1. Trang chủ
  2. » Giáo án - Bài giảng

Slides 11 3 calculate schedule and cost variances with earne

63 180 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 63
Dung lượng 5,05 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Consider the Possibilities at any Given Consider the Possibilities at any Given Point During the Project • Being right on schedule and at the expected cost is perfect but rarely happens

Trang 1

Calculate Schedule and Cost Variances with Earned Value Analysis

Trang 2

How Can We Better Manage Large, Complex, Non Repetitive Projects?

Trang 3

Terminal Learning Objective

• Task: Calculate Schedule and Cost Variances with

Earned Value Analysis

• Condition: You are training to become an ACE with

access to ICAM course handouts, readings, and

spreadsheet tools and awareness of Operational

Environment (OE)/Contemporary Operational

Environment (COE) variables and actors.

• Standard: with at least 80% accuracy:

• Describe theory of Earned Value Analysis

• Explain the concept of schedule and cost variances in

context of Earned Value Analysis

• Prepare AAR reconciliation using Earned Value Analysis

Trang 4

• In subsequent lessons we will be dealing with

• Organization based control

• Role based control

• Output based control

• Here we would like to start with a simpler

concept

• Project management and control

• The question is “how can we perform better in

Trang 5

Definition of Project

• Projects are

• Discrete tasks rather than continuous operations

• Often one-time or infrequent rather than repeated

• Frequently complex, ambiguous, or pioneering

• Tasks that require a significant length of time

Trang 6

• The nature of projects results in a high degree

of risk

• There are two types of risk:

• Risk that the project will not be completed in the timeframe expected: schedule varianceschedule variance

• Risk that the project will not be completed within the budget allotted: cost variancecost variance

Trang 7

Consider the Possibilities at any Given

Consider the Possibilities at any Given

Point During the Project

• Being right on schedule and at the expected cost is perfect (but rarely happens)

Ahead Of Right On Behind

Trang 8

Consider the Possibilities at any Given

Consider the Possibilities at any Given

Point During the Project

• Being ahead of or on schedule and at or less than

expected cost is a good thing

Ahead Of Right On Behind

Trang 9

Consider the Possibilities at any Given

Consider the Possibilities at any Given

Point During the Project

• Being behind or on schedule and at or more than

expected cost is not a good thing

Ahead Of Right On Behind

cost

More than Expected Not Good! Terrible!!

Less than Expected

Trang 10

Consider the Possibilities at any Given

Consider the Possibilities at any Given

Point During the Project

• Can’t really tell if this is good news or bad without further analysis

Ahead Of Right On Behind

Trang 11

Consider the Possibilities at any Given

Consider the Possibilities at any Given

Point During the Project

Ahead Of Right On Behind

cost

More than Expected ?? Not Good! Terrible!!

As Expected Great! Perfect Not Good!Less than Expected Terrific!! Great! ??

Trang 12

Earned Value Analysis

• Earned value management (EVM) provides an common set of metrics for measuring both

• Schedule variance and

• Cost Variance

• EVM combined with AAR offers a template for cost management and control of projects

Trang 13

Earned Value Analysis

• There are many resources available for more

in depth study of Earned Value

Trang 14

Requirements for Success

• The four requirements for successful cost

management and control remain the same

• Leadership: actively engaged in understanding and

improving performance

• Cost staff: supporting leadership with analysis, insight, and advice

• Process: the AAR where accountable subordinates

explain costs and schedules and ways to improve both

• Measurement: schedule and cost variances as

Trang 15

What Does Earned Value Mean?

• Since there are risks to both cost and schedule

some method is needed to link the two

• Earned value measures what has been

accomplished in terms of planned (budgeted)

cost

• In this sense it is similar to the flexible forecast we

used previously in analyzing volume variance

• Just like in the flexible forecast we will use the original planning factors to evaluate (in dollar terms) how

much more or less work has been done

Trang 16

Learning Check

• What are some of the characteristics of

projects that may pose management

challenges?

• What are the two categories of risk related to projects?

Trang 17

Starting Point: The Plan (Budget)

• Just as in analyzing volume and performance

variance we must start with an expectation

• This is the plan or budget

• The plan or budget must define two of the

following three variables in the equation:

cost = output x cost per output

• Some measure of output (like units)

• A measure of cost per output

• The total cost

• Furthermore, the plan defines these variables for all time periods or milestones within the project

Trang 18

One Difference: Non-Linearity Possible

• Volume variance recognizes that cost fits the equation

• Cost = variable cost per unit x units + fixed cost

• Resulting in a linear relationship in plotting $

versus units

• Earned value analysis planning is likely to be non-linear

• This is to say that cost and effort will not increase

at a constant rate when plotting $ versus time

Trang 19

Comparing Flexible Forecast to Project

Budget

$

time

Trang 20

Comparing Flexible Forecast to Project

Budget

$

units

Trang 21

Essential Vocabulary of EVM Variables

BCWS Budgeted Cost for Work Scheduled

• How much work should be done?

