As production goals in manufacturing activities to be taken into consideration in this study, three production goals in terms of the production time or production rate, the production
Trang 1most advanced technological means to photograph and reproduce this document
have been used, the quality is heavily dependent upon the quality of the material
submitted.
The following explanation of techniques is provided to help you understand
markings or notations which may appear on this reproduction.
1.T h e sign or “target” for pages apparently lacking from the document
photographed is “ Missing Page(s)” If it was possible to obtain the missing
page(s) or section, they are spliced into the film along with adjacent pages
This may have necessitated cutting through an image and duplicating
adjacent pages to assure you o f complete continuity.
2 When an image on the film is obliterated with a round black mark it is an
indication that the film inspector noticed either blurred copy because of
movement during exposure, or duplicate copy Unless we meant to delete
image of the page in the adjacent frame If copyrighted materials were
deleted you will find a target note listing the pages in the adjacent frame.
3 When a map, drawing or chart, etc., is part of the material being photo
graphed the photographer has followed a definite method in “sectioning”
the material It is customary to begin filming at the upper left hand corner of
a large sheet and to continue from left to right in equal sections with small
overlaps If necessary, sectioning is continued again—beginning below the
first row and continuing on until complete.
4 For any illustrations that cannot be reproduced satisfactorily by xerography,
photographic prints can be purchased at additional cost and tipped into your
xerographic copy Requests can be made to our Dissertations Customer
Services Department.
5 Some pages in any document may have indistinct print In all cases we have
filmed the best available copy.
University Microfilms International
300 N ZEEB RD ANN ARBOR Ml 48106
Trang 3MULTIOBJECnVE OPTIMIZATION OF MANUFACTURING SYSTEMS
The Pennsylvania Stale University Ph.D 1982
University
Microfilms
International 300 N Zeeb Road, Ann Arbor, MI 48106
Trang 51 Glossy photographs or pages
2 Colored illustrations, paper or print _
3 Photographs with dark background
4 Illustrations are poor copy
5 Pages with black marks, not original copy
6 Print shows through as there is text on both sides of page
7 Indistinct, broken or small print on several pages ^
8 Print exceeds margin requirements
9 Tightly bound copy with print lost in spine
10 Computer printout pages with indistinct print
11 Page(s) lacking when material received, and not available from school or
author.
12 Page(s) seem to be missing in numbering only as text follows.
13 Two pages numbered _ Text follows.
14 Curling and wrinkled pages
15 Other _
University Microfilms International
Trang 7Multiobjective Optimization of Manufacturing Systems
Doctor of Philosophy
March 1982
© 1982 by Souemon Takakuwa
I grant The Pennsylvania State University the nonexclusive
right to use this work for the University's own purposes and
a non-for-profit basis if copies are not otherwise available,
Souemon Takakuwa
Trang 8Date of Signature:
/ * / 2 / sy
h )
rofessor of gineering, Chairman
of Committee, Thesis Adviser
Allen L Soyster, Proffessor of Industrial Engineering, Head of the Department of Industrial and Management Systems Engineering
William E Biles, Professor of Industrial Engineering
frYYlXj P. v2.
/ CkYYljU
-Barnes P Ignizio, Industrial Engineering
Kochenberger, Professor of Management Science
Trang 9objective optimization, optimization analyses of manufacturing systems
are made First, single-product, single-stage manufacturing systems
are treated and analyzed Then, the discussion is extended to multi
product manufacturing systems, and finally to multi-stage manufactur
ing systems.
As production goals in manufacturing activities to be taken into
consideration in this study, three production goals in terms of the
production time or production rate, the production cost, and the
profit rate are introduced and utilized for multiobjective optimiza
tion Through the study, nonlinear goal programming is mainly applied
to multiobjective optimization of machining conditions because of its
suitability and flexibility for application to problems considered in
this study.
In optimization analyses of single-product, single-stage manu
facturing systems, the nondominated solution sets for both uncon
strained and constrained optimization are examined In unconstrained
optimization, characteristics and sensitivity of functions of perform
ance measures are discussed, and the concept of optimal machining
speeds under multiple objectives is introduced Also, multiobjective
optimization of both machining speed and feed rate is considered.
