GENERAL SPECIFICATIONS 2.1 Materials requiring paint 2.1.1 Ductile iron and Malleable Iron 2.1.2 Carbon and low alloy steel 2.2 Materials which shall not be painted 2.2.1 Stainle

Trang 1

INSTRUCTION OF PAINTING

PROJECT : DINH VU POLYESTER PLANT PROJECT

LOCATION : DVIZ, HAI PHONG CITY, VIETNAM

CONTRACT : PVTEX., JSC

PO NO : 09035-00-PPO-PI022

VENDOR DATA STATUS

□ 1 : APPROVED SUBMIT FINAL

□ 2 : APPROVED WITH COMMENTS

SUBMIT CORRECTED FINAL

□ 3 : NOT APPROVED

(REVISE AND RESUBMIT)

□ 4 : APPROVAL NOT REQUIRED INFORMATION ONLY REVIEW DATE:

Document Class:

1 APR.19.2010 Issued For Approval J.K.PARK Y.J.CHO S.P.CHOI

0 MAR.22.2010 Issued For Approval J.K.PARK Y.J.CHO S.P.CHOI

As-Built

Trang 2

1 PURPOSE AND SCOPE

This instruction defines the requirements for painting standard of product line valves, and related equipment When a special painting is specified in contract, follow the customer's requirements

2 GENERAL SPECIFICATIONS

2.1 Materials requiring paint

2.1.1 Ductile iron and Malleable Iron

2.1.2 Carbon and low alloy steel

2.2 Materials which shall not be painted

2.2.1 Stainless Steels

2.2.2 Corrosion-resistant alloys such as Monel, Nickel, Inconel, Hastelloy, Alloy 20,

and other non ferrous materials

3 PAINT REQUIREMENT BY PRODUCT LINE

3.1 Sleeved plug valves

Classification Surface

Preparation

Full System Primer Undercoat

Finishing Coats Remark

Paint Type

SSPC-SP10 (Sa2-1/2)

Two pack Zinc Rich Epoxy Primer

Two pack Micaceous Iron Oxide Pigmented

Epoxy

Two pack Acrylic Modified Polyurethane

- Nominal Dry-Film

(RAL 9006)

2 APR.17.2010 For Approval J.S.Bae C.H.KOOK Y.D.Park

1 MAR,23,2010 FOR Approval J.S.Bae C.G.Lim Y.D.Park

0 JAN,07,2009 FIRST ISSUE Y.K.NAM K.J.HONG C.G.LIM

REV No ISSUED DESCRIPTIONS PREPARED CHECKED APPROVED

Trang 3

3.2 Accessories & Individual Parts (Handles, Brackets, etc)

Classification Surface

Preparation 1

st

Coat 2 nd Coat Remark

Paint Type

SSPC-SP10 (Sa2-1/2)

Epoxy Polyamide Acrylic Polyurethane

- Nominal Dry-Film

4 PROCEDURE OF PAINTING PROCESS

4.1 Paintings shall be applied for a good even coat, fully covering all surfaces with no paint voids, transparencies or misses

4.2 Paints shall prepared and mixed for application as per manufacturer's instructions, and

all applicable safety and health precautions shall be observed

4.3 All parts and products painted as per requirements of this Instruction nominally shall be

air-dried; no heat-drying shall be used unless prior Engineering Approval for such heat drying method is obtained

4.4 All surfaces to be painted must be dry and free of foreign material and other surface contaminants such as rust oxide, dirt, grease, water, and loose scale that may cause poor paint adhesion

4.5 Serrated flange facing should not have paint runs or be painted thick for interfere with the ability of the flange serrations to form a pressure seal with gasket when bolted into the pipe line

4.6 Interior waterway surfaces should be given a thin coating for rust protection by antirust agent while in storage (Check special instruction as to whether the customer desires other type of rust preventative in this area.)

4.7 Painting shall be performed in accordance with guidance of paint manufacturers, and painting general conditions are as follows

Trang 4

4.8.1 Temperatures

1) The optimum coating temperature : 15 ~ 32℃

※ Typically, paint coating shall not perform at 10℃ or below and 38℃ or higher

2) During painting for prevention of surface condensation, the substrate temperature is

3℃ higher than dew paint

4.8.2 Humidity

Humidity condensation a harmful influence upon paint drying time, therefore coating

shall be performed at 40 ~ 80% humidity

4.8.3 Others

Painting outdoor shall not be performed in foggy, rainy and stormy days

4.9 Painting correction shall be performed in the touch-up method If surface to be painted has broad damaged paint coat, coat the surface in accordance with the first time paint coating procedure

4.10 Painted valves shall be dried before being packed

4.11 Paint may be applied by any conventional process such as hand spray gun, etc., providing good quality coating is obtained Brushes may be used for touch-up and corrections

Ngày đăng: 07/03/2017, 08:50