17.1 Adjusted Present Value Approach17.2 Flows to Equity Approach 17.3 Weighted Average Cost of Capital Method 17.4 A Comparison of the APV, FTE, and WACC Approaches 17.5 Capital Budgeti
Trang 117
Capital Budgeting for
the Levered Firm
Trang 2Recall that there are three questions in corporate
finance.
The first regards what long-term investments the firm
should make (the capital budgeting question).
The second regards the use of debt (the capital structure question).
This chapter considers the nexus of these questions.
Recall that there are three questions in corporate
finance.
The first regards what long-term investments the firm
should make (the capital budgeting question).
The second regards the use of debt (the capital structure question).
This chapter considers the nexus of these questions.
Trang 317.1 Adjusted Present Value Approach
17.2 Flows to Equity Approach
17.3 Weighted Average Cost of Capital Method
17.4 A Comparison of the APV, FTE, and WACC Approaches
17.5 Capital Budgeting When the Discount Rate Must Be Estimated 17.6 APV Example
17.7 Beta and Leverage
17.8 Summary and Conclusions
17.1 Adjusted Present Value Approach
17.2 Flows to Equity Approach
17.3 Weighted Average Cost of Capital Method
17.4 A Comparison of the APV, FTE, and WACC Approaches
17.5 Capital Budgeting When the Discount Rate Must Be Estimated 17.6 APV Example
17.7 Beta and Leverage
17.8 Summary and Conclusions
Trang 4APV = NPV + NPVF
The value of a project to the firm can be thought
of as the value of the project to an unlevered firm
(NPV) plus the present value of the financing side effects (NPVF):
There are four side effects of financing :
The Tax Subsidy to Debt The Costs of Issuing New Securities The Costs of Financial Distress
Subsidies to Debt Financing
APV = NPV + NPVF
The value of a project to the firm can be thought
of as the value of the project to an unlevered firm
(NPV) plus the present value of the financing side effects (NPVF):
There are four side effects of financing :
The Tax Subsidy to Debt The Costs of Issuing New Securities The Costs of Financial Distress
Subsidies to Debt Financing
Trang 50 1 2 3 4
–$1,000 $125 $250 $375 $500
50 56
$
) 10 1 (
500
$ )
10 1 (
375
$ )
10 1 (
250
$ )
10 1 (
125
$ 000
, 1
$
% 10
4 3
2
% 10
The unlevered cost of equity is r 0 = 10%:
The project would be rejected by an all-equity firm: NPV < 0.
Consider a project of the Pearson Company, the timing and size of the incremental after-tax cash flows for an all-equity firm are:
Trang 6The project would be
10
CF4 CF3
Trang 7Now, imagine that the firm finances the project with
$600 of debt at r B = 8%
Pearson’s tax rate is 40%, so they have an interest tax
shield worth T C Br B = 40×$600×.08 = $19.20 each year.
Now, imagine that the firm finances the project with
$600 of debt at r B = 8%
Pearson’s tax rate is 40%, so they have an interest tax
shield worth T C Br B = 40×$600×.08 = $19.20 each year.
The net present value of the project under leverage is:
APV = NPV + NPV debt tax shield
$ 50
56
$
APV
09 7
$ 59
63 50
56
Trang 8Note that there are two ways to calculate the NPV of the loan Previously, we calculated the PV of the interest tax shields Now, let’s calculate the actual NPV of the loan:
Note that there are two ways to calculate the NPV of the loan Previously, we calculated the PV of the interest tax shields Now, let’s calculate the actual NPV of the loan:
09 7
$ 59
63 50
56
$
) 08 1 (
600
$ )
08 1 (
) 4 1 ( 08 600
$ 600
APV = NPV + NPVF
Trang 9NPV of the loan:
NPV of the loan:
CF2 CF1
F2 F1
CF0
3 –$28.80 =
8
PV of the interest tax shields.
CF1 F1
8
$19.20 = 40×$600×.08
$600×.08×(1–.40)
Trang 1017.2 Flows to Equity Approach
Discount the cash flow from the project to the
equity holders of the levered firm at the cost of
levered equity capital, r S
There are three steps in the FTE Approach:
Step One: Calculate the levered cash flows
Step Two: Calculate r S
Step Three: Valuation of the levered cash flows at r S
Discount the cash flow from the project to the
equity holders of the levered firm at the cost of
levered equity capital, r S
There are three steps in the FTE Approach:
Step One: Calculate the levered cash flows
Step Two: Calculate r S
Step Three: Valuation of the levered cash flows at r S
Trang 11Since the firm is using $600 of debt, the equity holders only have
to come up with $400 of the initial $1,000.
Thus, CF 0 = –$400
Each period, the equity holders must pay interest expense The
after-tax cost of the interest is B×r B ×(1 – T C ) = $600×.08×(1 – 40)
= $28.80
Since the firm is using $600 of debt, the equity holders only have
to come up with $400 of the initial $1,000.