BCWP Budgeted Cost for Work Performed

• How much should it cost for the work actually done?

ACWP Actual Cost of Work Performed

• How much did the work done actually cost?

BAC Budget at Completion

• What was the total project supposed to cost?

EACEstimate at Completion

• What do we now expect the project to cost?

Trang 22

Tying Terminology to Graph

• Suppose that halfway through the project

• ACWP is lower than expected “at that time”

• BCWP is higher than expected “at that time”

$

time

BCWS ACWP

Trang 23

Tying Terminology to Graph

• Suppose that halfway through the project

• ACWP is lower than expected “at that time”

• BCWP is higher than expected “at that time”

• What does this mean????? (Terrific!!: we are ahead of

$

time

BCWS ACWP BCWP

Trang 24

Tying Terminology to Graph

• Suppose that halfway through the project

• ACWP is lower than expected “at that time”

• BCWP is higher than expected “at that time”

$

time

BCWS ACWP BCWP

Trang 25

Tying Terminology to Graph

• Suppose that halfway through the project

• ACWP is lower than expected “at that time”

• BCWP is higher than expected “at that time”

• What does this mean????? (Terrific!!: we are ahead of

$

time

BCWS ACWP

BCWP

BAC EAC

Trang 26

Schedule Variance Logic Differs

From Cost Variance

• In calculating cost volume variance cost volume variance we looked at increased units resulting

in more cost

• More cost is (unfavorable) by definition in cost variance analysis

• In calculating schedule variance schedule variance we look at this situation quite differently

• Even though cost is higher the logic here is that we are ahead of the spending schedule and therefore this is a favorable schedule variance

Plan Flexible Fcst Variance Volume

Variable cost 500 650 (150)

Plan BCWP Schedule

Trang 27

Here’s Why: We’re Looking at Two

Different Dimensions

Cost Variance looks at the Y axis

• Any point above the BCWS is over

cost: unfavorable

Schedule variance looks at the X axis

• Any point left of the BCWS is ahead

of spending schedule in the time

$

time

$

time

Trang 28

EVM Variance Template

• Here you can see some of the similarities to other variance analyses

• BCWP is calculated using the budgeted cost per and the actual units

• Cost variance is favorable since ACWP is less than BCWP

• And differences:

• Note that the sum of variance is no longer meaningful

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost at a Point in

Trang 29

EVM Variance Summary

• Cost Variance = BCWP – ACWP

• Logic: Like a typical cost variance less actual cost than budgeted is a favorable variance

• More actual cost than budgeted is an (unfavorable)

Trang 30

Calculating EAC: Estimate at

Completion

• One other very useful metric to calculate is

the estimated cost at completion

• There are numerous ways to estimate this

• Detailed re-forecast of remaining costs – may be costly

• Management guess – may be optimistic

• Projection from results to date – assumes that we will finish remaining work with the same level of

Trang 31

Calculating EAC: Estimate at

Completion

• Consider the previous example

• The ratio of ACWP to BCWP is 80%

• If we complete the project at this efficiency then EAC will be 80% of BAC

• If BAC was 1000 then we would estimate completion

Trang 32

• What information does the comparison of

BCWP to BCWS give?

• What can be said about the project if ACWP is greater than BCWS?

Learning Check

Trang 33

The Project Management AAR

• Uses EVM metrics as part of the measurement

• There are many application opportunities for

project management AARs

• Acquisitions, research and development,

experimentations, building and construction, BRAC,

Trang 34

course the last semester with each costing $2000

• You successfully completed the first semester’s

course which cost $2000

• Task: Determine your budget at completion (BAC),

schedule variance, cost variance, and estimate at

Trang 35

Budget at Completion: BAC

semester courses cost per bcws cum

Trang 36

Schedule and Cost Variances Estimate at Completion (EAC)

• We are on schedule and at cost expected: perfect

• Cost Estimated At Completion (EAC) will be

unchanged from the BAC since ACWP is same as

BCWS Schedule Variance BCWP Variance Cost ACWP

Courses Taken – 1 st Semester 1

Cost per Unit – 1 st Semester 2000

Cost after 1 st Semester 2000

Trang 37

Schedule and Cost Variances Estimate at Completion (EAC)

• We are on schedule and at cost expected: perfect

• Cost Estimated At Completion (EAC) will be

unchanged from the BAC since ACWP is same as

BCWP

BCWS Schedule Variance BCWP Variance Cost ACWP

Trang 38

Schedule and Cost Variances Estimate at Completion (EAC)

