• Standard: with at least 80% accuracy • Identify key variables from case study data • Calculate BAC, schedule and cost variances, and EAC... Building the Great Pyramid Case A: The Air F
Trang 1Apply Earned Value Management
Principles to Case Study Scenario:
Completing the Great Pyramid
Trang 2If Only the Pharaoh Had
the Corps of Engineers
Trang 3Terminal Learning Objective
• Task: Apply Earned Value Management Principles
to Case Study Scenario
• Condition: You are training to become an ACE
with access to ICAM course handouts, readings, and spreadsheet tools and awareness of
Operational Environment (OE)/Contemporary
Operational Environment (COE) variables and
actors.
• Standard: with at least 80% accuracy
• Identify key variables from case study data
• Calculate BAC, schedule and cost variances, and EAC
Trang 4Building the Great Pyramid Case A: The Air Force Approach
• Read the paper “If the Pharaoh Had Only Used an
Earned Value System in Building the Pyramids”
• By LTC Neimann (USAF Ret) found at
https://acc.dau.mil/CommunityBrowser.aspx?id=19572
• Using the tools learned:
• Build and verify the BAC presented in the paper
• Determine schedule variance at Year 12
• Determine the cost variance at Year 12
• Calculate EAC at Year 12
Trang 5Budget at Completion: BAC
Year Design Mfg Comp Test Assemble Intg Test Total Cum
Trang 6Schedule and Cost Variances:
Design at Year 12
BCWS Schedule Variance BCWP Variance Cost ACWP
Trang 7Schedule and Cost Variances:
Manufacture at Year 12
BCWS Schedule Variance BCWP Variance Cost ACWP
Trang 8Schedule and Cost Variances:
Component Test at Year 12
BCWS Schedule Variance BCWP Variance Cost ACWP
Trang 9Year 12 Results
• We are now behind schedule and over cost: terrible!!
• ACWP is 130% of BCWP so EAC can be projected at 130% of BAC: (1.30)20M = 26M
BCWS Schedule Variance BCWP Variance Cost ACWP
Trang 10Building the Great Pyramid Case B: Corps of Engineers
• The Pharaoh was quite displeased with the Air Force Pyramid Building Project’s AAR results
• LTC Neimann was re-assigned to flying carpets and
moved to a lovely tent in the Sinai where he soon retired
• The Pharaoh turned to the Corps of Engineers
• He asked for project proposals to complete the Great
Pyramid within four years
• The Corps of Engineers tasked six teams to make
proposals to complete an enhanced, Army-ized Army-ized pyramid
Trang 11The U.S Army Corps of Engineers
www.usace.army.mil/services
• Is the Nation’s number one federal provider of outdoor recreation
• Owns and operates more than 600 dams
• Operates and maintains 12,000 miles of commercial inland navigation channels
• Dredges more than 200 million cubic yards of construction and maintenance dredge material annually
• Maintains 926 coastal, Great Lakes and inland harbors
• Restores, creates, enhances or preserves tens of thousands of acres of wetlands
annually under the Corps’ Regulatory Program
• Provides a total water supply storage capacity of 329.2 million acre-feet in major
Trang 12Team Design Options:
Pick Two from Left and Three from Right
Take advantage of Corps’ Core
Competencies
• Add a dam and lake to
provide recreational venue
for tourists and pilgrims
• Divert the Nile River to ease
transportation to site
• Build levees around pyramid
to eliminate any flooding
threat
• Build barracks facilities for
workers and guests
• Up to one more of your
Trang 13Task 1: Build Your BAC
• Build your work breakdown structure given your
choices from the previous page
• Assume each task takes two years
• Don’t ignore need for more blocks and the assembly task
• You should have seven tasks (blocks, assembly, two corps’
core competency, and three Army-ize)
• Estimate cost for each task for years 1, 2, 3, 4 (in year
3000 BC shekels)
• Present your design, work schedule and graph of BCWS
to the class
• Make sure you don’t exceed the $13M the Air Force had
estimated for added cost to completion
Trang 14Budgeted Cost of Work Scheduled:
Fill in the Blanks
Trang 15Graph of Pyramid Completion Project
Trang 16Team Proposal Presentations
Trang 17Task 2: AAR for the Pharaoh
• Generate actual cost and schedule per following page’s instructions
• Present to class
• Cost and schedule variances for each year until
completion (4+ slides)
• BAC and EAC for the first year (1 slide)
• Graph of BCWS, BCWP, ACWP (1 slide)
• A reconciliation of your variance results at completion (1
slide)
• Suggestions for continuous improvement (1 slide)
• A view of what your finished pyramid looks like (1 slide)
Trang 18Task 2: Developing Actual
Cost and Schedule
• Use the randbetween formula in Excel to generate a random number between 1 and 10 for each task:
Trang 19Task 2: Reality Hits
1 Freak rain storms wash out a year’s progress: add year at same cost
2 Assyrians attack but are easily defeated: however, add 20% to task cost
3 Engineering error: task takes a third year at same average cost per year
4 Outsourcing accelerates progress, raises 1st year cost 50% but completes task
5 Slaves rebel: add 50% to task cost
6 Conquests add slaves to workforce: cut task cost 30% & finish one year early
7 Dust storms disrupt work: add 20% to task cost
8 Hidden Air Force funds discovered: reduce task cost 50%
9 LSS improves process: eliminate 2nd year and its cost
10 Finance Corps ACES assigned to project: reduce cost of all tasks 10%
Trang 20Team AAR Presentations
Trang 21Teacher’s Notes: Example
Trang 22Teacher’s Notes: Actual Costs
2 20% more cost assemble 540 540 1080 1755
1010% less all tasks divert nile 900 900 1800 3555
3 add yr at same cost dam and lake 1800 900 1350 4050 7605
2 20% more cost camo 2160 1080 3240 10845
total 1215 3465 4635 2880 12195
Trang 23Teacher’s Notes: Example
bcws schedule variance bcwp variance cost acwp
cost at point in time 500 500 1000 325 675
cost at point in time 500 0 500 (40) 540
year 1 total 1000 500 1500 285 1215
acwp/bcwp 81%
Trang 24Teacher’s Notes: 2 nd Year Results
Trang 25Teacher’s Notes: 3 rd Year Results
bcws variance bcwp variance acwp
Trang 27Graphing the Pyramid Project
ACWP BCWS
BCWP
Trang 28Graphing the Pyramid Project
ACWP BCWS
BCWP
Trang 29Army audit agency discovered hidden Air Force funds 1500
Block outsourcing continuous improvement 250
Trang 30Teacher’s Notes:
Continuous Improvement Suggestions
• Get more ACES and involve them more
• Check Engineering designs before they create major cost overruns
• Double check Engineering designs
• Look for more outsourcing opportunities
Trang 31Camouflaged Pyramid on Lake:
Excellent Camouflage, Isn’t It?!