In optimization analyses of multi-product, single-stage manufactur
ing systems, first, optimizing machining speeds under fundamental
evaluation criteria is examined Then, multiobjective optimization of
the machining condition on manufacturing systems under a GT environment
Trang 10proposed for obtaining a multiobjective optimal machining condition.
In optimizing analyses of multi-stage manufacturing systems, a
basic nonlinear multiobjective (goal-programming) model for the flow-
type multi-stage manufacturing system is built and analyzed in an
attempt to determine optimal machining conditions to be set on pro
duction stages.
Some modification of the nonlinear goal programm ing via pattern
search is made, particularly in exploratory moves for obtaining
multiobjective optimal solutions.
Trang 11LIST OF TABLES viii
LIST OF F I G U R E S ix
LIST OF S Y M B O L S xi
ACKNOWLEDGEMENTS xv
CHAPTER 1: GENERAL INTRODUCTION 1
1.1 Introduction 1
1.2 Previous Related Studies 2
1.3 Outline of T h e s i s 4
CHAPTER 2: MANUFACTURING S Y S T E M S 6
2.1 Manufacturing Systems - Functions and Procedures 6
2.2 Basic Mathematical Models of Manufacturing Systems 10
2.2.1 Basic mathematical models of manufacturing systems 10
2.2.1.1 Unit production time 10
2.2.1.2 Production rate 11
2.2.1.3 Unit production cost 11
2.2.1.4 Unit p r o f i t 12
2.2.1.5 Profit r a t e 13
2.2.2 Manufacturing models as a function of machining speed 13
2.2.3 Manufacturing models as a function of machining speed and feed rate 15
2.3 Production Goals in Manufacturing Activities 16
2.3.1 Three fundamental evaluation criteria 16
2.3.1.1 Maximum-production-rate or minimum-time criterion 17
2.3.1.2 Minimum-cost criterion 17
2.3.1.3 Maximum-profit-rate criterion 17
2.3.2 Aspiration levels on production goals 18
CHAPTER 3: OPTIMIZATION OF SINGLE-PRODUCT, SINGLE-STAGE MANUFACTURING SYSTEMS 19
3.1 Determining Optimal Machining Speeds - Unconstrained O p t i m i z a t i o n 19
3.1.1 Characteristics of functions of performance m e a s u r e s 19
3.1.1.1 Unit production time 19
3.1.1.2 Unit production cost 20
3.1.1.3 Profit 20
3.1.1.4 Profit r a t e 20
3.1.2 Optimal machining speeds under fundamental evaluation criteria 21
Trang 12o b j e c t i v e s 27
3.1.4 Sensitivity of single-stage manufacturing systems 32
3.2 Determining Optimal Machining Speeds and Feed Rates -Constrained Optimization 33
3.2.1 Introduction 33
3.2.2 Basic measures of p e r f o r m a n c e 43
3.2.3 The nondominated solution s e t 50
3.2.4 Nonlinear multiobjective (goal-programming) m o d e l 55
3.2.5 Applicability of nonlinear goal programming for the multiobjective optimization of manufacturing systems 58
3.3 C o n c l u s i o n s 64
CHAPTER 4: OPTIMIZATION OF MULTI-PRODUCT, SINGLE-STAGE MANUFACTURING SYSTEMS 65
4.1 Multi-Product, Single-Stage Manufacturing Systems 65
4.1.1 Introduction 65
4.1.2 Optimal machining speeds under fundamental evaluation criteria 65
4.2 Determining Optimal Machining Speeds - Unconstrained Optimization of Manufacturing Systems Under a GT Environment 72
4.2.1 Introduction 72
4.2.2 Problem d e f i n e d 72
4.2.3 Basic mathematical models 73
4.2.3.1 Job production t i m e 73
4.2.3.2 Group production time 74
4.2.3.3 Total production time 74
4.2.3.4 Unit production cost 74
4.2.3.5 Group production cost 74
4 2 3 6 Total production cost 75
4.2.3.7 Profit * 75
4 2 3 8 Profit r a t e 75
4.2.4 Nonlinear multiobjective (goal-programmin g) m o d e l 75
4.2.4.1 Baseline m o d e l 75
4.2.4.2 Nonlinear goal-programming m o d e l 77
4.2.5 Numerical examples and consideration 80
4.3 Determining Optimal Machining Speeds and Feed Rates -Constrained Optimization of Manufacturing Systems Under a GT E n v i r o n m e n t 91
4.3.1 Introduction 91
4.3.2 Problem d e f i n e d 92
4.3.3 Algorithmic procedure for determining optimal machining speeds and feed rates 93
4.3.3.1 Determining optimal feed rates and machining-speed range (Phase I ) 93
Trang 135.1 Introduction 105
5.2 Assumptions for Analysis of Multi-Stage Manufacturing Systems 106
5.3 Determining Optimal Machining Speeds - Unconstrained Optimization 107
5.3.1 Basic mathematical m o d e l s 107
5.3.1.1 Stage production time 107
5.3.1.2 Cycle time and waiting t i m e 107
5.3.1.3 Stage production cost 108
5.3.1.4 Total production cost 109
5.3.1.5 Profit 110
5.3.1.6 Profit r a t e 110
5.3.2 Manufacturing models as a function of machining c o n d i t i o n s 110
5.3.3 Determining bottleneck stage and machining-speed r ange 112
5.3.4 Some considerations of the multi-stage manu facturing system 115
5.3.4.1 Optimization under the minimum-cycle-time criterion 115
5.3.4.2 Production cost 118
5.3.5 Nonlinear multiobjective (goal-programming) m o d e l
5.3.5.1 Baseline m o d e l 119
5.3.5.2 Nonlinear goal-programming m odel 122
5.3.6 Numerical example and consideration 124
5.4 C o n c l u s i o n s 135
CHAPTER 6 : C O N C L U S I O N S 137
6.1 Summary and C o n c l u s i o n s 137
6.2 Suggestions for Future R e s e a r c h 139
APPENDIX A: NONLINEAR GOAL PROGRAMMING VIA PATTERN SEARCH 141
A 1 N L G P / P S 141
A 2 NLGP/PS-M1 and N L G P / P S - M 2 143
A 3 Considerations 144
APPENDIX B : COMPUTER CODES F OR MULTIOBJECTIVE OPTIMIZATION OF MANUFACTURING S Y S T E M S 147
REFERENCES 165
Trang 14Table Page
3.1 Basic Data for Numerical Computation of Machining
Speeds for the Single-Stage Manufacturing System 23
3.2 Basic Data for Numerical Computation of
S e n s i t i v i t y 34
3.3 Impact of Changes of Time and Cost Parameters on
Optimal Machining Speeds Under Three Kinds of Evaluation Criteria 42
3.4 Basic Data for Numerical Computation of Machining
Speeds and Feed Rates for the Single-Stage Manufacturing System 45
4.1 Basic Data for Numerical Computation of Example 4.1 69
4.2 Basic Data for Unconstrained Optimization of a
4.3 Basic Data for Constrained Optimization of a
5.1 Basic Data for Optimization of a Four-Stage
Manufacturing System 125
A.l CPU Times Required for Solving Numerical Examples 145
Trang 152.2 Block Diagram of Process Planning Stage 8
2.3 General Flowchart of Optimization of Machining Conuitions 9
3.1 Unit Production Cost, Unit Production Time, and Profit Rate Versus Machining Speed 24
3.2 Functions of Performance Measures and Their Derivatives in the High-Efficiency Speed Range 26
3.3 Speed Range Satisfying Priority 1 in Example 3.1 28
3.4 Speed Range Satisfying Priorities 1 and 2 in Example 3 1 29
3.5 The Multiobjective Optimal Solution in Example 3.1 30
3.6(a) Change in t£ (tool-replacement time, min/edge) 35
3.6(b) Change in tp (preparation time, min/pc) 37
3.6(c) Change in k, (direct labor cost and overhead, $/min) 38
3.6(d) Change in km (machining overhead, $/min) 39
3.6(e) Change in k £ (tool cost, $/edge) 40
3.6(f) Change in r^ (gross revenue, $/pc) 41
3.7(a) Contours of the Unit Production Time and V-Minimum L i n e 46
3.7(b) Contours of the Production Rate and V-Maximum Line 47
3.7(c) Contours of the Unit Production Cost and V-Minimum L i n e 48
3.7(d) Contours of the Profit Rate and V-Maximum Line 49
