You may only use and print one copy of this document for private study Supply Chain Planning: Production Planning materials to the purchasing department.. The primary business issues ad
Trang 1Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Supply Chain Planning: Production Planning
materials to the purchasing department
The primary business issues addressed by production planning include:
• Ensuring machines and materials are available for production when needed
• Maximizing throughput and utilization of factory resources
Trang 2How is a Production Planning Integrated with Supply Chain Planning?
Production planning is one component of the supply chain planning process Supply chain
planning is an integrated process that allows companies to plan and integrate the supply chain functions of procurement, manufacturing, and fulfillment
Demand, supply, production, and fulfillment planning operate as interdependent supply chain planning functions The goal is to integrate these processes so that all the plans are synchronized with one another Plans generated during one process are used by one or more of the other processes In other words, planners need to know:
• What to do with the information generated
• How the different processes relate to one another
Specifically, a materials planner may wonder, "What if my suppliers can't deliver to our requested quantities and timing?" There are many ways to resolve this issue One viable option is to delay the production of some of the items until materials are available, and inform fulfillment planning about the delay in meeting customer requirements Another option may be to work with
Procurement to determine if the finished goods could be sourced from another vendor
Trang 3Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Objectives
After completing this module, you should be able to:
• Discuss the purpose, objectives, and benefits of production planning
• Describe the different components of production planning, the business problems it solves, and the key capabilities production planning offers
• Identify key inputs, constraints, and other considerations for the components of
production planning
• Describe the measurements and metrics for production planning
Trang 4Introduction to Production Planning
Overview
Once a company has developed demand and supply plans, it must plan how to manufacture the
product Production planning (sometimes referred to as factory planning) includes two
components:
• Production Schedule - Determine the resources required (labor and machines) and the
sequence (time frame) of the manufacturing operations In some cases, the production schedule specifies the start times for the different items; it is occasionally referred to as
the start plan
• Materials Plan - Identify the materials needed (raw materials or sub-components) to
meet manufacturing requirements, along with the time and factory floor location where the material will be needed This differs in the level of detail from the materials plan generated during supply planning
Trang 5Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Production Planning Constraints
Production planning is limited by capacity and materials constraints For example, a machine can produce a maximum number of items per hour, or is scheduled to run a set number of times per week This differs from supply planning in the level of detail An example of a supply planning
constraint is the daily production capacity of one line, while an example of a production planning constraint is the production capacity for one station on the entire manufacturing line The
production capacity may be stated as either the number of items processed per time unit, or the processing time required per item
Similarly, there could be materials constraints that affect production The materials plan
generated during supply planning considers only key components, while the materials plan generated during production planning considers all materials required for manufacturing the products
Trang 6Components of Production Planning
Production planning consists of the following two components:
Trang 7Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Production Planning in Different Industries
Planning emphasis on the different production planning components can vary by industry For example, capacity constraints are very important in the semiconductor industry, while materials planning is very important in the computer industry
Trang 8Production Planning in Different Industries - Semiconductor
The semiconductor industry is a capacity constrained industry In addition, very few
manufacturers produce product without orders from their customers A new factory can cost in excess of $2 billion In addition, while wafers are made of sand (a negligible material cost), it may take several weeks to manufacture a wafer Thus, manufacturers have limited capacity to satisfy customer orders, and demand often exceeds supply Some of the challenges of the
semiconductor industry are:
Maximizing product throughput
Since demand exceeds supply in this industry, maximizing product throughput becomes
extremely important Companies strive to develop "optimal" production schedules that maximize machine utilizations and product throughput Furthermore, because different products are
processed on the same resource (i.e., machine), the resource requires a certain amount of
"changeover" time (e.g., tool changes, cooling down) The amount of changeover time required depends on what product was just processed and which will be processed next As a result, the sequence in which products are processed on resources is also very important
Inaccurate due date promises
Manufacturers must ensure that they can provide accurate order promise dates to their
customers Unfortunately, most manufacturers provide promise dates for customer orders based
on predetermined lead-times that do not always reflect reality With accurate production planning information (when product will be manufactured), manufacturers can quote more accurate order due dates to customers
Industry Sector Production Planning High-Tech - Semiconductor • Maximize product throughput
o Minimize changeover and other "down" times
o Develop "optimal" production schedules
• Ability to quote due dates accurately
The semiconductor industry thus tends to focus on production scheduling
Trang 9Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Production Planning in Different Industries - Computer
In contrast to the semiconductor industry, the computer industry is not capacity constrained at all, i.e., there is sufficient capacity to meet all customer demand However, the profit margins for computer manufacturers are thin, and customers demand customized configurations Thus, ensuring that sufficient material is available (without incurring excessive inventory costs) is very important in this industry Challenges in the computer industry include:
High fluctuations in demand
Consumers want new and improved products As a result, demand often hits a peak very soon after a new product is introduced and declines rapidly after that If the company carries too much material, they could be left holding obsolete inventory
Increasing customer demand for customized products
Customers want to customize their computer products; this makes it difficult for
manufacturers to forecast demand for end products accurately At the same time, the manufacturer must be able to assemble a computer relatively quickly Hence, they must plan for material to be available when needed By creating production schedules quickly and for short time horizons, manufacturers can communicate with their materials suppliers
to provide material just in time for production
Industry
Sector
Production Planning
Computer • Ability to plan for customized configurations
• Ability to create production schedules quickly
• Ability to create materials plan for a short time horizon and communicate with
suppliers
The computer industry thus tends to focus on materials planning
Trang 10Production Planning in Different Industries - Automotive
The automotive industry is an example in which production scheduling and materials planning are both very important Each car requires several thousand parts; therefore, material coordination is extremely important At the same time, manufacturers must ensure that assembly lines are balanced and assembly stations are not over or under-utilized (idle) Some challenges of the automotive industry are:
Production Flexibility
Every car traveling down an assembly line is different from the preceding or succeeding car Despite this, the assembly line must remain in balance to ensure minimal disruptions to
production
High Number of Parts
Despite the fact that automotive makers use an extremely high number of parts—a typical car manufacturer uses approximately 1.5 million parts every day—they must ensure that the right parts with the right quality are available at the right place, at the right time
Maintaining Inventory
Due to the large number of parts, manufacturers cannot afford to keep a high inventory of each part They must therefore minimize their inventory for parts and ensure availability
Collaboration with Suppliers
To maintain a low inventory of parts, manufacturers must communicate effectively, i.e.,
collaborate, with their suppliers Manufacturers receive parts just in time for production To ensurethis, they must share their production schedules with their suppliers The best manufacturers provide their suppliers a daily (and sometimes hourly) delivery schedule four to 10 days ahead of delivery
Industry Sector Production Planning
• Coordinate material availability
o Provide a four - 10 day rolling delivery schedule to suppliers
• Maintain low inventory
o Provide a four - 10 day rolling delivery schedule to suppliers
Both production scheduling and materials planning are thus critical in the automotive industry
Trang 11Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Topic Summary
What is it?
