Consider the Possibilities at any Given Consider the Possibilities at any Given Point During the Project • Being right on schedule and at the expected cost is perfect but rarely happens
Trang 1Calculate Schedule and Cost Variances with Earned Value Analysis
Trang 2How Can We Better Manage Large, Complex, Non Repetitive Projects?
Trang 3Terminal Learning Objective
• Task: Calculate Schedule and Cost Variances with
Earned Value Analysis
• Condition: You are training to become an ACE with
access to ICAM course handouts, readings, and
spreadsheet tools and awareness of Operational
Environment (OE)/Contemporary Operational
Environment (COE) variables and actors.
• Standard: with at least 80% accuracy:
• Describe theory of Earned Value Analysis
• Explain the concept of schedule and cost variances in
context of Earned Value Analysis
• Prepare AAR reconciliation using Earned Value Analysis
Trang 4• In subsequent lessons we will be dealing with
• Organization based control
• Role based control
• Output based control
• Here we would like to start with a simpler
concept
• Project management and control
• The question is “how can we perform better in
Trang 5Definition of Project
• Projects are
• Discrete tasks rather than continuous operations
• Often one-time or infrequent rather than repeated
• Frequently complex, ambiguous, or pioneering
• Tasks that require a significant length of time
Trang 6• The nature of projects results in a high degree
of risk
• There are two types of risk:
• Risk that the project will not be completed in the timeframe expected: schedule varianceschedule variance
• Risk that the project will not be completed within the budget allotted: cost variancecost variance
Trang 7Consider the Possibilities at any Given
Consider the Possibilities at any Given
Point During the Project
• Being right on schedule and at the expected cost is perfect (but rarely happens)
Ahead Of Right On Behind
Trang 8Consider the Possibilities at any Given
Consider the Possibilities at any Given
Point During the Project
• Being ahead of or on schedule and at or less than
expected cost is a good thing
Ahead Of Right On Behind
Trang 9Consider the Possibilities at any Given
Consider the Possibilities at any Given
Point During the Project
• Being behind or on schedule and at or more than
expected cost is not a good thing
Ahead Of Right On Behind
cost
More than Expected Not Good! Terrible!!
Less than Expected
Trang 10Consider the Possibilities at any Given
Consider the Possibilities at any Given
Point During the Project
• Can’t really tell if this is good news or bad without further analysis
Ahead Of Right On Behind
Trang 11Consider the Possibilities at any Given
Consider the Possibilities at any Given
Point During the Project
Ahead Of Right On Behind
cost
More than Expected ?? Not Good! Terrible!!
As Expected Great! Perfect Not Good!Less than Expected Terrific!! Great! ??
Trang 12Earned Value Analysis
• Earned value management (EVM) provides an common set of metrics for measuring both
• Schedule variance and
• Cost Variance
• EVM combined with AAR offers a template for cost management and control of projects
Trang 13Earned Value Analysis
• There are many resources available for more
in depth study of Earned Value
Trang 14Requirements for Success
• The four requirements for successful cost
management and control remain the same
• Leadership: actively engaged in understanding and
improving performance
• Cost staff: supporting leadership with analysis, insight, and advice
• Process: the AAR where accountable subordinates
explain costs and schedules and ways to improve both
• Measurement: schedule and cost variances as
Trang 15What Does Earned Value Mean?
• Since there are risks to both cost and schedule
some method is needed to link the two
• Earned value measures what has been
accomplished in terms of planned (budgeted)
cost
• In this sense it is similar to the flexible forecast we
used previously in analyzing volume variance
• Just like in the flexible forecast we will use the original planning factors to evaluate (in dollar terms) how
much more or less work has been done
Trang 16Learning Check
• What are some of the characteristics of
projects that may pose management
challenges?
• What are the two categories of risk related to projects?
Trang 17Starting Point: The Plan (Budget)
• Just as in analyzing volume and performance
variance we must start with an expectation
• This is the plan or budget
• The plan or budget must define two of the
following three variables in the equation:
cost = output x cost per output
• Some measure of output (like units)
• A measure of cost per output
• The total cost
• Furthermore, the plan defines these variables for all time periods or milestones within the project
Trang 18One Difference: Non-Linearity Possible
• Volume variance recognizes that cost fits the equation
• Cost = variable cost per unit x units + fixed cost
• Resulting in a linear relationship in plotting $
versus units
• Earned value analysis planning is likely to be non-linear
• This is to say that cost and effort will not increase
at a constant rate when plotting $ versus time
Trang 19Comparing Flexible Forecast to Project
Budget
$
time
Trang 20Comparing Flexible Forecast to Project
Budget
$
units
Trang 21Essential Vocabulary of EVM Variables
• BCWS Budgeted Cost for Work Scheduled
• How much work should be done?
