Training Design of Vertical Roller Mill Polysius Headquarters Germany Raw material preparation Roller mill RM 6629555 – THALOFA Roller mill RM 6629555 – BAZIFA Schematic movement of material on the grinding table Doublegroove grinding system Roller mill feed shute with preseparation Mill housing Roller pairs
Trang 1Design of Vertical Roller Mill
Training
Polysius Headquarters / Germany
19 May – 13 June 2008
Trang 2Raw
material-preparation
Cement- production
Trang 3Raw Material (Mixture) Raw Meal
THALOFA raw mixture
Trang 4Hot gas Return air
Exhaust gas
Mixed gas before mill
Roller mill RM 66/29-555 – THALOFA
Trang 5 High drying capacity
Grinding, drying and separating in only one unit
Compact arrangement
Low energy requirement
Proven wear protection
Does not necessarily need
a proper mill building
Roller mill RM 66/29-555 – BAZIFA
Trang 6 Tie rods & hydraulic system
Mill main drive & auxiliary drive
SEPOL Separator
Water injection
Roller pair dismounting device
Roller Mill Assemblies
Roller mill RM 66/29-555 – BAZIFA
Trang 7Capacity: 500 t/h raw material
at 12% R 90µm
Initial moisture content: max 8.0%
External material circuit:
100% of nominal mill output
Mill fan sizing: 1,000,000 m³/h
90 mbar
required 3,762 kW
SEPOL separator 5,550 mm cage diameter
2,900 mm roller diameter with bypass lubrication system for roller bearings
6,850 mm grinding table diameter with quick changeable dam ring arrangement
Required 4,830 kW
Roller mill RM 66/29-555 – THALOFA
Trang 9Schematic movement of material on the grinding table
Trang 10table outside inside
Material bed
Movement of grinding roller
Trang 11Feed Chute
Trang 12with chute optimised
Feed Chute
Trang 13Coarse Feed Valve Hot gas
Trang 14Coarse Feed Valve
Basic data
Maximum moisture content 8 %Construction size 2.000 x 2.000 Diameter of the housing (internal) 2.000 mmLength of the valve (internal) 2.000 mm Overall height with base frame 2.800 mmRotational speed of the vane rotor 5.1 min-1
Total weight 16.200 kg
Heating with hot air requires the following indications
Minimum velocity of the hot air in the valve vmin 18 m/s Minimum hot air volume at Vmin 28.800 m³/h
Nominal width of the supply pipe 800 mm Minimum temperature of the hot air at the valve 200 C Maximum permissible temperature of the hot air 350 C
Trang 15Coarse Feed Valve
Overload coupling
Type Syntex 50 TD1 Rotex GS48/50 Overload torque set when being
delivered 225 Nm
Trang 16Wear inside the housing
Wear on top of the sealing strips
Scraper jammed
Coarse Feed Valve
Trang 17Hot gas
Material
Heated feed chute Feed Chute
Trang 18Feed Chute
Material flow Feed chute
20°C
259°C max 350°C
261°C Hot gas
Trang 19Hot gas Material
Trang 20Feed Chute
Mill housing
Trang 21Mill doors Mill housing
Trang 22Mill doors
Rubber sealMill housing
Trang 23Mill housing
Trang 24Adjustable nozzle ring
Trang 25POSITIONS FOR THE NOZZLE RING
Trang 26Adjustable nozzle ring
Trang 27Adjustable nozzle ring
Hot gas chanel
Grinding table with grinding track
Nozzle ring
Cross-section with the highest
velocity
Adjustable nozzle
ring segment
Hot gas Adjustment
distance
Trang 28Feed Chute
Mill housing
Roller pairs
Trang 29Roller Pair
Trang 30Roller Pair
Trang 31Roller Pair
Basic data
Outside diameter of grinding rollers:
2.900 mm
Material of roller tyres:
wear resistant cast iron
Weight of one roller tyre: 16,2 t
Weight of one complete roller pair unit:
107,8 t Setting values for oil temperature:
Alarm 115 C Shutdown 125 C
Maximum wear, measured value „S2“
190 mm
Data for repair work
Dimension „Z“ for pre tensioning of the grinding roller bearings 0.1 mm
