TBM (tunnel boring machine) is the machine which use for the excavation of tunnel, galery , underground openings in metro, water, energy construction and mining projects etc. Advantages of EPB Lower capital cost Smaller site and launch Muck is immediately ready for disposal In case of face collapse amount of ground loss is limited
Trang 1MAD 427
Tunnelling and Support Design
Lecturer: Prof Dr.Bahtiyar ÜNVER
Subject: EPB and SLURRY types TBM
Janurary 2012
Trang 4WHAT IS THE TBM?
Trang 5WHAT IS THE TBM?
TBM (tunnel boring machine) is the
machine which use for the excavation of
tunnel, galery, underground openings in metro, water, energy construction and
mining projects etc
Trang 7
TYPES OF TBM
TBM
Soft Rock
Hard Rock
Gripper
Trang 8EPB (Earth PressureBalance)
Type TBM
Trang 9Working Area Condition EPB
Silt and clay (fine grained size)
Max 4 bar pressure (if over pressure
we can not use)
We do not want more water
Trang 10Advantages of EPB
Lower capital cost
Smaller site and launch
Muck is immediately ready for disposal
In case of face collapse amount of
ground loss is limited
Trang 11Disadvantages of EPB
Requires higher torque
Requires greater Cuttinghead power
Required confinement pressure must
be calculated
Muck is exposed into tunnel
Trang 12Slurry type TBM
Trang 13Working Area Conditions
Slurry
Sand and gravel
If we got more water income (slurry condition )
We can use approxiametly more than
10 bar pressure ( i.e In Bosphorus 13 bar pressure)
Trang 14Advantages of Slurry
Lower torque
Lower Cuttinghead Power
Cleaner Tunnel Environment
Contaminated muck is not exposed until it reaches the surface
Trang 15Disadvantages of Slurry
Requires a large size job site
Higher capital costs
Higher power requirement
Requires extensive addition of material
MAD 427
Tunnelling and Support Design
Trang 16Applications in TURKEY
Trang 18Collapse
If the ground pressure higher than the machine pressure The result ;
Trang 19Swelling
If the ground pressure lower than the machine pressure The result ;
Trang 20Leakage of Additivies
If we don’t control the additives and the slurry where they go The result ;
Trang 21Wrong Selection of TBM
If we do not make a good analyse of our ground and do not select the right TBM The result;
Trang 22CONCLUSION
Trang 23CONCLUSION
Trang 24Have a Nice and Shorter
Vacation
Before After
Trang 25ANY QUESTIONS??