Work Breakdown Structure for Computer Order Processing System Project Work Breakdown Structure for Computer Order Processing System Project... Organizational Breakdown Structure OBS
Trang 1Project Management
Operations Management - 6th Edition
Operations Management - 6th Edition
Chapter 9
Roberta Russell & Bernard W Taylor, III
Trang 3Project Management Process
Project
unique, one-time operational activity or effort
Trang 4Project Management Process
(cont.)
Trang 5Project Management Process
(cont.)
Trang 7Project Team and Project Manager
Project team
made up of individuals from various areas and
departments within a company
Matrix organization
a team structure with members from functional
areas, depending on skills required
Project manager
most important member of project team
Trang 8Scope Statement and Work
written description of objectives of a project
Work breakdown structure (WBS)
breaks down a project into components,
subcomponents, activities, and tasks
Trang 9Work Breakdown Structure for Computer Order
Processing System Project
Work Breakdown Structure for Computer Order
Processing System Project
Trang 10 Organizational Breakdown
Structure (OBS)
a chart that shows which organizational units are
responsible for work items
Responsibility Assignment Matrix (RAM)
shows who is responsible for work in a
project
Responsibility Assignment Matrix
Trang 11Global and Diversity Issues in
Project Management
In existing global business environment,
project teams are formed from different
genders, cultures, ethnicities, etc.
In global projects diversity among team
members can add an extra dimension to
project planning
Cultural research and communication are
important elements in planning process
Trang 13Gantt Chart
Graph or bar chart with a bar for each
project activity that shows passage of
time
Provides visual display of project
schedule
Slack
amount of time an activity can be delayed
without delaying the project
Trang 15 Earned Value Analysis
a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation
Enterprise project management
Trang 16 Critical Path Method (CPM)
DuPont & Remington-Rand (1956)
Deterministic task times
Activity-on-node network construction
Project Evaluation and Review Technique
(PERT)
US Navy, Booz, Allen & Hamilton
Multiple task time estimates; probabilistic
Activity-on-arrow network construction
Trang 17Project Network
Activity-on-node (AON)
nodes represent activities,
and arrows show
precedence relationships
Activity-on-arrow (AOA)
arrows represent activities
and nodes are events for
two or more activities
cannot share same start
and end nodes
Branch
Node
Trang 18AOA Project Network for
Design house
and obtain
financing
Order and receive materials
Dummy
Finish work
Select carpet
Select paint
Build house
Trang 194 2
Dummy
Lay foundation
Order material
1
Trang 20AON Network for House
Order and receive materials Select paint
Select carpet Lay foundations Build house
Finish work
Trang 21 Minimum project completion time
Trang 22Activity Start Times
Trang 24Activity Scheduling
Earliest start time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors
Forward pass
starts at beginning of CPM/PERT network to
determine earliest activity times
Earliest finish time (EF)
earliest time an activity can finish
earliest start time plus activity time
EF= ES + t
Trang 25Earliest Activity Start and
Finish Times
1 0 3
1
2 3 5 2
3 3 4
1
4 5 8 3
6 6 7 1
7 8 9 1
Trang 26Activity Scheduling (cont.)
Latest start time (LS)
Latest time an activity can start without delaying
critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without
delaying critical path time
LF = minimum LS of immediate predecessors
Backward pass
Determines latest activity times by starting at the end
of CPM/PERT network and working forward
Trang 27Latest Activity Start and
Trang 28* Critical Path
0 9
9 8
8
*7
1 7
8 6
7 6
1 6
7 5
6 5
0 8
8 5
5
*4
1 4
5 3
4 3
0 5
5 3
3
*2
0 3
3 0
0
*1
Slack S EF
LF ES
LS Activity
Activity Slack
Trang 29Probabilistic Time Estimates
Beta distribution
a probability distribution traditionally used in
CPM/PERT
a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate where
Mean (expected time): t = a + 4 m + b
6
Variance: 2 = b - a
6
2
Trang 30Examples of Beta Distributions
Trang 31Project Network with Probabilistic Time Estimates: Example
3,6,9
31,3,5
16,8,10
52,3,4
63,4,5
42,4,12
72,2,2
83,7,11
92,4,6
System development
Position recruiting
Equipment testing and modification
Manual testing
Job Training
Orientation
System training
System testing
Final debugging
System changeover
Trang 32Activity Time Estimates
Trang 33Activity Early, Late Times,
Trang 352 = б2 2 + б5 2 + б8 2 + б11 2
= 6.89 weeks Total project variance
Trang 37Probabilistic Network Analysis
Determine probability that project is
completed within specified time
where
= tp = project mean time
is from mean
Z = x -
Trang 39Southern Textile Example
What is the probability that the project is completed
From Table A.1, (appendix A) a Z score of 1.91 corresponds to a
probability of 0.4719 Thus P (30) = 0.4719 + 0.5000 = 0.9719
Trang 40Southern Textile Example
From Table A.1 (appendix A) a Z score of -1.14 corresponds to a
probability of 0.3729 Thus P (22) = 0.5000 - 0.3729 = 0.1271
Trang 41Microsoft Project
Popular software package for project
management and CPM/PERT analysis
Relatively easy to use
Trang 42Microsoft Project (cont.)
Trang 43Microsoft Project (cont.)
Trang 44Microsoft Project (cont.)
Trang 45Microsoft Project (cont.)
Trang 46Microsoft Project (cont.)
Trang 47Microsoft Project (cont.)
Trang 48PERT Analysis with
Microsoft Project
Trang 49PERT Analysis with
Microsoft Project (cont.)
Trang 50PERT Analysis with
Microsoft Project (cont.)
Trang 53Normal Time and Cost
vs Crash Time and Cost
Slope = crash cost per week
Trang 54Project Crashing: Example
TOTAL
Trang 5512
2 8
3
4
6 4
7 4
3
4
6 4
7 4
Trang 56 Crashing costs increase as project
duration decreases
Indirect costs increase as project
duration increases
Reduce project length as long as
crashing costs are less than indirect
costs
Time-Cost Relationship
Trang 57Minimum cost = optimal project time
Total project cost Indirect cost
Direct cost
Trang 58Copyright 2009 John Wiley & Sons, Inc 9-58
Copyright 2009 John Wiley & Sons, Inc.
All rights reserved Reproduction or translation
of this work beyond that permitted in section 117
of the 1976 United States Copyright Act without express permission of the copyright owner is
unlawful Request for further information should
be addressed to the Permission Department,
John Wiley & Sons, Inc The purchaser may
make back-up copies for his/her own use only
and not for distribution or resale The Publisher assumes no responsibility for errors, omissions,
or damages caused by the use of these
programs or from the use of the information