168.56 + $15.18(1,475) = $25,559.06
The regression run on the 11 months of data from “typical” months appears to be
outlier (85.88 percent versus 74.512 percent), and the scattergraph gives Joseph confidence that the data without the outlier describe a relatively linear relation- ship Since the storm damage is not expected to recur, month 11 can safely be dropped from a regression meant to help predict future receiving cost
Trang 233–23
1 Salaries:
Internet and software subscriptions—mixed
Consulting by senior partner—variable
Trang 24Thus, total clinic cost = $9,025 + $22.60/professional hour
For 140 professional hours:
Clinic cost = $9,025 + $22.60(140) = $12,189
Charge per hour = $12,189/140 = $87.06
Fixed charge per hour = $9,025/140 = $64.46
Variable charge per hour = $22.60
Charge/day = $9,025/170 + $22.60 = $53.09 + $22.60 = $75.69
The charge drops because the fixed costs are spread over more professional hours
Trang 25Setups explain about 63.4 percent of the variability in order filling cost,
pro-viding evidence that Brett’s choice of a cost driver is reasonable However,
other drivers may need to be considered because 63.4 percent may not be
strong enough to justify the use of only receiving orders
Trang 26Setup hours explain about 82.5 percent of the variability in order filling cost
This is a better result than that of setups and should convince Brett to try
multiple regression
Trang 273–24 Concluded
4 Regression routine with pounds of material and number of receiving orders
as the independent variables:
F = $752 (rounded)
Y = $752 + $3.34a + $7.147b
R 2 = 0.95, or 95%
Multiple regression with both variables explains 95 percent of the variability
in receiving cost This is the best result
3–25
1 The order should cover the variable costs described in the cost formulas
These variable costs represent flexible resources
Garner should accept the order because it would cover total variable costs
and increase income by $15 per unit ($212 – $197), for a total increase of
$300,000
Trang 28er than direct labor hours that are affecting variability in overhead cost What these drivers are and how resource spending would change need to be known before a sound decision can be made
3 Resource spending attributable to order:
The order would not be accepted now because it does not cover the variable activity costs Each unit would lose $2 ($212 – $214)
It would also be useful to know the step-cost functions for any activities that have resources acquired in advance of usage on a short-term basis It is possible that there may not be enough unused activity capacity to handle the special order, and resource spending may also be affected by a need (which,
in this case, would be unexpected) to expand activity capacity
Trang 293–26
1 High (2,000; $120,000); Low (1,200; $52,000)
V = ($120,000 – $52,000)/(2,000 – 1,200) = $85/nursing hour
This problem illustrates how the high-low method can be misleading when
cost behavior patterns have changed Fortunately, in this case, the negative
value of fixed cost tells us that something is wrong
2 a Output of spreadsheet multiple regression routine: