1. Trang chủ
  2. » Giáo án - Bài giảng

Introduction to management science 10e by bernard taylor chapter 08

82 247 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 82
Dung lượng 9,27 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

■ Project Crashing and Time-Cost Trade-Off■ Formulating the CPM/PERT Network as a Linear Programming Model Chapter Topics Copyright © 2010 Pearson Education, Inc.. Elements of Project M

Trang 2

■ Project Crashing and Time-Cost Trade-Off

■ Formulating the CPM/PERT Network as a

Linear Programming Model

Chapter Topics

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 3

■ Network representation is useful for project

analysis

■ Networks show how project activities are

organized and are used to determine time duration

of projects

■ Network techniques used are:

▪ CPM (Critical Path Method)

▪ PERT (Project Evaluation and Review

Trang 4

Elements of Project

Management

■ Management is generally perceived as concerned

with planning, organizing, and control of an

ongoing process or activity

■ Project Management is concerned with control of

an activity for a relatively short period of time after which management effort ends

■ Primary elements of Project Management to be

Trang 5

■ Risk and Problem Analysis

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 6

■ Project team typically consists of a group of

individuals from various areas in an organization and often includes outside consultants

■ Members of engineering staff often assigned to

project work

■ Project team may include workers.

■ Most important member of project team is the

project manager.

■ Project manager is often under great pressure

because of uncertainty inherent in project activities and possibility of failure Potential rewards,

however, can be substantial

■ Project manager must be able to coordinate various

skills of team members into a single focused effort

Elements of Project Management

The Project Team

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 7

Figure 8.1 The project management process

The Project Management Process

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 8

■ Justification describing the factors giving rise to

need for project

Expected results and what constitutes success.

■ List of necessary documents and planning reports

Statement of work (SOW) - a planning

document for individuals, team members, groups, departments, subcontractors and suppliers,

describing what are required for successful completion on time

Copyright © 2010 Pearson Education, Inc Publishing as Prentice Hall

Trang 9

Elements of Project Management

Work Breakdown Structure (WBS)

(1 of 2)

(modules).

Modules are further broken down into activities and,

finally, into individual tasks.

■ Identifies activities, tasks, resource requirements and

relationships between modules and activities.

■ Helps avoid duplication of effort.

■ Basis for project development, management ,

schedule, resources and modifications.

■ Approaches for WBS development:

1 Top down process 2 Brainstorm entire project

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 10

Figure 8.2 WBS for Computer Order-processing System Project

Elements of Project Management Work Breakdown Structure (2 of 2)

Copyright © 2010 Pearson Education, Inc Publishing as Prentice Hall

Trang 11

Elements of Project Management

Responsibility Assignment Matrix

(1 of 2)

■ Project manager assigns work elements to

organizational units, departments, groups,

individuals or subcontractors

■ Uses an organizational breakdown structure

(OBS)

■ OBS is a table or a chart showing which

organizational units are responsible for work

items

■ OBS leads to the responsibility assignment matrix

(RAM)

■ RAM shows who is responsible for doing the

necessary work in the project

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 12

Elements of Project Management

Responsibility Assignment Matrix

Trang 13

Elements of Project

Management

Project Scheduling

■ Project Schedule evolves from planning documents,

with focus on timely completion

■ Critical element in project management – source of most conflicts and problems

■ Schedule development steps:

1 Define activities, 2 Sequence activities,

3 Estimate activity times, 4 Construct schedule

Gantt chart and CPM/PERT techniques can be

Trang 14

Elements of Project Management

Gantt Chart (1 of 2)

■ Popular, traditional technique, also known as a bar

chart -developed by Henry Gantt (1914)

■ Direct precursor of CPM/PERT for monitoring work

progress

■ A visual display of project schedule showing

activity start and finish times and where extra time is available

■ Suitable for projects with few activities and

Trang 15

Elements of Project Management

Gantt Chart (2 of 2)

Figure 8.4 A Gantt chart

Copyright © 2010 Pearson Education, Inc Publishing as Prentice Hall

Trang 16

■ Monitoring project to minimize deviations from project

plan and schedule

■ Corrective actions necessary if deviations occur.

■ Key elements of project control

 Time management

 Cost management

 Performance management

 Earned value analysis

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 17

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

■ A branch reflects an activity of a project

■ A node represents the beginning and end of

activities, referred to as events

■ Branches in the network indicate precedence

Trang 18

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

■ Network aids in planning and scheduling.

■ Time duration of activities shown on branches

■ Activities can occur at the same time

(concurrently)

■ A dummy activity shows a precedence

relationship but reflects no passage of time

■ Two or more activities cannot share the same start

and end nodes

The Project Network

Concurrent Activities

Figure 8 7 A Dummy

Activity

Trang 19

The Project Network

House Building Project Data

No Activity Activity Predecessor

Trang 20

The Project Network

AOA Network for House Building

Trang 21

The Project Network

AON Network for House Building Project

Activity-on-Node (AON) Network

A node represents an activity, with its label and time shown on the node

 The branches show the precedence relationships

 Convention used in Microsoft Project software

Copyright © 2010 Pearson Education, Inc Publishing as Prentice Hall

Figure 8.8

Trang 22

The Project Network

Paths Through a Network

Table 8.1 Paths Through the House-Building

Trang 23

The critical path is the longest path through the

network; the minimum time the network can be

completed From Figure 8.8:

The Project Network

The Critical Path

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 24

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

The Project Network

Activity Start Times

Figure 8.9 Activity start time

Trang 25

The Project Network

Activity-on-Node Configuration

Figure 8.10 Activity-on-Node Configuration

Copyright © 2010 Pearson Education, Inc Publishing

as Prentice Hall

Trang 26

The Project Network

Activity Scheduling : Earliest Times

Figure 8.11 Earliest activity start and finish times

Trang 27

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

■ LS is the latest time an activity can start without

delaying critical path time: LS = LF - t

■ LF is the latest finish time LF = Minimum (LS)

The Project Network

Activity Scheduling : Latest Times

Figure 8.12 Latest activity start and finish times

Trang 28

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Slack is the amount of time an activity can be

delayed without delaying the project: S = LS – ES =

LF - EF

Slack Time exists for those activities not on the

critical path for which the earliest and latest start

times are not equal

Shared Slack is slack available for a sequence of

activities

The Project Network

Activity Slack Time (1 of 2)

Table 8.2

Trang 29

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

The Project Network

Activity Slack Time (2 of 2)

Figure 8.13 Activity slack

Trang 30

■ Activity time estimates usually cannot be

made with certainty.

PERT used for probabilistic activity

times.

■ In PERT, three time estimates are used:

most likely time (m), the optimistic time

(a), and the pessimistic time (b).

■ These provide an estimate of the mean and

variance of a beta distribution:

variance:

mean (expected time):

6

b4m

a

t  

26

a-

Probabilistic Activity Times

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 34

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Expected project time is the sum of the expected

times of the critical path activities

Project variance is the sum of the critical path

activities’ variances

■ The expected project time is assumed to be

normally distributed (based on central limit

Probabilistic Activity Times

Expected Project Time and Variance

Trang 35

■ Using the normal distribution, probabilities

are determined by computing the number of standard deviations (Z) a value is from the

mean.

■ The Z value is used to find corresponding

probability in Table A.1, Appendix A.

Probability Analysis of a Project

Network (1 of 2)

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 37

What is the probability that the new order

processing system will be ready by 30 weeks?

µ = 25 weeks

2 = 6.9  = 2.63 weeks

Z = (x-)/  = (30 -25)/2.63 = 1.90

Z value of 1.90 corresponds to probability of 4713

in Table A.1, Appendix A Probability of completing project in 30 weeks or less: (.5000 + 4713)

Trang 39

■ A customer will trade elsewhere if the new

ordering system is not working within 22 weeks

What is the probability that she will be retained?