3.8 The Optimal Region for Absolute Objectives 52
3.9(a) The Nondominated Solution Set (a) 53
3.9(b) The Nondominated Solution Set (b) 54
Trang 16Figure Page
3.10 Graphical Presentation of a Nonlinear Multi
objective M o d e l 56
3.11 Optimal Solution of Example 3 3 62
4.1 Profit Rate in Two-Product Manufacturing 71
4.2 Optimal Machining Speeds Under Achievement Functions
in Terms of Different Sets of Weighting Factors (Sj and W 2 ) 86
4.3 Three Performance Measures Under Achievement
Functions in Terms of Different Sets of Weighting Factors (W^ and W ^ 87
4.4 Computational Process of Phase I in Example 4.3 100
5.1 Schematic Model of a Flow-Type Multi-Stage
Manufacturing System 106
5.2 Relationships Among Machining Speed, Stage Produc
tion Cost, and Cycle Tim e 116
5.3 Stage Production Cost 120
5.4 Computational Process of Machining-Speed Ranges 127
5.5 Optimal Machining Speeds at Corresponding Cycle
T i m e 132
5.6 Total Production Cost and Profit Rate at
Corresponding Cycle Time 133
Trang 17k^ = overhead cost ($/min)
k^ = direct labor and overhead cost ($/min)
km = overhead cost during machining ($/min)
k t = tool cost per cutting edge ($/edge)
K = stage number governing the cycle time; used as subscript
K' = stage number having the longest stage production time at v ^
N
= Z = total direct l^.bor and overhead cost for N-stage manufactur-
J =1 ing system ($/min)
Simplified notation and nomenclature in Appendix A not included.
Trang 181 = additional feed length (mm)
1 = lot size of J (pcs/lot)
N = total number of jobs to be processed
= number of jobs in group i
P = profit rate or profit per unit time interval ($/min)
P = positive deviation from desired performance level in goal-
programming model
P = profit rate ($/min) (Chapts 4 and 5)
P = motor power (W)
P^ = sum of total job production time of G (min)
P „ = total job production time of J „ (min/lot)
q = production rate (pc/min)
= group production time of (min)
R = nose radius of cutting tool (mm)
R = surface roughness goal (y)
r = r - m = unit revenue minus material cost ($/pc)
r^ = unit revenue ($/pc)
r^, = total revenue per unit time interval ($/min)
s = feed rate (mm/rev)
= group set-up time for G^ (min)
S _ = set-up time for (min/lot)
Trang 19Ce = tool-replacement time (min/pc)
t = machining time (min/pc)
t = preparation time (min/pc)
Cw = waiting time (min/pc)
t CT = cycle time (min/pc)
(c)
t = unit production time at the minimum-cost machining speed (min/pc)
t ^ = unit production time at the maximum-production-rate m a c h i n i n g
speed (min/pc)
T = total production time (min) (Chapt 4)
T = tool life (min/edge)
u^, = total production cost per unit time interval ($/min)
U = total production cost ($) (Chapt 4)
UT = total production cost ($) (Chapt 5)
(c)
v = minimum-cost machining speed (m/min)
(e)
v - a high-efficiency machining speed (m/min)
v ^ = maximum-profit-rate machining speed (m/min)
v ^ = maximum-production-rate machining speed or minimum-time machining speed (m/min)
= group production cost for ($)
Trang 20a = constant in power function
3 = constant in power function
A = constant dependent on work size and machining conditions
Aq = machining constant
E = sum in regard to J from 1 to N, exclusive of K
J^K
Trang 21Appreciation is also expressed to the other members of his
doctoral committee, composed of Drs J P Ignizio, C D Pegden,
W E Biles, and G A Kochenberger.
Finally, the author would like to express gratitude to Dr K
Hitomi for his continuous encouragement.