(Difference between the dimension „X” and the height of the intermediate ring, see 7.4 Repair)
Trang 33Roller Pair
Item No relating to the roller pair unit
2.3 Spring type straight pin 25 Roller tyre
9 Inner bearing cover
10 Air chamber cover
11 Radial shaft seal 12.1 Hose pipe for radial shaft seal
Trang 34Confining air system
PRoller Pair
Trang 35Confining air systemRoller Pair
Trang 36Confining air system
viewRoller Pair
Trang 37Confining airRoller Pair
Trang 38Confining air system
Roller Pair
Positive air pressure to avoid dust penetration
Trang 39Oil circulation system
Roller Pair
Trang 40Roller Pair
Oil circulation system
Filter contamination checked by Delta Pressure
Metal detector to separate particles
of the oil
Trang 41Roller Pair
Recording of the wear
on the roller tyres
Trang 42Roller Pair
Trang 43Maximum wear on roller tyres
To prevent breakage of the roller tyres, the specified maximum limit values
„S2” = 190 mm must not be exceeded (see Section Technical data).
Roller Pair
Trang 44Roller Pair
Recording of the wear on the roller tyres
Trang 45Roller Pair
Force application to the roller pair units
Force application to the roller pair is determined by the position of the hooks relative to the roller unit axis Experience has shown that shifting the hooks influences the wear pattern on the roller path For this reason, the roller pair units are equipped with adjustable hooks
A wear-measuring inspection of the grinding elements forms the basis for the decision in which
direction to shift the hooks A shift towards the outside (+Y) is necessary when the inner roller path shows more advanced wear A shift towards the centre of the grinding table ( Y) is necessary when the outer roller path shows more advanced wear
The roller pair units are delivered with the hook mounted in „zero position (A)”.
When turning around the roller pair units to spread the wear uniformly over the roller tyres, definitely make sure that the hooks are in the same position relative to the roller unit axis (both in magnitude and direction) as before turning
NOTE
The tie rods are always suspended from the outer hooks (20).
Trang 46Roller Pair
Force application to the roller pair units
• Roller Pairs are delivered with hooks in the zero position
• Wear inspection of the roller may indicate a need to reverse roller pair 180 degrees
position relative to the roller unit axis.
Permissible shifting of hooks
in +Y direction 100 mm
in Y direction 100 mm
Trang 47Roller Pair Turning roller pair units around
Remove the roller pair units, turn them around through 180°
outside of the roller mill and re-install them into the roller mill.
When the roller pair units have been turned around,
definitely make sure that the hooks are in the same
position relative to the roller unit axis (both in magnitude
and direction) as before turning.
After installation of the roller pair units, the oil probes must be
re-calibrated and checked for proper functioning.
Trang 48Roller Pair
Replacement of the roller tire
Lay the roller pair unit horizontally on its side Remove the nuts
from studs (26) and force off the clamping ring (27) by means of
the forcing screws The roller tire can now be lifted off If the
roller tire (25) has got stuck on the roller body (8) and cannot be
pulled off by means of customary fitting tools, the roller tire may
also be sprung off.
In this case proceed as follows:
Locally heat up the roller tire (25) by means of a welding
torch,
Then cool the heated areas with water (quenching).
Polysius personnel must be present at the first time.