• We are on schedule and at cost expected: perfect

• Cost Estimated At Completion (EAC) will be

unchanged from the BAC since ACWP is same as

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost per Unit – 1 st Semester 2000 2000 2000 Cost after 1 st Semester 2000 2000 2000

Trang 39

Schedule and Cost Variances Estimate at Completion (EAC)

• We are on schedule and at cost expected: perfect

• Cost Estimated At Completion (EAC) will be

unchanged from the BAC since ACWP is same as

BCWP

Trang 40

Schedule and Cost Variances Estimate at Completion (EAC)

• We are on schedule and at cost expected: perfect

• Cost Estimated At Completion (EAC) will be

unchanged from the BAC since ACWP is same as

Trang 41

Schedule and Cost Variances Estimate at Completion (EAC)

• We are on schedule and at cost expected: perfect

• Cost Estimated At Completion (EAC) will be

unchanged from the BAC since ACWP is same as

BCWP

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost per Unit – 1 st Semester 2000 2000 2000 Cost after 1 st Semester 2000 2000 2000

Trang 42

Classroom Exercise – 2nd Semester

Trang 43

2nd Semester Results

• We are now behind schedule and over cost: terrible!!

• ACWP is 105% of BCWP so EAC can be projected at 105% of

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 1 st Semester 2000 2000 2000

Courses Taken – 2 nd Semester 2

Cost per Unit – 2 nd Semester 2000

Cost of 2 nd Semester 4000

Cost after 2 nd Semester 6000

Trang 44

2nd Semester Results

• We are now behind schedule and over cost: terrible!!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 1 st Semester 2000 2000 2000

Trang 45

2nd Semester Results

• We are now behind schedule and over cost: terrible!!

• ACWP is 105% of BCWP so EAC can be projected at 105% of

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 1 st Semester 2000 2000 2000

Cost per Unit – 2 nd Semester 2000 2000 2200

Trang 46

2nd Semester Results

• We are now behind schedule and over cost: terrible!!

Trang 47

2nd Semester Results

• We are now behind schedule and over cost: terrible!!

• ACWP is 105% of BCWP so EAC can be projected at 105% of

Trang 48

2nd Semester Results

• We are now behind schedule and over cost: terrible!!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 1 st Semester 2000 2000 2000

Cost per Unit – 2 nd Semester 2000 2000 2200 Cost of 2 nd Semester 4000 (2000) 2000 (200) 2200

Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200

Trang 49

Classroom Exercise – 3rd Semester

Trang 50

3rd Semester Results

• We are now back on schedule but over cost: not

good!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200

Courses Taken – 3 rd Semester 2

Cost per Unit – 3 rd Semester 2000

Cost of 3 rd Semester 4000

Cost after 3 rd Semester 10000

Trang 51

3rd Semester Results

• We are now back on schedule but over cost: not

good!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200

Trang 52

3rd Semester Results

• We are now back on schedule but over cost: not

good!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200

Cost per Unit – 3 rd Semester 2000 2000 2400

Cost after 3 rd Semester 10000 10000 11400

Trang 53

3rd Semester Results

• We are now back on schedule but over cost: not

good!

Trang 54

3rd Semester Results

• We are now back on schedule but over cost:

not good!

Trang 55

3rd Semester Results

• We are now back on schedule but over cost: not

good!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200

Cost per Unit – 3 rd Semester 2000 2000 2400 Cost of 3 rd Semester 4000 2000 6000 (1200) 7200

Cost after 3 rd Semester 10000 10000 (1400) 11400

Trang 56

Individual Exercise: 4th Semester

Trang 57

4th Semester Results

• We are now back on schedule but over cost: not

good!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 3 nd Semester

Courses Taken – 4 th Semester

Cost per Unit – 4 th Semester

Cost of 4 th Semester

Cost after 4 th Semester

Trang 58

4th Semester Results

• We are now ahead of schedule but over cost: not

good!

BCWS Schedule Variance BCWP Variance Cost ACWP

Cost after 3 nd Semester 10000 10000 (1400) 11400

Cost per Unit – 4 th Semester 2000 2000 2600 Cost of 4 th Semester 4000 2000 6000 (1800) 7800

Cost after 4 th Semester 14000 2000 16000 (3200) 19200

Trang 59

MBA Project Graph after 4th Semester Semester

BAC

Trang 60

MBA Project Graph after 4th Semester Semester

BCWP

EAC

Trang 61

• Projects offer many important opportunities for cost management and control

• The requirements for success are identical to

other cost management and control effort

• The major difference is that project management requires attention to both

• Schedule variance

• Cost variance

• Another difference is that AARs might be

scheduled at logical project milestones rather

than fixed time intervals

Trang 62

Teacher’s Note

petition to avoid courses

This is like a performance variance

This is like a volume variance

Trang 63

Teacher’s Note: MBA Exercise

Ngày đăng: 08/01/2018, 10:49