• Determine how to manufacture the product (i.e.,
what resources will be used, what materials are
required, and in what sequence (and time) the
manufacturing operations will be performed)
Determine what materials will be required to meet
the manufacturing requirements
Key output
• Production schedule
• Detailed materials plan
Sample business problems addressed
• Ensure that machines/materials are available for
production when needed
• Maximize resource utilization
Key capabilities
• Scheduling and sequencing production activities
• Defining material requirements
• Communicating purchase order recommendations to purchasing
• Managing exceptions
Trang 13Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Introduction to Production Scheduling
The master production schedule (MPS) created during supply planning defines what must be
produced in the factory to meet customer demand The MPS now needs to be converted into a
production schedule that is used to drive manufacturing on the factory floor The production
schedule will determine the resources required and the sequence in which operations will be performed on each resource to manufacture the product The production scheduling process strives to respect the capacity constraints of each resource and reflect cycle times This is
inherently a very complex process because planners generate the schedule while considering dozens of business rules and constraints
In many cases, a company will have many different products to manufacture and could do so in a variety of ways For effective production scheduling, a company must implement key capabilities, including the ability to:
Schedule production activities
Convert the MPS into a production schedule that specifies the sequence in which the product is processed on multiple resources, as well as the processing times (or starting and stopping times
of each operation) for each operation This also includes matching work in process (WIP) and manufacturing orders (supply/demand match)
Consider different constraints
Two types of constraints are generally considered during production scheduling—capacity
constraints and materials constraints The production schedule generated must ensure that sufficient capacity is available on each resource, and that the materials are available when required
Evaluate multiple scenarios
Certain orders must be processed, or expedited, through the factory quickly This may affect the completion date of other orders The company must be capable of understanding the impact of expediting one or more orders on other orders, as well as evaluating multiple production
schedules and their impact on customer order completion dates
Production schedulers use the production schedule to drive production through the factory shop floor They will usually receive a report that specifies the sequence and start times for each item
to be manufactured during a given day or shift They may also use specialized software to
evaluate multiple scenarios before making a final decision on the production schedule for the day
Trang 14Production Scheduling Stakeholders and Business Issues
We have established the outputs from and the capabilities required for production scheduling During production scheduling, companies strive to:
Maximize throughput
The MPS process during supply planning considers high-level capacity constraints and creates a daily schedule for production scheduling to follow The goal of the production scheduling process
is to ensure that manufacturers can produce maximum product using available resources
Maximize resource utilization
Since factory resources are very expensive and require large capital expenditures, a company must ensure that they utilize such resources effectively to obtain a high return on investment Idle resources are resources not fully utilized; in other words, the factory may not be operating to its optimal capacity
Minimize changeover times and costs
Many resources can be used for manufacturing multiple products In many instances, when a resource is switched from manufacturing one type of product to another, there is some
changeover time and cost Generally, machines are not usable during changeover periods, leading to lost capacity One of the goals during production scheduling is to minimize such changeover times and costs
Minimize lateness
Orders scheduled in the factory have a due date, i.e., a date prior to which they must be
completed In many cases, sufficient capacity and/or materials are not available to meet all due dates During the detailed scheduling process, manufacturers strive to minimize late orders
Minimize earliness
Orders scheduled in the factory have a due date, i.e., a date prior to which they must be
completed In many cases, sufficient capacity and/or materials are not available to meet all due dates on the exact date specified, and items may be manufactured ahead of that date Early completion means incurring undesirable inventory-carrying costs During the detailed scheduling process, manufacturers strive to minimize early orders
Manufacturing uses the output from the production scheduling process to ensure that machines, labor, and materials are available when required Fulfillment may use the production schedule as
an input to determine when transportation is needed to move the product from the factory to the distribution centers and/or customers Customer service may use the production plan to
determine whether orders will be met on time or late
Production scheduling is typically performed for one to seven days, and updated daily Some advanced companies update their schedules more frequently, e.g., a high-volume discrete manufacturer has a four-hour scheduling horizon
Trang 15Key Inputs, Outputs, and Considerations
A key concept related to production scheduling is the concept of production scheduling
algorithms, including:
• Shortest process time
• Earliest due date
• Minimum total manufacturing time
Additional considerations include:
• Business objectives
• Customer prioritization
• Supply prioritization
• Alternate production routes
The figure illustrates the key inputs and outputs for production scheduling
Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Trang 16Key Outputs - Production Schedule
The production schedule specifies what items are started on which resources at what times The schedule considers capacity constraints and manufacturing cycle times while trying to ensure maximum utilization of resources and maximum throughput of product
Example
Consider the example of a cookie manufacturer that bakes two types of cookies—chocolate chip (CC) and peanut butter (PB)
• The CC cookies are baked at 275 degrees F for one hour, and the PB cookies are baked
at 350 degrees F for one hour
• The company only has one oven in which to bake these cookies
• If the oven is already set at 275 degrees, it requires another 15 minutes for it to heat up
to 350 degrees, whereas if it has been set at 350 degrees, it takes 45 minutes for it to cool down to 275 degrees (both of these times are analogous to changeover times)
• Due to the capacity constraints of the oven, the company can bake a maximum of 15 CC cookies or 10 PB cookies at one time
• The baker (and hence the oven) works from 7 a.m to 3:30 p.m
• According to the Cookie Delivery Schedule, the company needs to produce 30 CC
cookies and 50 PB cookies
Quantity Due Time
The following information is required to create a solution:
• Identify the factory resources required - an oven is the only resource that is required
• Understand the manufacturing process/routes - in this case, the process and the
route is very simple Put the cookies in the oven at the appropriate temperature and bake for the required time period
• Define the raw materials required to make the cookies - the dough for each type of
cookie is premixed
• Identify the constraints - the constraint for baking cookies is that only one oven is
available from 7 a.m to 3:30 p.m., and the set-up time to change the temperature from
275 degrees to 350 degrees is 15 minutes, while the set-up time to change the
temperature from 350 degrees to 275 degrees is 45 minutes The company can bake a maximum of 15 CC cookies or 10 PB cookies at one time
• Determine when the items are demanded - the schedule of demand for the cookies is
identified in the problem description
Trang 17Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Key Outputs - Production Schedule - continued
There are many ways to go about determining a feasible production schedule One approach is trial and error—try a sequence of activities and determine if the resulting sequence satisfies all the constraints If it does, you have a solution If it does not, you then must modify some aspect of the sequence, and try again until you reach a feasible solution
Determine which of the following sequences provides a feasible production schedule Be sure to
consider the Cookie Delivery Schedule and Capacity Constraints Click the button below to
review the schedule and constraints
2 Heat Oven to 350 degrees
3 Bake 10 Peanut Butter Cookies
4 Bake 10 Peanut Butter Cookies
5 Cool Oven to 275 degrees
6 Bake 15 Chocolate Chip Cookies
7 Heat Oven to 350 degrees
8 Bake 10 Peanut Butter Cookies
9 Bake 10 Peanut Butter Cookies
10 Bake 10 Peanut Butter Cookies
1 Bake 10 Peanut Butter Cookies
2 Cool Oven to 275 degrees
3 Bake 15 Chocolate Chip Cookies
4 Bake 15 Chocolate Chip Cookies
5 Heat Oven to 350 degrees
6 Bake 10 Peanut Butter Cookies
7 Bake 10 Peanut Butter Cookies
8 Bake 10 Peanut Butter Cookies
9 Bake 10 Peanut Butter Cookies
Schedule and Constraints
Cookie Delivery Schedule
Quantity Due Time
is 45 minutes The company can bake a maximum of 15
CC cookies or 10 PB cookies at one time
Production Schedule Solution
Trang 18In most cases, a product would have to go through multiple resources before it is completely
manufactured To simplify this example, we considered only one resource
Trang 19Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Key Concepts - Production Scheduling Algorithms
Generating a production schedule is extremely difficult, especially in cases where the goods must
be processed on multiple machines and can have multiple routes through the manufacturing facility Commonly used methods for solving such scheduling problems include:
Shortest Process Time
On a given machine, complete the job that has the shortest process time first, and the job with the longest process time last This ensures that short jobs move through the manufacturing facility more quickly than long jobs This tends to reduce congestion
Earliest Due Date