• BCWP Budgeted Cost for Work Performed
• How much should it cost for the work actually done?
• ACWP Actual Cost of Work Performed
• How much did the work done actually cost?
• BAC Budget at Completion
• What was the total project supposed to cost?
• EACEstimate at Completion
• What do we now expect the project to cost?
Trang 22Tying Terminology to Graph
• Suppose that halfway through the project
• ACWP is lower than expected “at that time”
• BCWP is higher than expected “at that time”
$
time
BCWS ACWP
Trang 23Tying Terminology to Graph
• Suppose that halfway through the project
• ACWP is lower than expected “at that time”
• BCWP is higher than expected “at that time”
• What does this mean????? (Terrific!!: we are ahead of
$
time
BCWS ACWP BCWP
Trang 24Tying Terminology to Graph
• Suppose that halfway through the project
• ACWP is lower than expected “at that time”
• BCWP is higher than expected “at that time”
$
time
BCWS ACWP BCWP
Trang 25Tying Terminology to Graph
• Suppose that halfway through the project
• ACWP is lower than expected “at that time”
• BCWP is higher than expected “at that time”
• What does this mean????? (Terrific!!: we are ahead of
$
time
BCWS ACWP
BCWP
BAC EAC
Trang 26Schedule Variance Logic Differs
From Cost Variance
• In calculating cost volume variance cost volume variance we looked at increased units resulting
in more cost
• More cost is (unfavorable) by definition in cost variance analysis
• In calculating schedule variance schedule variance we look at this situation quite differently
• Even though cost is higher the logic here is that we are ahead of the spending schedule and therefore this is a favorable schedule variance
Plan Flexible Fcst Variance Volume
Variable cost 500 650 (150)
Plan BCWP Schedule
Trang 27Here’s Why: We’re Looking at Two
Different Dimensions
Cost Variance looks at the Y axis
• Any point above the BCWS is over
cost: unfavorable
Schedule variance looks at the X axis
• Any point left of the BCWS is ahead
of spending schedule in the time
$
time
$
time
Trang 28EVM Variance Template
• Here you can see some of the similarities to other variance analyses
• BCWP is calculated using the budgeted cost per and the actual units
• Cost variance is favorable since ACWP is less than BCWP
• And differences:
• Note that the sum of variance is no longer meaningful
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost at a Point in
Trang 29EVM Variance Summary
• Cost Variance = BCWP – ACWP
• Logic: Like a typical cost variance less actual cost than budgeted is a favorable variance
• More actual cost than budgeted is an (unfavorable)
Trang 30Calculating EAC: Estimate at
Completion
• One other very useful metric to calculate is
the estimated cost at completion
• There are numerous ways to estimate this
• Detailed re-forecast of remaining costs – may be costly
• Management guess – may be optimistic
• Projection from results to date – assumes that we will finish remaining work with the same level of
Trang 31Calculating EAC: Estimate at
Completion
• Consider the previous example
• The ratio of ACWP to BCWP is 80%
• If we complete the project at this efficiency then EAC will be 80% of BAC
• If BAC was 1000 then we would estimate completion
Trang 32• What information does the comparison of
BCWP to BCWS give?
• What can be said about the project if ACWP is greater than BCWS?
Learning Check
Trang 33The Project Management AAR
• Uses EVM metrics as part of the measurement
• There are many application opportunities for
project management AARs
• Acquisitions, research and development,
experimentations, building and construction, BRAC,
Trang 34course the last semester with each costing $2000
• You successfully completed the first semester’s
course which cost $2000
• Task: Determine your budget at completion (BAC),
schedule variance, cost variance, and estimate at
Trang 35Budget at Completion: BAC
semester courses cost per bcws cum
Trang 36Schedule and Cost Variances Estimate at Completion (EAC)
• We are on schedule and at cost expected: perfect
• Cost Estimated At Completion (EAC) will be
unchanged from the BAC since ACWP is same as
BCWS Schedule Variance BCWP Variance Cost ACWP
Courses Taken – 1 st Semester 1
Cost per Unit – 1 st Semester 2000
Cost after 1 st Semester 2000
Trang 37Schedule and Cost Variances Estimate at Completion (EAC)
• We are on schedule and at cost expected: perfect
• Cost Estimated At Completion (EAC) will be
unchanged from the BAC since ACWP is same as
BCWP
BCWS Schedule Variance BCWP Variance Cost ACWP
Trang 38Schedule and Cost Variances Estimate at Completion (EAC)
• We are on schedule and at cost expected: perfect
• Cost Estimated At Completion (EAC) will be
unchanged from the BAC since ACWP is same as
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost per Unit – 1 st Semester 2000 2000 2000 Cost after 1 st Semester 2000 2000 2000
Trang 39Schedule and Cost Variances Estimate at Completion (EAC)
• We are on schedule and at cost expected: perfect
• Cost Estimated At Completion (EAC) will be
unchanged from the BAC since ACWP is same as
BCWP
Trang 40Schedule and Cost Variances Estimate at Completion (EAC)
• We are on schedule and at cost expected: perfect
• Cost Estimated At Completion (EAC) will be
unchanged from the BAC since ACWP is same as
Trang 41Schedule and Cost Variances Estimate at Completion (EAC)
• We are on schedule and at cost expected: perfect
• Cost Estimated At Completion (EAC) will be
unchanged from the BAC since ACWP is same as
BCWP
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost per Unit – 1 st Semester 2000 2000 2000 Cost after 1 st Semester 2000 2000 2000
Trang 42Classroom Exercise – 2nd Semester
Trang 432nd Semester Results
• We are now behind schedule and over cost: terrible!!