Trang 22GENERAL INTRODUCTION
1.1 Introduction
The optimization analysis of manufacturing systems has been
studied for the past few decades In the field of economics of
machining, the machining, as run by a single tool (i.e., single-stage
manufacturing), has been discussed frequently Optimal machining
conditions, particularly optimal machining speed, have been analyzed
from the standpoint of the minimum-cost criterion (1), the maximum-
production-rate criterion or minimum-time criterion (1), and the
maximum-profit-rate criterion (2,3) ln practice, however, there
exist various constraints: i.e., feed-rate constraints,
machining-speed constraints, power constraints, rouehness constraints, and so on.
Recent developments in material-removal technology relying upon
computers have resulted in the advancement of machining information
systems which provide effective information, particularly, optimal
machining conditions for a certain criterion such as those mentioned
earlier.
Ideally, optimization should be applied to a total manufacturing
system, such as material fabrication, part-machining, product assembly,
and so on In this study, however, optimization for part-machining is
to be made for both single-stage and multi-stage manufacturing systems
Practically, 'machining' is a complex physical phenomenon; hence, a
simplified mathematical model should be constructed for the optimiza
tion analysis of machining conditions.
For mathematical optimization analysis, there are unconstrained
optimization and constrained optimization The typical controllable
Trang 23depth of cut Depth of cut can often be determined by the sizes of
the work material and the products; hence, in this research, it is
assumed constant Therefore, setting a fixed value for feed rate,
optimal machining speed will be determined in unconstrained problems.
In constrained optimization, in addition to optimal machining speed,
optimal feed rate is simultaneously determined.
The purpose of this research is to develop basic non-linear
multiobjective (goal-programming) models and make analyses for various
types of manufacturing systems Optimal machining conditions,
especially optimal machining speeds and/or feed rates, are analyzed
under multicriteria achievement functions.
1.2 Previous Related Studies
The optimization analysis of machining speeds on a single-stage
manufacturing system has been studied since Gilbert's first work (1),
in which the "maximum production rate" and the "minimum production
cost" criteria were introduced Computerized optimization and analyses
have been made by Ham (4) and Field et al (5,6) Okushima and Hitomi
(2 ) proposed a new criterion for manufacturing, i.e., "maximum profit"
in a limited time interval, which was named the "maximum profit rate"
by Armarego and Russel (3) Later, this analysis was made by Wu and
Ermer (7) and Hitomi (8 ).
On the single-objective constrained optimization, several
approaches, such as Lagrange multipliers (9) and geometric programming
(10), have been proposed Little research on the multiobjective
optimization has been done, even in a single-stage manufacturing system
The surrogate worth trade-off method (SOT Method) has been applied to
Trang 24multiobjective optimization of machining conditions (11) Linear goal
programming has been formulated and analyzed by taking logarithms of
goals and constraints (12, 13) In these papers, however, the multiple
production goals are not considered simultaneously Also, nonlinear
goal programming has been applied to multiobjective optimization for a
single-stage manufacturing system (14).
Recently, in the manufacturing area the concept of Group Technology
(GT) has been introduced and has become widely used in real-life
workshops Group technology is generally considered to be a manufac
turing philosophy or concept which identifies and exploits the sameness
or similarity of parts and operation processes in design and manufacture
In batch-type manufacturing, by grouping similar parts into part
families, based on their geometrical shapes or operation process and
also by forming machine groups or cells which process the designated
part families, it should be possible to reduce various costs (15).
From the GT standpoint, the production scheduling problem, i.e.,
"Group Scheduling", has been investigated, and several optimizing
algorithms for determining both the optimal group sequence and the
optimal job sequence (in each group) have been developed under
scheduling criteria, such as minimizing the total flow time and
minimizing the total tardiness (16, 17, 18, 19, 20, 21, 22) The
machine loading and product-mix problems under a GT environment have
been also discussed In this problem, the optimal kinds of products
(parts or jobs) to be produced within a limited time available and
the optimal machining speeds for all products are determined so as to
maximize the production amount for a given period of time (23, 24).
Trang 25or product is rarely done in a single-stage manufacturing; rather, it
is usually completed by being processed successively on several machine
tools or w ork stations that constitute a multi-stage manufacturing
system Single-objective optimization for multi-stage manufacturing
systems has been analyzed (25, 26, 27, 28).
