Learning ObjectivesWhen you complete this chapter, you should be able to: process-oriented facility layout a work cell in a repetitive or product-oriented facility... Kroger’s Supermark
Trang 4Focused Factory
Trang 5Outline – Continued
Layout
Trang 6Learning Objectives
When you complete this chapter you
should be able to:
and terms such as ASRS, cross-docking, and random stocking
appropriate
Trang 7Learning Objectives
When you complete this chapter, you
should be able to:
process-oriented facility layout
a work cell
in a repetitive or product-oriented facility
Trang 9Six out of the seven are layout decisions!
Trang 10McDonald’s New Layout
the world
Linger zone with comfortable chairs and Wi-Fi connections
Grab and go zone with tall counters
Flexible zone for kids and families
competitive advantage
Trang 11Strategic Importance of
Layout Decisions
The objective of layout strategy
is to develop a cost-effective layout that will meet a firm’s
competitive needs
Trang 12Layout Design Considerations
Trang 14Types of Layout
their equipment, and spaces/offices
to provide for movement of information
and responds to customer behavior
trade-offs between space and material handling
Trang 15Types of Layout
the layout requirements of large, bulky projects such as ships and buildings
low-volume, high-variety production (also called job shop or intermittent production)
Trang 16Types of Layout
machinery and equipment to focus
on production of a single product or group of related products
best personnel and machine utilizations in repetitive or
continuous production
Trang 17Good Layouts Consider
work areas
Trang 18Layout Strategies
Table 9.1
Office Retail Warehouse (storage)
Examples Allstate Insurance
Microsoft Corp.
Kroger’s Supermarket Walgreen’s Bloomingdale’s
Federal-Mogul’s warehouse
The Gap’s distribution center
Problems/Issues Locate workers
Balance low-cost storage with low- cost material
handling
Trang 19Layout Strategies
Table 9.1
Project (fixed position) (process oriented) Job Shop Examples
Ingall Ship Building Corp.
Trump Plaza Pittsburgh Airport
Arnold Palmer Hospital Hard Rock Café
Olive Garden
Problems/Issues Move material to the limited storage areas around the site
Manage varied material flow for each product
Trang 20Layout Strategies
Table 9.1
Work Cells (product families) Repetitive/ Continuous (product oriented)
Examples Hallmark Cards Wheeled Coach Standard Aero
Sony’s TV assembly line
Toyota Scion
Problems/Issues Identify a product family, build teams, cross train team members
Equalize the task time
at each workstation
Trang 21Office Layout
and spaces to provide comfort, safety, and movement of information
information is main distinction
flux due to frequent technological
changes
Trang 22Relationship Chart
Figure 9.1
Trang 23Supermarket Retail Layout
profitability per square foot of floor space
directly with customer exposure
Trang 24Five Helpful Ideas for Supermarket Layout
periphery of the store
and high-margin items
an aisle and disperse them to increase viewing of other items
positioning of lead-off department
Trang 25Store Layout
Figure 9.2
Trang 26Retail Slotting
to get the retailers to display (slot) their product
products
through POS data collection
Trang 27Retail Store Shelf Space
Trang 28characteristics such as lighting, sound, smell, and temperature
involve customer circulation path planning, aisle characteristics, and product grouping
artifacts - characteristics
of building design that carry social significance
Trang 29Warehousing and Storage
Layouts
between handling costs and costs associated with warehouse space
warehouse – utilize its full volume while maintaining low material
handling costs
Trang 30Warehousing and Storage
Material Handling Costs
Trang 31Warehousing and Storage
Layouts
inversely with the number of different items stored
Retrieval Systems (ASRSs) can significantly improve warehouse productivity by
an estimated 500%
design element
Trang 32receiving to shipping and are not placed in storage
in the warehouse
scheduling and accurate shipments, bar code or RFID
identification used for advanced shipment notification as materials are unloaded
Trang 33Random Stocking
systems (AISs) and effective information systems
allows more efficient use of space
1 Maintain list of open locations
2 Maintain accurate records
3 Sequence items to minimize travel, pick time
4 Combine picking orders
5 Assign classes of items to particular areas
Trang 35Shipping and receiving docks
Staging
Warehouse Layout
Traditional Layout
Trang 37Fixed-Position Layout
required at different stages of the project
needed is dynamic
Trang 38Alternative Strategy
is completed off-site in a oriented facility
significantly improve efficiency but is only
possible when multiple similar units need to be created
Trang 39Process-Oriented Layout
grouped together
wide variety of products or services
setup, material handling, and labor costs can be high
Trang 40Radiology
ER triage room
ER Beds Pharmacy
Emergency room admissions
Billing/exit Laboratories
Process-Oriented Layout
Patient A - broken leg
Patient B - erratic heart
pacemaker
Figure 9.3
Trang 41Layout at Arnold Palmer Hospital
Central break and medical supply rooms
Local linen
supply
Local
Pie-shaped rooms
Central nurses
station
Trang 42Process-Oriented Layout
minimize the costs of material handling
between centers
between centers
Trang 43© 2008 Prentice Hall, Inc. 9 – 43
X ij = number of loads moved from department i to department j
C ij = cost to move a load between department i and
Trang 44Process Layout Example
1 Construct a “from-to matrix”
2 Determine the space requirements
3 Develop an initial schematic diagram
4 Determine the cost of this layout
5 Try to improve the layout
6 Prepare a detailed plan
Arrange six departments in a factory to minimize the material handling costs
Each department is 20 x 20 feet and the building is 60 feet long and 40 feet wide.