25
Trang 49No Work to be performed Frequency Remarks
1 Check oil level in the oil reservoirs for weekly
lubrication of the radial shaft seals
2 Check oil level in the oil circulation weekly
Trang 50No Work to be performed Frequency Remarks
4 Take an oil sample of the grinding every 6 months check the oil for lubrication
roller lubrication system properties and soiling
5 Check the wear on the roller tyres (25) every 6 months during commissioning
Recording of the wear
6 Check the wear on the guide pins (21) every 3 months the permissible wear is
10 mm
Maintenance - Roller pair
Trang 51Servicing
No Work to be performed Frequency Remarks
1 Retighten the studs (26) with the every 6 months if the roller tyres are new,
specified tightening torque after 30 to 50,after 250,
Damaged studs have to be replaced after 500 operating hours
2 Retighten the following bolted connections every 6 months at the first start-up and
with the specified tightening torque as per subsequently to every
table in section Repair repair after 30 to 50
- of hook (20) operating hours
- of guide pin (21)
- of outer bearing cover (13)
- of bearing cover plate (14)
- of confining air connection (22) to the roller carrier
3 Turn around roller pair units as required latest all 2 years see Repair
Maintenance - Roller pair
Trang 52No Work to be performed Frequency Remarks
4 Shift hooks (20) as required see Repair
5 Replace roller tyres (25) as required see Repair
6 Replace guide pins (21)
or rehabilitate by build up welding as required
Maintenance - Roller pair
Trang 53Fault Cause Rectification
Maintenance - Roller pair
Trang 54Feed Chute
Mill housing
Roller pairs
Grinding table
Trang 55Grinding Table
Trang 56Technical Data:
• Outside Diameter 7.040 mm
• Height 2.500 mm
• Number of table liner segm 8
• Weight of table liners 53.800 kg
• Total weight of the Grinding table 214.800 kg
Grinding Table
Trang 576
7 7
8 8
10 10
11
1 Complete surface machined
2 Flatness of surface
3 Contact faces of clamping pieces machined
4 Dimensional check with template
5 Hollow spaces filled with insulation material
6 Sleeve centred
7 Sleeve material
8 Clamping piece secured against turning
9 Clamping piece reinforced
10 Expansion bolt with rolled thread
11 Expansion bolt with heat insulation
Grinding Table
Trang 58Grinding table insulation
Dam ring heightener
Clamping piece
Lug Wedge element
Table liner segment
Table liner fastening
Grinding Table
Trang 59Assembly of table liners
• Alignment of the table liner segments on the
grinding table
• Adjustment of equal gaps between segments
• At the inner radius, the table liner segments must be in contact with the limit stops
• The lugs must be in contact on the side which is opposite to the sense of rotation Gaps must be closed with packing plates
• The wedge elements must be ground until they have the right size depending on the toleranced casting dimensions
• The table liner fastenings must be tightened with the specified torque
• Assembly of grinding table insulation
Grinding Table
Trang 60Adjustable Table Seal Grinding Table
Trang 61Grinding Table Insulation
Grinding Table
Trang 62- Dam Ring
- Discharge Ring
Grinding Table
Trang 63Discharge Ring
Scraper elements
Wear plates
Grinding Table
Trang 64Discharge Ring
Scraper elements
Grinding Table
Trang 65Recording of wear on the grinding track
Checking and recording of wear on the
grinding track every 6 months
During the commissioning phase: every 3 months
Grinding Table
Trang 67• Dam ring adjustment acc
Trang 68No Work to be performed Frequency Remarks
1 Checking and recording of wear every 6 months During the
on the grinding track (2) commissioning phase:
every 3 months
Maintenance - Grinding table
Trang 69Servicing
No Work to be performed Frequency Remarks
1 Retighten the expansion bolts (8.1) every 6 months When the table liners
with the specified tightening torque Are new, after 30 - 50,
Damaged expansion bolts have to be after 250, after 500
2 Retighten the following bolted connections every6 months At the first start-up and
with the specified tightening torque acc subsequently to every
to the drawing specification repair after 30 to 50
- of table body (1) with gear unit operating hours
of dam ring heightener (4)
- of cover (5.1)
3 Check the seals in the joints between the every 6 months If necessary, stuff with
table liner segments, dam ring and grinding sealing cord and then
cord
Maintenance - Grinding table
Trang 70No Work to be performed Frequency Remarks
4 Adapt the dam ring heightener (4) to match as required
the wear progress of the grinding track
5 Replace worn out table liners (2) as required
Maintenance - Grinding table
Trang 72Tie Rods and Hydraulic
Trang 74Tie Rods and Hydraulic system
Description of functioning
The force required for grinding the feed material is generated by a hydraulic system.