1.3 Outline of Thesis
In Chapter 2, first, functions and procedures of manufacturing
systems and the general procedure to obtain optimal machining condi
tions are discussed Second, in order to analyze manufacturing
systems, basic mathematical models expressing production goals are
constructed, with manufacturing models expressed as a function of
machining conditions Third, production goals in manufacturing activ
ities are defined in terms of the production time, production cost,
and profit rate These production goals might constitute integrated
production goals to be optimized in the chapters which follow.
In Chaper 3, optimization analysis of single-product, single-
stage manufacturing systems is made In unconstrained optimization,
characteristics and sensitivity of functions of performance measures
are discussed, and the concept of optimal machining speeds under
multiple objectives is introduced Next, in constrained optimiza
tion, which is made considering various system constraints, the
nondominated solutions set is discussed Then, the nonlinear multi
objective model is formulated and analyzed via goal programming.
There are several approaches to the problems with multiple objectives
(29) In this thesis, nonlinear goal programming (30) is mainly
Trang 26applied to multiobjective optimization of machining conditions because
of its suitability and flexibility for application to problems
considered in this study.
In Chapter 4, optimization analysis of multi-product, single-
stage manufacturing systems is made First, optimizing machining
speeds under fundamental evaluation criteria on multi-product manu
facturing systems is discussed Next, multiobjective optimization
of the machining condition on manufacturing systems under the GT
environment is treated in both unconstrained and constrained cases
Also, the relationships among production goals are discussed in
multiobjective optimization.
In Chapter 5, optimization analysis of multi-stage manufacturing
system is made A basic nonlinear multiobjective (goal-programming)
model for the flow-type multi-stage manufacturing system iz built
and analyzed in an attempt to determine optimal machining conditions
to be set on production stages Based upon the multiple production
goals on the cycle time (production time), the total production cost,
and the profit rate, the optimal machining speeds to be set on pro
duction stages and the cycle time for the multi-stage manufacturing
system are analyzed, and the computational procedure for obtaining
them is developed.
Trang 27The procedure of manufacturing (i.e., production of material goods)
can be divided into the product design stage, the process planning
stage, and the production implementation stage, as shown in Figure
2.1 In the product design stage* technical specifications of the
products to meet the market needs are decided through research and
development (R and D) activities; then, the product design is com
pleted Next, in the process planning stage, an optimal process route
is decided, and machines, tools, and jigs to be used are selected,
together with optimum decisions for an operation sequence and machin
ing conditions In the implementation stage, raw materials are
acquired, parts are machined, and then the products required are
assembled and inspected Finally, the finished products are shipped
and distributed to the market or the customers This production pro
cedure is known as IMS (integrated manufacturing system).
Figure 2.2 shows the relationship between decision making and
associated information in the process planning stage (32) Through
out the research, the discussion is focused on optimizing machining
conditions in this phase.
The general procedure for obtaining optimal machining conditions
is shown in Figure 2.3 The machinability data files store data for
material-removal operations, ■work materials, cutting tools, jigs,
machine tools, machining conditions, and so on On receiving input
information concerning the type of material-removal operation, work
materials, cutting and machine tools, and machining situations,
Trang 28a DET E R M I N I N G MA C H I N I N G CON DI T I O N S
o M A T E R I A L A C Q U I S I T I O N
< ^ PAR T F AB RICAT ION
z PR O D U C T AS S E M B L Yz
INSPECTI ON
PR O D U C T S HI PMENT
Figure 2.1 Functions of Integrated Manufacturing Systems (IMS) (31)
Trang 29Figure 2.2 Block Diagram of Process Planning Stage
Trang 30M O D E LSUR FACE
Trang 31ing models are mathematical models which represent the relationships
between machining conditions and variables expressing machinability,
such as tool life, surface finish, accuracy, machining power, and
others Based on those models and by the use of the machine tool,
cutting tool, and time and cost files, the optimizing processing is
performed to obtain the optimal machining conditions against produc
tion goals, which will be defined later.
2.2 Basic Mathematical Models of Manufacturing Systems
2.2.1 Basic mathematical models of manufacturing systems
Basic mathematical models expressing production goals are to be
constructed for the purpose of analyzing manufacturing systems For
simplicity, the case of the single-product, single-stage manufactur
ing systems is treated.
Basic mathematical models are constructed as follows (31).