Order jobs according to their due dates, with the earliest due date first and the latest due date last This minimizes the maximum lateness of any one job This approach will also allow the manufacturer to finish all jobs on time if it is possible to do so
Minimum Total Manufacturing Time
Minimize the time to complete n jobs through m machines in a manufacturing facility While this is
a well-known and well-researched problem by practitioners and researchers, obtaining an optimal solution for this is extremely difficult One possible heuristic approach is used to schedule jobs using their latest possible start times (LPST) for each machine, which allows manufacturers to take into consideration the due dates for the jobs and the manufacturing lead-times To
accomplish this, planners use a job and its due date, then subtract the manufacturing lead-time for the last operation (in its manufacturing sequence) to determine its LPST for the last operation They continue this process backwards until they determine the start time for the first operation
Trang 20Inputs for Production Scheduling
There are several inputs required for production scheduling The most common and important inputs are classified into three types—demand inputs, supply inputs, and static inputs (inputs that seldom change)
Demand Inputs
Customer Orders
Orders placed by customers and given top priority for scheduling to ensure that due
dates are met
Manufacturing Orders
Generated during distribution planning and master production scheduling, and used as
the key input for developing the production schedule
Stock Orders
Requests to increase inventory (demand) at certain locations Stock orders are not
customer specific, but placed according to inventory location (e.g., distribution centers)
and are not tied to any specific customers
Inventory of materials that has been shipped and is en route to the appropriate location;
this information is used to determine the net material requirements
Work in Process (WIP)
Work that has already started and is partially completed The WIP may be used during
the calculation of net material requirements
Static Inputs
Run Rates
The rate at which resources manufacture goods, e.g., a machine may be capable of
manufacturing 30 units of Product A per hour, or 20 units of Product B per hour Its run
rate would then be 30 units per hour for Product A, and 20 units per hour for Product B
Cycle Times
The time it takes to manufacture an item
Set-up Times
Some resources may require an initial set-up time before they can become operational
for production Set-up time is usually defined in units of time, e.g., 30 minutes or two
hours
Transfer Times
The amount of time required to move product from one factory resource to another As
Trang 21Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
The number of items that can be simultaneously processed on a resource There are
numerous resources that can produce many units of a product at the same time A
conventional oven able to bake several cookies simultaneously is one such example
(e.g., 15 chocolate chip cookies or 10 peanut butter cookies per oven batch)
Trang 22Additional Considerations
In developing production schedules, companies may account for additional considerations, such as:
• Business Objectives - In addition to maximizing product throughput and resource
utilization, a company may consider additional business objectives at this time, e.g., minimizing the cost of production, or minimizing the cost of goods sold
• Customer Prioritization - Some customers are more important than others, and
companies go to great lengths to satisfy this customer base (e.g., meeting delivery dates) Companies develop production schedules that accomplish this even if it means slippage
in delivery dates to some other customers
• Supply Prioritization - A company may have multiple sources of supply for certain raw
materials, or sub-assemblies and components, and they will typically specify the primary source and a secondary source of supply for each of these items They will use
secondary sources only if the primary source is unable to meet requirements
• Alternate Production Routes - In many instances, a product can follow more than one
manufacturing route through a factory In such cases, the company may be able to
specify a primary route and one or more alternate routes The alternate routes may be used in cases of insufficient capacity and/or materials
Trang 23Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Organizational Implications
Currently, many organizations create production schedules manually, e.g., by using spreadsheets, pegboards, and/or whiteboards Consequently, they cannot consider all the possible inputs and constraints To use and benefit from the production scheduling process, companies must
implement scheduling software that, in turn, leads to fundamental changes in the process,
including:
• Centralized Decisions - Often there is a central schedule coordinator who works with
schedulers from each manufacturing line or factory to coordinate all production schedules and ensure that the business objectives of the organization are met
• Team-based Decisions - Decisions made by the schedulers are team-based, preventing
individual schedulers from making isolated decisions
• Coordinated Decision Support - The schedule coordinator, who provides coordinated
decision support to all schedulers, now coordinates any changes and decisions that must
