1. Trang chủ
  2. » Giáo án - Bài giảng

Operation management 6e by russel and taylor ch09

58 257 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 58
Dung lượng 8,41 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Work Breakdown Structure for Computer Order Processing System Project Work Breakdown Structure for Computer Order Processing System Project...  Organizational Breakdown Structure OBS 

Trang 1

Project Management

Operations Management - 6th Edition

Operations Management - 6th Edition

Chapter 9

Roberta Russell & Bernard W Taylor, III

Trang 3

Project Management Process

 Project

 unique, one-time operational activity or effort

Trang 4

Project Management Process

(cont.)

Trang 5

Project Management Process

(cont.)

Trang 7

Project Team and Project Manager

 Project team

 made up of individuals from various areas and

departments within a company

 Matrix organization

 a team structure with members from functional

areas, depending on skills required

 Project manager

 most important member of project team

Trang 8

Scope Statement and Work

 written description of objectives of a project

 Work breakdown structure (WBS)

 breaks down a project into components,

subcomponents, activities, and tasks

Trang 9

Work Breakdown Structure for Computer Order

Processing System Project

Work Breakdown Structure for Computer Order

Processing System Project

Trang 10

 Organizational Breakdown

Structure (OBS)

 a chart that shows which organizational units are

responsible for work items

 Responsibility Assignment Matrix (RAM)

 shows who is responsible for work in a

project

Responsibility Assignment Matrix

Trang 11

Global and Diversity Issues in

Project Management

 In existing global business environment,

project teams are formed from different

genders, cultures, ethnicities, etc.

 In global projects diversity among team

members can add an extra dimension to

project planning

 Cultural research and communication are

important elements in planning process

Trang 13

Gantt Chart

 Graph or bar chart with a bar for each

project activity that shows passage of

time

 Provides visual display of project

schedule

 Slack

 amount of time an activity can be delayed

without delaying the project

Trang 15

 Earned Value Analysis

 a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation

 Enterprise project management

Trang 16

 Critical Path Method (CPM)

 DuPont & Remington-Rand (1956)

 Deterministic task times

 Activity-on-node network construction

 Project Evaluation and Review Technique

(PERT)

 US Navy, Booz, Allen & Hamilton

 Multiple task time estimates; probabilistic

 Activity-on-arrow network construction

Trang 17

Project Network

 Activity-on-node (AON)

 nodes represent activities,

and arrows show

precedence relationships

 Activity-on-arrow (AOA)

 arrows represent activities

and nodes are events for

 two or more activities

cannot share same start

and end nodes

Branch

Node

Trang 18

AOA Project Network for

Design house

and obtain

financing

Order and receive materials

Dummy

Finish work

Select carpet

Select paint

Build house

Trang 19

4 2

Dummy

Lay foundation

Order material

1

Trang 20

AON Network for House

Order and receive materials Select paint

Select carpet Lay foundations Build house

Finish work

Trang 21

 Minimum project completion time

Trang 22

Activity Start Times

Trang 24

Activity Scheduling

 Earliest start time (ES)

 earliest time an activity can start

 ES = maximum EF of immediate predecessors

 Forward pass

 starts at beginning of CPM/PERT network to

determine earliest activity times

 Earliest finish time (EF)

 earliest time an activity can finish

 earliest start time plus activity time

EF= ES + t

Trang 25

Earliest Activity Start and

Finish Times

1 0 3

1

2 3 5 2

3 3 4

1

4 5 8 3

6 6 7 1

7 8 9 1

Trang 26

Activity Scheduling (cont.)

 Latest start time (LS)

 Latest time an activity can start without delaying

critical path time

LS= LF - t

 Latest finish time (LF)

 latest time an activity can be completed without

delaying critical path time

 LF = minimum LS of immediate predecessors

 Backward pass

 Determines latest activity times by starting at the end

of CPM/PERT network and working forward

Trang 27

Latest Activity Start and

Trang 28

* Critical Path

0 9

9 8

8

*7

1 7

8 6

7 6

1 6

7 5

6 5

0 8

8 5

5

*4

1 4

5 3

4 3

0 5

5 3

3

*2

0 3

3 0

0

*1

Slack S EF

LF ES

LS Activity

Activity Slack

Trang 29

Probabilistic Time Estimates

 Beta distribution

 a probability distribution traditionally used in

CPM/PERT

a = optimistic estimate

m = most likely time estimate

b = pessimistic time estimate where

Mean (expected time): t = a + 4 m + b

6

Variance:  2 = b - a

6

2

Trang 30

Examples of Beta Distributions

Trang 31

Project Network with Probabilistic Time Estimates: Example

3,6,9

31,3,5

16,8,10

52,3,4

63,4,5

42,4,12

72,2,2

83,7,11

92,4,6

System development

Position recruiting

Equipment testing and modification

Manual testing

Job Training

Orientation

System training

System testing

Final debugging

System changeover

Trang 32

Activity Time Estimates

Trang 33

Activity Early, Late Times,

Trang 35

2 = б2 2 + б5 2 + б8 2 + б11 2

= 6.89 weeks Total project variance

Trang 37

Probabilistic Network Analysis

Determine probability that project is

completed within specified time

where

 = tp = project mean time

is from mean

Z = x -  

Trang 39

Southern Textile Example

What is the probability that the project is completed

From Table A.1, (appendix A) a Z score of 1.91 corresponds to a

probability of 0.4719 Thus P (30) = 0.4719 + 0.5000 = 0.9719

Trang 40

Southern Textile Example

From Table A.1 (appendix A) a Z score of -1.14 corresponds to a

probability of 0.3729 Thus P (22) = 0.5000 - 0.3729 = 0.1271

Trang 41

Microsoft Project

 Popular software package for project

management and CPM/PERT analysis

 Relatively easy to use

Trang 42

Microsoft Project (cont.)

Trang 43

Microsoft Project (cont.)

Trang 44

Microsoft Project (cont.)

Trang 45

Microsoft Project (cont.)

Trang 46

Microsoft Project (cont.)

Trang 47

Microsoft Project (cont.)

Trang 48

PERT Analysis with

Microsoft Project

Trang 49

PERT Analysis with

Microsoft Project (cont.)

Trang 50

PERT Analysis with

Microsoft Project (cont.)

Trang 53

Normal Time and Cost

vs Crash Time and Cost

Slope = crash cost per week

Trang 54

Project Crashing: Example

TOTAL

Trang 55

12

2 8

3

4

6 4

7 4

3

4

6 4

7 4

Trang 56

 Crashing costs increase as project

duration decreases

 Indirect costs increase as project

duration increases

 Reduce project length as long as

crashing costs are less than indirect

costs

Time-Cost Relationship

Trang 57

Minimum cost = optimal project time

Total project cost Indirect cost

Direct cost

Trang 58

Copyright 2009 John Wiley & Sons, Inc 9-58

Copyright 2009 John Wiley & Sons, Inc.

All rights reserved Reproduction or translation

of this work beyond that permitted in section 117

of the 1976 United States Copyright Act without express permission of the copyright owner is

unlawful Request for further information should

be addressed to the Permission Department,

John Wiley & Sons, Inc The purchaser may

make back-up copies for his/her own use only

and not for distribution or resale The Publisher assumes no responsibility for errors, omissions,

or damages caused by the use of these

programs or from the use of the information

Ngày đăng: 15/05/2017, 09:32

TỪ KHÓA LIÊN QUAN