2.2.1.1 Unit production time The unit production time is
the time needed to manufacture a unit of a product It is generally
assumed that unit production time is comprised of the following three
time elements:
(a) Preparation (or setup) time tp (min/pc): time necessary
to prepare for machining This includes the loading time
of work materials to a machine tool, the approach time of
a cutting tool to the workpiece, etc.
(b) Machining time tffl (min/pc): time necessary to manipulate
the machine tool for cutting.
(c) Tool-replacement time tg (min/pc): time required to
Trang 32Denoting the time required to replace a worn cutting tool, t^,
with a new variable, tfi (min/edge), and the tool life (which is the
time length from the beginning of using a new edge until its replace
ment) , by T (min/edge), the too1-replacement time per unit piece is:
Accordingly, the unit production time, t (min/pc), is repre
sented by:
2.2.1.2 Production r at e The production rate is the number
of pieces produced per unit time, and is the reciprocal of the unit
production time given by equation (2.2), hence, denoting the produc
tion rate by q (pc/min) as:
(2.3)
2.2.1.3 Unit production cost The unit production cost is a
cost required to manufacture a unit piece This cost consists of the
following six cost elements:
(a) Material cost mc ($/pc): cost of raw material per unit
piece produced.
Preparation (or
preparation time.
Trang 33(d) Tool-replacement cost ug ($/pc) : cost of the
tool-replacement time.
(e) Tool cost ($/pc): cost of cutting edge required to
produce a unit product This includes purchasing and
depreciation cost of the tool and grinding wheel, direct
labor and overhead costs for grinding worn cutting edges,
etc.
(f) Overhead cost u^ ($/pc) : indirect cost necessary to
produce a unit product This includes depreciation cost
for machine tools, general administration expenses, etc.
The unit production cost, u ($/pc), is thus expressed by:
- k t — + k —
(2.4)
k l ^=kd + k i^ (S/™-11) = direct labor and overhead
km ($/min) = machining cost
2.2.1.4 Unit profit The profit is obtained by producing a
unit product The gross profit per unit piece produced, g ($/pc), is
the unit revenue or selling price, r^ ($/pc), minus the unit produc
tion cost of u ($/pc):
Trang 34(2.5) T
2.2.1.5 Profit rate The profit rate, p ($/min), is obtained
by multiplying the unit profit, g ($/.pc) by the production rate, q
(pc/min):
g r - m + k.t + (k, + k )t -
6 u L c l p 1 m m : gq = _ = -K -
2.2.2 Manufacturing models as a function of machining speed
In this case, machining speed is chosen as a representative
decision variable among three machining variables (i.e., machining
speed, feed rate, and depth of cut) An analysis is developed to
determine the optimal machining speed to be utilized on the machine
tool used For this purpose, basic mathematical models, especially
unit production time (equation (2.2)) or production rate (equation
(2.3)), unit production cost (equation (2.4)), and profit rate
(equation (2.6)), are to be expressed as a function of machining speed
The tool-life value, T (min/edge), and the machining time, tm (min/
p c ) , are the only factors in the basic models which vary with change
where X is a machining constant, and is determined, depending upon
machining patterns, as follows:
(a) For turning, boring, drilling, and reaming operations,
Trang 35(b) For a milling operation,
= length of the hole to be machined (mm) for boring,
drilling, and reaming operations.
1 = additional feed length (mm) for a milling operation,
s = feed rate per tooth (mm/tooth) for a milling operation.
= feed rate per revolution (mm/rev) for other
operations.
Z = number of teeth of the milling cutter.
The relationship between tool life and machining conditions is
expressed by the tool-life equation The most typical model is the
Taylor tool-life equation (34), which shows the relationship between
tool life, T (min/edge), and machining speed, v (m/min), as follows:
where n and C are constants: n, slope of Taylor tool-life curve with
regard to machining speed, in general, between 0 and 1, usually 0.1 ^
0.4; and C, 1-min tool-life machining speed, both depending upon kinds
of cutting tools used and work material to be machined (with or
Trang 36out cutting fluids), machine tools used, other machining conditions,
and so on.