Two hydraulic cylinders per roller pair ensure that the grinding force is evenly applied
to the rollers, while maintaining the maximum freedom of roller movement.
The hydraulic System permits infinite adjustment of the pressure in order to adapt
the grinding force to actual operating conditions.
When the mill is started up, the hydraulic pressure is lowered in order to reduce the
force applied to the grinding rollers This in turn reduces the starting torque.
Each hydraulic cylinder is connected to a piston accumulator which dampens the
shocks generated by the rollers running over the bed of material.
Trang 75No Work to be performed Frequency Remarks
1 Check of the hydraulic system for leakage 1 x per shift
2 Check of the filter (25) for dirt 1 x per shift
3 Check of the oil level in the reservoir (1) 1 x per shift
4 Check of the pumps (7.1 and 7.2) for 1 x per shift
abnormal running noises
5 Check of the gas pressure in the piston weekly Depressurise the
accumulators at the pressure gauges of the oil side of thenitrogen filling units (40.1 to 40.4) piston accumulators
Trang 76No Work to be performed Frequency Remarks
5 Oil sampling and check for ageing and every 26 weeks Max contamination
lubricity by the oil supplier acc to ISO 18/15,
NAS 1638 class 9
6 Functional check of the hydraulic system yearly
7 Maintenance work at the hydraulic According to
9 Recurring check of the piston accumulators in accordance Pressure vessel
by an expert according to the pressure with the national regulations § 10vessel regulations regulations or in accordance
with the nationalregulations
Maintenance - hydraulic tie rods
Trang 77Fault Cause Rectification
Maintenance - hydraulic tie rods
Trang 78Fault Cause Rectification
Maintenance - hydraulic tie rods
Trang 79Fault Cause Rectification
Maintenance - hydraulic tie rods
Trang 81Main Drive Unit
Trang 82Main Drive Unit
Trang 83Main Drive Unit
Location of
acceleration
sensors
Trang 841.0 Horizontal driving flange 1.1 Tilting pad thrust bearing
2.0 Coupling 3.0 Main motor 4.0 Overrunning clutch 5.0 Auxiliary gear unit 6.0 Auxiliary motor 7.0 Safeguard
8.0 Oil supply system 9.0 Vibration monitor 10.0 Gear unit bed plate
11.0 Base frame for the
main motor
Standard unit
Main Drive Unit
Trang 85Technical data Main gear unit
Power output 4.550 kW Output speed 21,16 rpm Input speed 995 rpm Weight 95,2 t Total oil quantity 4.000 l (max 8.000 l) Oil Viscosity CLP OIL ISO VG 320
Main Drive Unit
Trang 86Set points of the lubrication SystemLubrication oil pressure < 0,7 bar Mill stopOil temperature 60°C AlarmOil temperature 70°C Mill stop
Axial bearingsBearing temperature 70°C AlarmBearing temperature 75°C Mill stop
Lubrication high pressurePressure < 8,0 bar Alarm loaded conditionsPressure < 2,0 bar Alarm unloaded conditions
Filter contaminationDifferential pressure1,75 bar High pressure SystemDifferential pressure3,15 (4,5) bar Circulation System
Main Drive Unit
Trang 88Separator SEPOL
Trang 89Drive shaft Mill outlet gas duct Guide vane adjustment Guide vanes
Sepol housing Sepol rotor
Separator SEPOL
Trang 90upper bearing arrangement guide vane ring
housing guide vanes
rotor
Separator SEPOL
Trang 91Technical data
Type RMR 555
Diameter of the rotors 5.500 mm Direction of rotor rotation (top view) right Weight of the rotor 23.400 kg
Wear plates in the housing
Eye bolt
Size M 48 Bearing capacity 32.000 kg
Quantities of lubricants for initial filling
Upper bearing 4.500 g Lower bearing 3.000 g
Separating air
Flow rate 870.000 – 1.000.000 m3/h
Separator SEPOL