Trang 45Department Assembly Painting Machine Receiving Shipping Testing
Number of loads per week
Trang 46Area 1 Area 2 Area 3
Area 4 Area 5 Area 6
60’
40’
Process Layout Example
Figure 9.5
Trang 47100 30
Process Layout Example
Interdepartmental Flow Graph
Figure 9.6
Trang 48Process Layout Example
Trang 49Process Layout Example
Trang 50Process Layout Example
Trang 51Area 1 Area 2 Area 3
Area 4 Area 5 Area 6
60’
40’
Process Layout Example
Figure 9.8
Trang 52Computer Software
small problems
solve bigger problems
Trang 53ITERATION 3
(b) Figure 9.9
Trang 54Computer Software
software allows managers to view possible layouts and assess process, material
handling, efficiency, and safety issues
Trang 55Work Cells
into groups to focus on single products or product groups
products that have similar characteristics for particular cells
designs or volume changes
Trang 56Advantages of Work Cells
1 Reduced work-in-process inventory
2 Less floor space required
3 Reduced raw material and finished
goods inventory
4 Reduced direct labor
5 Heightened sense of employee
Trang 57Improving Layouts Using
workers can assist each other
May be able to add a third worker
as additional output is needed.
Figure 9.10 (a)
Trang 58Improving Layouts Using
Work Cells
Current layout - straight lines make it hard to balance tasks because work may not
be divided evenly
Improved layout - in U shape, workers have better access Four cross-trained workers were reduced.
Trang 59Requirements of Work Cells
1 Identification of families of
products
2 A high level of training, flexibility
and empowerment of employees
equipment and resources
the cell
Trang 60Staffing and Balancing Work
Cells
Determine the takt time
Takt time = Total work time available
Trang 61Staffing Work Cells Example
600 Mirrors per day required
Mirror production scheduled for 8 hours per day
From a work balance chart
total operation time = 140 seconds
Trang 62Staffing Work Cells Example
600 Mirrors per day required
Mirror production scheduled for 8 hours per day
From a work balance chart
total operation time = 140 seconds
Takt time = (8 hrs x 60 mins) / 600 units
= 8 mins = 48 seconds Workers required = Total operation time required Takt time
= 140 / 48 = 2.91
Trang 63Work Balance Charts
times in work cells
operations
can help address labor bottlenecks
other approaches
Trang 64Focused Work Center and
Focused Factory
Identify a large family of similar products that have a large and stable demand
Moves production from a general-purpose, process-oriented facility to a large work cell
A focused work cell in a separate facility
May be focused by product line, layout, quality, new product introduction, flexibility,
or other requirements
Trang 65Focused Work Center and
Focused Factory
A work cell is a
temporary oriented arrangement
product-of machines and personnel in what is ordinarily a process- oriented facility.
A focused work center is
a permanent oriented arrangement
product-of machines and personnel in what is ordinarily a process- oriented facility.
A focused factory is a permanent facility to produce a product or component in a
product-oriented facility Many focused factories currently being built were originally part of a process-oriented facility.
Example: A job shop
with machinery and personnel rearranged
to produce 300 unique control panels.
Example: Pipe bracket manufacturing at a shipyard.
Example: A plant to produce window mechanism for automobiles.
Trang 66Repetitive and
Product-Oriented Layout
1 Volume is adequate for high equipment
utilization
2 Product demand is stable enough to justify high
investment in specialized equipment
3 Product is standardized or approaching a phase
of life cycle that justifies investment
4 Supplies of raw materials and components are
adequate and of uniform quality
Organized around products or families of
similar high-volume, low-variety products
Trang 67 Paced by work tasks
Balanced by moving tasks Both types of lines must be balanced so that the
time to perform the work at each station is the same
Trang 68Product-Oriented Layouts
1 Low variable cost per unit
2 Low material handling costs
3 Reduced work-in-process inventories
4 Easier training and supervision
5 Rapid throughput
Advantages
1 High volume is required
2 Work stoppage at any point ties up the
whole operation
3 Lack of flexibility in product or production
rates
Disadvantages
Trang 69McDonald’s Assembly Line
Figure 9.12
Trang 70Disassembly Lines
new product designs
standards are important consideration
disassembly is the 16 th largest industry in
the US
Trang 71Assembly-Line Balancing
between machines or personnel while meeting required output
relationships
1 Determine cycle time
2 Calculate theoretical
minimum number of workstations
3 Balance the line by
assigning specific tasks to workstations
Trang 72Wing Component Example
This means that tasks B and E cannot be done until task A has been completed
Performance Task Must Follow
Time Task Listed Task (minutes) Below
Trang 73Wing Component Example
Performance Task Must Follow
Time Task Listed Task (minutes) Below
C
D
H
B E
A
10
11 12
Trang 74G F
C
D
H
B E
A
10
11 12
Performance Task Must Follow
Time Task Listed Task (minutes) Below
= 480 / 40
= 12 minutes per unit
Minimum number of
Trang 75Wing Component Example
I
G F
C
D
H
B E
A
10
11 12
Performance Task Must Follow
Time Task Listed Task (minutes) Below
workstations = 5.5 or 6
Line-Balancing Heuristics
1 Longest task time Choose the available task
with the longest task time
2 Most following tasks Choose the available task
with the largest number of following tasks
3 Ranked positional weight Choose the available task for which the sum of following
task times is the longest
4 Shortest task time Choose the available task
with the shortest task time
5 Least number of following tasks Choose the available task with the least number of
following tasks
Table 9.4
Trang 76480 available
mins per day
40 units required Cycle time = 12 mins Minimum
workstations = 5.5 or 6
Performance Task Must Follow
Time Task Listed Task (minutes) Below
H
C
D B
Station 2
Trang 77Performance Task Must Follow
Time Task Listed Task (minutes) Below
workstations = 5.5 or 6
Efficiency = ∑ Task times
(Actual number of workstations) x (Largest cycle time)
= 66 minutes / (6 stations) x (12 minutes)
= 91.7%