Substituting tffl and T, expressed as a function of v given by
equations (2.7) and (2.10), into equations (2.2), (2.4), and (2.6),
unit production time and cost, and profit rate are expressed as a
In this case, optimal machining speed and optimal feed rate are
to be determined Therefore, a basic mathematical model for a single-
stage manufacturing system is constructed as a function of machining
speed and feed rate.
The basic three measures of performance are expressed in general
form as in equations (2.2), (2.4), and (2.6) In these formulae, the
tool life, T (min/edge), and the machining time, t^ (min/pc), are
dependent upon feed rate, s (mm/rev), and machining speed, v (m/min)
As to T, the following generalized tool-life equation is employed:
Trang 37where mg, n^, and Cq are constants tffi is expressed as a function
of s and v as follows, similar to equation (2.7):
X0
where Ag is a machining constant.
Substituting equations (2.14) and (2.15) into equations
(2.2), (2.4), and (2.6), unit production time and cost, and profit
rate are expressed as:
Unit production time:
2.3 Production Goals in Manufacturing Activities
2.3.1 Three fundamental evaluation criteria
The following three fundamental evaluation criteria are utilized
in the traditional single-objective manufacturing optimization (31).
Trang 382.3•1.1 Maximum-production-rate or minimum-time criterion.
The maximum-production-rate or minimum-time criterion maximizes
the amount of products produced in a unit time interval; hence, it
minimizes the production time per unit piece It is the criterion to
be adopted when an increase in physical productivity or productivity
efficiency is desired, neglecting the production cost needed and/or
profit obtained The objective is expressed as:
2.3.1.2 Minimum-cost criterion The minimum-cost criterion
refers to producing a piece of product at the least cost, and coincides
with the maximum-profit criterion if the unit revenue is constant.
This criterion is to be adopted when there is ample time for produc
tion The objective is expressed as:
2.3.1.3 Maximum-profit-rate criterion The maximum-profit-
rate criterion maximizes the profit in a given time interval This
criterion is to be recommended when there is insufficient capacity for
a specific time interval "Profit rate" usually means "return on
investment" in the field of economics and engineering economy In the
evaluation criteria for economical production, "profit rate" means
"profit per unit time interval." Where market demands are large com
pared to the productive capacity, a larger total profit is obtained
by producing and selling a large amount of products as a result of
reducing unit production time associated with sacrificing unit pro
duction cost, rather than based upon the minimum-cost criterion The
objective is expressed as:
Trang 392.3.2 Aspiration levels on production goals
Depending upon the objectives of the decision maker, the pro
duction goals may be set to achieve some levels (aspiration levels)
on the production rate (or the production time), the production cost,
and/or the profit rate In such cases, the production objectives are
expressed in aspiration-level goals (35):
The production goals are employed according to the manufacturing
objectives An optimal selection from among them should be done from
2 the managerial standpoint.
inequalities (2.24) to (2.27) are represented as three major
production goals in the baseline model of goal-programming formulation 2
Methods on priority-selection from among production goals will
not be discussed in this study For priority structure, several
references are available, for example, (36).
Trang 40OPTIMIZATION OF SINGLE-PRODUCT, SINGLE-STAGE MANUFACTURING SYSTEMS
3 *1 Determining Optimal Machining Speeds - Unconstrained Optimization
3.1.1 Characteristics of functions of performance measures
Optimization analysis of the single-stage manufacturing system
is fundamental to the optimization of the integrated manufacturing
systems.
It is necessary, first, to examine the characteristics of
functions of performance measures, i.e., the unit production time (or
the production rate), the unit production cost, and the profit rate
Basic mathematical models of these performance measures as a function
of machining speed have been constructed as equations (2.2), (2.4),
and (2.6) In this section, some simplified notation is used for
simplicity of discussion.1
Definition 3 1: A controllable continuous variable which
specifies the production time and cost is the machining speed, and
it is denoted by v v is feasible if 0 < v < ®.
3.1.1.1 Unit production time The time function consists of
a fixed time and variable (inversely and positively proportional)
time elements, and can be expressed simply as
where a, b, c, and n _> 1 are positive constants.
Property 3 1 ; The time function t(v) is a positive, unimodal
twice-differentiable, and strictly convex function.
1 For a more detailed discussion, see reference (37).