• ACWP is 105% of BCWP so EAC can be projected at 105% of
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 1 st Semester 2000 2000 2000
Courses Taken – 2 nd Semester 2
Cost per Unit – 2 nd Semester 2000
Cost of 2 nd Semester 4000
Cost after 2 nd Semester 6000
Trang 442nd Semester Results
• We are now behind schedule and over cost: terrible!!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 1 st Semester 2000 2000 2000
Trang 452nd Semester Results
• We are now behind schedule and over cost: terrible!!
• ACWP is 105% of BCWP so EAC can be projected at 105% of
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 1 st Semester 2000 2000 2000
Cost per Unit – 2 nd Semester 2000 2000 2200
Trang 462nd Semester Results
• We are now behind schedule and over cost: terrible!!
Trang 472nd Semester Results
• We are now behind schedule and over cost: terrible!!
• ACWP is 105% of BCWP so EAC can be projected at 105% of
Trang 482nd Semester Results
• We are now behind schedule and over cost: terrible!!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 1 st Semester 2000 2000 2000
Cost per Unit – 2 nd Semester 2000 2000 2200 Cost of 2 nd Semester 4000 (2000) 2000 (200) 2200
Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200
Trang 49Classroom Exercise – 3rd Semester
Trang 503rd Semester Results
• We are now back on schedule but over cost: not
good!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200
Courses Taken – 3 rd Semester 2
Cost per Unit – 3 rd Semester 2000
Cost of 3 rd Semester 4000
Cost after 3 rd Semester 10000
Trang 513rd Semester Results
• We are now back on schedule but over cost: not
good!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200
Trang 523rd Semester Results
• We are now back on schedule but over cost: not
good!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200
Cost per Unit – 3 rd Semester 2000 2000 2400
Cost after 3 rd Semester 10000 10000 11400
Trang 533rd Semester Results
• We are now back on schedule but over cost: not
good!
Trang 543rd Semester Results
• We are now back on schedule but over cost:
not good!
Trang 553rd Semester Results
• We are now back on schedule but over cost: not
good!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 2 nd Semester 6000 (2000) 4000 (200) 4200
Cost per Unit – 3 rd Semester 2000 2000 2400 Cost of 3 rd Semester 4000 2000 6000 (1200) 7200
Cost after 3 rd Semester 10000 10000 (1400) 11400
Trang 56Individual Exercise: 4th Semester
Trang 574th Semester Results
• We are now back on schedule but over cost: not
good!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 3 nd Semester
Courses Taken – 4 th Semester
Cost per Unit – 4 th Semester
Cost of 4 th Semester
Cost after 4 th Semester
Trang 584th Semester Results
• We are now ahead of schedule but over cost: not
good!
BCWS Schedule Variance BCWP Variance Cost ACWP
Cost after 3 nd Semester 10000 10000 (1400) 11400
Cost per Unit – 4 th Semester 2000 2000 2600 Cost of 4 th Semester 4000 2000 6000 (1800) 7800
Cost after 4 th Semester 14000 2000 16000 (3200) 19200
Trang 59MBA Project Graph after 4th Semester Semester
BAC
Trang 60MBA Project Graph after 4th Semester Semester
BCWP
EAC
Trang 61• Projects offer many important opportunities for cost management and control
• The requirements for success are identical to
other cost management and control effort
• The major difference is that project management requires attention to both
• Schedule variance
• Cost variance
• Another difference is that AARs might be
scheduled at logical project milestones rather
than fixed time intervals
Trang 62Teacher’s Note
petition to avoid courses
This is like a performance variance
This is like a volume variance
Trang 63Teacher’s Note: MBA Exercise