be made in the production schedules
Trang 24Organizational Implications - continued
Such changes to the production scheduling process also lead to several organizational changes within the company:
• Decreased Number of Schedulers - The use of advanced software usually leads to a
decrease in the number of schedulers required to create production schedules In many cases, it may even lead to centralized scheduling in which schedules for multiple plants are handled by one scheduler With increased responsibility for the centralized scheduler, other associates and planners may interpret it as an increase in power
• Different Performance Metrics - Measurement of individual performance will likely
change For example, while in the past a scheduler may have been measured on
resource utilization, they may now be measured on the ability to achieve the goals set forth in the production schedule
• Different Skill Requirements - Skill requirements for the scheduler change, e.g., ability
to manage multiple schedules simultaneously, increased analytical capability, and the ability to manage more complexity This may lead to retraining or even a new job grade
Trang 25A Production Scheduling Example
We will now consider a complex example by taking into account work in progress (WIP) and alternate routes
Example
A company manufactures two products—Product A and Product B It has three machines—Machine 1, Machine 2, and Machine 3
• Product B has only one route—process on Machine 3 for 30 minutes and then on
Machine 2 for 30 minutes
• Product A has two routes; the primary route is to process on Machine 1 for two hours, and then on Machine 2 for 90 minutes; the alternate route is to process on machine 3 for three hours, and then on Machine 2 for one hour
• We will assume that there are no materials constraints, set-up times, or changeover times
• The figure shows the routes
The factory is required to complete five units of Product B today, and four units of Product A today The only available WIP today is one unit of Product B that has completed processing on Machine 3 The machines are available during the hours of 8 a.m and 4 p.m The company's goals are to maximize resource utilization and product throughput
Solution Approach
The following information is required to create a production schedule
• Determine the materials required - The problem states that there are no materials
constraints, but in this case there is one WIP unit of Product B
• Identify the resources required - Machines 1, 2, and 3
• Understand the manufacturing process/routes - In this case, there is a different route
for each product; there is also an alternate route for Product A
• Identify the constraints - The constraints for the machines are the times they are
available (8 a.m to 4 p.m.)
Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Trang 26• Determine when the items are demanded - The schedule of demand for the products is
to complete five units of Product B today, and four units of Product A today
Trang 27A Production Scheduling Example - continued
There are many ways to go about solving this problem Select the Sample Solution button to
reveal one feasible solution
Sample Solution
A sample production schedule for each machine and product is shown in the tables (note that we have used A1, A2, etc., to differentiate between each unit of the product)
Select the Sample Solution Considerations button to reveal how this solution addresses capacity
and materials constraints and achieves production scheduling objectives
Sample Solution Considerations
Although the problem appears to be relatively simple, the solution procedure is very complex; it may take several minutes, or sometimes hours, for specialized software to generate a good
solution for the typical company that has several products and resources For this example, note the following:
• Only four units of Product B are manufactured on Machine 3 because one unit was
already a WIP and was netted out to determine the net requirements for the day
• Schedulers consider cycle time for each machine and unit in developing the schedule
• The capacity constraints are satisfied for each resource
• One unit of Product A is manufactured on the alternate route because not enough
capacity is available on the primary route
Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Trang 28• The goal of maximizing factory utilization is met because all the resources are fully utilized and are not idle at any time
• The goal of maximizing product throughput is met because after completing the required number of units for Product A, some additional units of Product A are manufactured, and they will serve as WIP for the subsequent days
Trang 29Copyright (c) 2004 Accenture All rights reserved You may only use and print one copy of this document for private study
Topic Summary
What is it?
• How to manufacture the product (i.e., what
resources will be used, and in what sequence (and time)
the manufacturing operations will be performed)
Key output
• Detailed production schedule
Business problems addressed
• Maximize throughput
• Maximize resource utilization
• Minimize changeover times and costs
• Minimize lateness
Key capabilities
• Schedule production activities
• Ability to consider different constraints
• Evaluate multiple scenarios