Thus, CF 0 = –$400
Each period, the equity holders must pay interest expense The
after-tax cost of the interest is B×r B ×(1 – T C ) = $600×.08×(1 – 40)
Trang 12) )(
4 3
20
19 )
10 1 (
500
$ )
10 1 (
375
$ )
10 1 (
250
$ )
10 1 (
08 10 )(.
40 1
( 09 407
$
600
$ 10
B V
To calculate the debt to equity ratio, , start with
Trang 13Step Three: Valuation for Pearson
Discount the cash flows to equity holders at r S = 11.77%
Discount the cash flows to equity holders at r S = 11.77%
56 28
$
) 1177
1 (
80 128
$ )
1177
1 (
20 346
$ )
1177
1 (
20 221
$ )
1177
1 (
20 96
$ 400
Trang 14Step Three: Valuation for Pearson
CF2 CF1
Trang 1517.3 WACC Method for Pearson
To find the value of the project, discount the unlevered cash flows at the weighted average cost of capital.
Suppose Pearson’s target debt to equity ratio is 1.50
To find the value of the project, discount the unlevered cash flows at the weighted average cost of capital.
Suppose Pearson’s target debt to equity ratio is 1.50
) 1
B S
B S
B r
B S
) 40 1 (
%) 8 ( ) 60 0 (
%) 77 11 ( ) 40 0
S
B
50
60
0 5
2
5
1 5
1
5
S
S S
Trang 16Valuation for Pearson using WACC
To find the value of the project, discount the
unlevered cash flows at the weighted average cost
of capital
To find the value of the project, discount the
unlevered cash flows at the weighted average cost
of capital
4 3
500
$ )
0758
1 (
375
$ )
0758
1 (
250
$ )
0758
1 (
125
$ 000
, 1
Trang 17Valuation for Pearson using WACC
CF2 CF1
Trang 18and WACC Approaches
All three approaches attempt the same
task:valuation in the presence of debt financing.
Guidelines:
Use WACC or FTE if the firm’s target debt-to-value
ratio applies to the project over the life of the project.
Use the APV if the project’s level of debt is known
over the life of the project.
In the real world, the WACC is the most widely
used by far.
All three approaches attempt the same
task:valuation in the presence of debt financing.
Guidelines:
Use WACC or FTE if the firm’s target debt-to-value
ratio applies to the project over the life of the project.
Use the APV if the project’s level of debt is known
over the life of the project.
In the real world, the WACC is the most widely
used by far.
Trang 19Summary: APV, FTE, and WACC
Initial Investment All All Equity Portion
Discount Rates r 0 r WACC r S
PV of financing effects Yes No No
Which approach is best?
Use APV when the level of debt is constant
Use WACC and FTE when the debt ratio is constant
WACC is by far the most common FTE is a reasonable choice for a highly levered firm
Initial Investment All All Equity Portion
Discount Rates r 0 r WACC r S
PV of financing effects Yes No No
Which approach is best?
Use APV when the level of debt is constant
Use WACC and FTE when the debt ratio is constant
WACC is by far the most common FTE is a reasonable choice for a highly levered firm
Trang 20Discount Rate Must Be Estimated
A scale-enhancing project is one where the project is
similar to those of the existing firm.
In the real world, executives would make the
assumption that the business risk of the
non-scale-enhancing project would be about equal to the business risk of firms already in the business.
No exact formula exists for this Some executives might select a discount rate slightly higher on the assumption that the new project is somewhat riskier since it is a new entrant.
A scale-enhancing project is one where the project is
similar to those of the existing firm.
In the real world, executives would make the
assumption that the business risk of the
non-scale-enhancing project would be about equal to the business risk of firms already in the business.
No exact formula exists for this Some executives might select a discount rate slightly higher on the assumption that the new project is somewhat riskier since it is a new entrant.
Trang 2117.6 APV Example:
Worldwide Trousers, Inc is considering replacing a $5
million piece of equipment The initial expense will be depreciated straight-line to zero salvage value over 5 years; the pretax salvage value in year 5 will be
$500,000 The project will generate pretax savings of
$1,500,000 per year, and not change the risk level of the firm The firm can obtain a 5-year $3,000,000 loan
at 12.5% to partially finance the project If the project were financed with all equity, the cost of capital would
be 18% The corporate tax rate is 34%, and the risk-free rate is 4% The project will require a $100,000
investment in net working capital. Calculate the APV.
Worldwide Trousers, Inc is considering replacing a $5
million piece of equipment The initial expense will be depreciated straight-line to zero salvage value over 5 years; the pretax salvage value in year 5 will be
$500,000 The project will generate pretax savings of
$1,500,000 per year, and not change the risk level of the firm The firm can obtain a 5-year $3,000,000 loan
at 12.5% to partially finance the project If the project were financed with all equity, the cost of capital would
be 18% The corporate tax rate is 34%, and the risk-free rate is 4% The project will require a $100,000
investment in net working capital. Calculate the APV.