Z = (22 - 25)/2.63 = -1.14

■ Z value of 1.14 (ignore negative) corresponds to

probability of 3729 in Table A.1, appendix A

■ Probability that customer will be retained is 1271

Probability Analysis of a Project

Network

Example 2 (1 of 2)

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 41

CPM/PERT Analysis with

QM for Windows & Excel QM (1 of 2)

Copyright © 2010 Pearson Education, Inc Publishing

as Prentice Hall

Trang 42

Copyright © 2010 Pearson Education, Inc Publishing as

CPM/PERT Analysis with

QM for Windows & Excel QM (2 of 2)

Trang 43

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Microsoft Project handles only AON networks

Analysis with Microsoft Project

(1 of 13)

Exhibit 8.3

Trang 56

■ Project duration can be reduced by assigning

more resources to project activities

■ However, doing this increases project cost.

■ Decision is based on analysis of trade-off

between time and cost

Project crashing is a method for shortening

project duration by reducing one or more critical activities to a time less than normal activity time

Project Crashing and

Time-Cost Trade-Off Overview

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 58

Copyright © 2010 Pearson Education, Inc Publishing as

Trang 59

Copyright © 2010 Pearson Education, Inc Publishing as

Project Crashing and Time-Cost

Trade-Off

Example Problem (3 of 5)

Trang 61

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Figure 8.22 Revised Network with Activity 1 Crashed

Project Crashing and Time-Cost

Trade-Off

Example Problem (5 of 5) As activities are crashed, the critical path

may change and several paths may become critical.

Trang 62

Copyright © 2010 Pearson Education, Inc Publishing as

Trang 63

Project Crashing and Time-Cost

Trade-Off

General Relationship of Time and

Cost (1 of 2) ■ Project crashing costs and indirect costs

have an inverse relationship.

■ Crashing costs are highest when the project

is shortened

■ Indirect costs increase as the project

duration increases.

■ Optimal project time is at minimum point on

the total cost curve.

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 64

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 65

General linear programming model with AOA

convention:

Minimize Z = xisubject to:

xj - xi  tij for all activities i  j

xi, xj  0

Where:

xi = earliest event time of node i

xj = earliest event time of node j

Trang 66

The CPM/PERT Network

Example Problem Formulation and

Data (1 of 2)

Figure 8.24

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 67

The CPM/PERT Network

Example Problem Formulation and

Data (2 of 2)

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 68

Exhibit 8.17

The CPM/PERT Network

Example Problem Solution with

Excel (1 of 4)

B6:B12

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 69

Exhibit 8.18

The CPM/PERT Network

Example Problem Solution with

Excel (2 of 4)

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 70

Exhibit 8.19

The CPM/PERT Network

Example Problem Solution with

Excel (3 of 4)

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 71

Exhibit 8.20

The CPM/PERT Network

Example Problem Solution with

Excel (4 of 4)

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 72

Minimize Z = $400y12 + 500y23 + 3000y24 + 200y45 +

7000y46 + 200y56 + 7000y67

xi = earliest event time of node I

xj = earliest event time of node j

yij = amount of time by which activity i  j is crashed

Project Crashing with Linear

Trang 73

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 74

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 75

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 76

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Given this network and the data on the following

slide, determine the expected project completion

time and variance, and the probability that the

project will be completed in 28 days or less

Example Problem

Problem Statement and Data (1 of 2)

Trang 78

t  

26

a-

Trang 80

Example Problem Solution (3 of

4)

Step 3: Identify the critical path and compute expected

completion time and variance

 Critical path (activities with no slack): 1  3  5  7

 Expected project completion time: tp = 9+5+6+4 =

24 days

 Variance: vp = 4 + 4/9 + 4/9 + 1/9 = 5 (days)2

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 81

Example Problem Solution (4 of

4)

Step 4: Determine the Probability That the Project Will

be Completed in 28 days or less (µ = 24,  =

5)

Z = (x - )/ = (28 -24)/5 = 1.79Corresponding probability from Table A.1, Appendix A,

is 4633 and P(x  28) = 4633 + 5 = 9633

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Trang 82

Copyright © 2010 Pearson Education, Inc Publishing as

Prentice Hall

Ngày đăng: 08/01/2018, 16:34

TỪ KHÓA LIÊN QUAN