Trang 2217.6 APV Example: Cost
25 561 ,
873 ,
4
$
) 1
(
) 34 1 ( 000 ,
500 )
1 (
000 ,
100 1
5
0 5
m
Cost
f
The cost of the project is not $5,000,000.
We must include the round trip in and out of net working capital and the after-tax salvage value
Let’s work our way through the four terms in this equation:
NWC is riskless, so we discount it at r f Salvage value should
have the same risk as the rest of the firm’s assets, so we use r 0
Trang 2317.6 APV Example: PV unlevered project
is the present value of the unlevered cash flows discounted at the unlevered cost of capital, 18%.
Turning our attention to the second term,
899 ,
095 ,
3
$
) 18 1 (
) 34 1 ( 5
1
$ )
1 (
5 1
t
project unlevered
PV
m r
UCF PV
Trang 24depreciation tax shield
is the is the present value of the tax savings due to
depreciation discounted at the risk free rate: r f = 4%
Turning our attention to the third term,
619 ,
513 ,
1
$ )
04 1 (
34 1
$
) 1
(
5 1
5 1
T D
Trang 2517.6 APV Example: PV interest tax shield
is the present value of the tax savings due to interest
expense discounted at the firm’s debt rate: r D = 12.5%
Turning our attention to the last term,
46 972 ,
453 )
125
1 (
500 ,
127
) 125
1 (
3
$ 125
0 34
0 )
1 (
3
$
5
1 shield
tax interest
5 1
5
1 shield
tax interest
PV
m r
m r
T PV
Trang 26Since the project has a positive APV, it looks like a go.
Let’s add the four terms in this equation:
Trang 2717.7 Beta and Leverage
Recall that an asset beta would be of the form:
2 Market
Asset
σ
) ,
(
Trang 2817.7 Beta and Leverage: No Corp.Taxes
In a world without corporate taxes, and with riskless corporate
debt, ( Debt = 0 ) it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
In a world without corporate taxes, and with riskless corporate
debt, ( Debt = 0 ) it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
In a world without corporate taxes, and with risky corporate
debt, it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
EquityDebt
Asset
Equity β
Asset Debt
Trang 2917.7 Beta and Leverage: with Corp Taxes
In a world with corporate taxes, and riskless debt,
it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
In a world with corporate taxes, and riskless debt,
it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
firmUnlevered
Equity
Debt 1
levered firm, it follows that Equity > Unlevered firm
Trang 30with Corp Taxes
If the beta of the debt is non-zero, then:
Trang 3117.8 Summary and Conclusions
1 The APV formula can be written as:
2 The FTE formula can be written as:
3 The WACC formula can be written as
1 The APV formula can be written as:
2 The FTE formula can be written as:
3 The WACC formula can be written as
investment
Initial debt
of effects
Additional )
1 (
Initial )
1 (
investment
Initial )
1 (
r UCF NPV
Trang 3217.8 Summary and Conclusions
4 Use the WACC or FTE if the firm's target debt to
value ratio applies to the project over its life.
WACC is the most commonly used by far.
FTE has appeal for a firm deeply in debt.
5 The APV method is used if the level of debt is
known over the project’s life.
The APV method is frequently used for special
situations like interest subsidies, LBOs, and leases.
6 The beta of the equity of the firm is positively
related to the leverage of the firm.
4 Use the WACC or FTE if the firm's target debt to
value ratio applies to the project over its life.
WACC is the most commonly used by far.
FTE has appeal for a firm deeply in debt.
5 The APV method is used if the level of debt is
known over the project’s life.
The APV method is frequently used for special
situations like interest subsidies, LBOs, and leases.
6 The beta of the equity of the firm is positively
related to the leverage of the firm.
Trang 33Example: Hamilos Worldwide
Hamilos Worldwide is considering a $5 million expansion of their existing business The initial expense will be
depreciated straight-line over 5 years to zero salvage value; the pretax salvage value in year 5 will be $500,000 The
project will generate pretax gross earnings of $1,500,000 per year, and not change the risk level of the firm Hamilos can obtain a 5-year 12.5% loan to partially finance the project Flotation costs are 1% of the proceeds If undertaken, this project should maintain a target D/E ratio of 1.50 If the project were financed with all equity, the cost of capital would be 18% The corporate tax rate is 30%, and the risk- free rate is 6% The project will require a $100,000
investment in net working capital.
Hamilos Worldwide is considering a $5 million expansion of their existing business The initial expense will be
depreciated straight-line over 5 years to zero salvage value; the pretax salvage value in year 5 will be $500,000 The
project will generate pretax gross earnings of $1,500,000 per year, and not change the risk level of the firm Hamilos can obtain a 5-year 12.5% loan to partially finance the project Flotation costs are 1% of the proceeds If undertaken, this
project should maintain a target D/E ratio of 1.50 If the
project were financed with all equity, the cost of capital
would be 18% The corporate tax rate is 30%, and the free rate is 6% The project will require a $100,000
risk-investment in net working capital.