Private Benefit-Cost AnalysisDeriving ‘Project’ and ‘Private’ cash flows: • Project cash flow refers to cash flow for the overall project • At market prices • Irrespective of who gains o
Trang 1© Harry Campbell & Richard Brown
School of Economics The University of Queensland
BENEFIT-COST ANALYSIS
Financial and Economic
Appraisal using Spreadsheets
Ch 4: Project and Private Benefit-Cost Analysis
Trang 2Private Benefit-Cost Analysis
Deriving ‘Project’ and ‘Private’ cash flows:
• Project cash flow refers to cash flow for the overall project
• At market prices
• Irrespective of who gains or loses
Trang 3Private Cash Flow
• at market prices
Private cash flow refers to cash flow to the individual investor
engaged in project
• after allowing for loan service costs
• after payment of profits taxes
Trang 4Deriving Private Cash Flow
To derive private cash flow, we begin by calculating overall project cash flow
• Debt/financing inflows and outflows to creditors
• Taxes paid to government
We then subtract from the project cash flow:
Trang 5Cash Flow on Equity
• The private cash flow is the cash flow on the investor’s own funds or ‘equity’
• Project cash flow minus debt cash flow = cash flow on equity (before tax).
• Cash flow on equity is the residual: what is left over after servicing debt
Trang 6Deriving Project Cash Flow
To derive project cash flow we need to be mindful of some important concepts and conventions:
• Inflation: usual to use constant prices with a real
discount rate (otherwise, nominal prices with nominal interest rate) See table 4.1
• Incremental rather than total cash flow: ‘with project’
less ‘without project’ cash flow See table 4.2.
Trang 9Deriving Project Cash Flow
• Interest on debt excluded from cost to avoid double
counting
• Depreciation excluded from cost to avoid double counting (See table 4.3)
• Changes in working capital appear under investment costs
at the beginning and end of the project (See table 4.4)
Trang 11Debt Financing Cash Flow
To derive debt financing flow, for each period, from theborrower’s perspective, begin with project cash flow, then:
• Add all loan receipts in each period
• Subtract all interest payments in each period
• Subtract all principal repayments in each period
Trang 12Private Cash Flow (Equity)
To derive private cash flow, for each period, before tax:
• Add debt financing flow to project cash flow
(See table 4.5)
Trang 14Project = Debt + Equity
Cash flow from the perspective of lenders and investors adds
up to Project Cash Flow (See table 4.6)
Trang 15Deriving IRR on Equity
We can calculate IRR on each ‘component’ of cash flow: project, debt and equity
• First, calculate IRR on Project Cash Flow:
when NPV = 0-5000 (1.0) + 1000(AF10) = 0
AF10 = 5000/1000
= 5IRR = 15%
Trang 16Deriving IRR on Equity
• Second, calculate IRR on Debt Financing Cash Flow:
when NPV = 03512(1.0) - 500(AF10) = 0
AF10 = 3512/500
= 7.024IRR = 7%
Trang 17Deriving IRR on Equity
• Third, calculate IRR on Equity Cash Flow:
when NPV = 0
-1488(1.0) + 500(AF10) = 0
AF10 = 1488/500
= 2.976IRR = 31%
Trang 18Gearing and Debt: Equity Ratio
• IRR on Equity + IRR on Debt = Project IRR
• Project IRR minus IRR on Debt = IRR on Equity
– By changing the ratio of debt to equity, you can change the IRR on equity, given the Project IRR and IRR on debt
Trang 19An Example of Gearing
• Assume debt:equity is $60:$40
• Assume Project IRR = 10%,
and, cost of debt = 5%
– What is the IRR on equity?
HINT: IRR on Debt + IRR on Equity = Project IRR
Trang 20An Example of Gearing
IRR on project = 0.6(IRR on debt)
+ 0.4(IRR on equity)10% = 0.6(5%) + 0.4(x%)
0.4(x%) = 10% - 3%
IRR on equity = x% = 7/0.4
= 17.5%
Trang 23Calculating After Tax Cash Flow
• Some items of project cost that do not enter into a project's
cash flow directly affect the net cash flow indirectly through their effect on the project's taxable profits.
• The analyst needs to prepare a separate statement to calculate
the project's taxable profits.
• The two items that are not part of the project’s cash flow that
enter into the calculation taxable profits are:
– depreciation– interest on debt
Trang 24Calculating After Tax Cash Flow
• These should be added to the operating costs in the project cash flow for the purpose of calculating taxable profits
• Taxes due are then calculated as some % of taxable profits and are deducted from the private cash flow to derive the
after tax private cash flow.
Trang 25Calculating Taxes
It should be noted that tax laws vary from one country or state to another In most cases, losses can be written off profits earned elsewhere or of future profits
• This implies that there could be negative taxes in some
project years
Trang 26To Summarise
equals private cash flow
(on equity after tax)
Project cash flow
minus debt finance
minus taxes
Trang 27Using Private BCA
• Why would the project analyst who is concerned with the wider public or social interest be concerned with the return
on private equity?
– When the private investor is one of the stakeholder’s
whose gains are part of the ‘Referent Group’ net benefits
– Because the policy maker needs to know what is ‘in it’ for the investor: need incentives or tax concessions? etc
Trang 28Distribution of Net Benefits
• The project net benefits (at market prices) can be disaggregated among three stakeholder groups:
– equity holders (private or public sector) – lenders
– recipients of taxes (government)
Trang 3050%
20%
Lenders (Debt ) Invest ors (Equit y) Government (Taxes)
Shares of Project’s Net Benefits
(hypothetical)
Trang 31Distribution of Net Benefits
• At a later stage we will be looking at the distribution of all project net benefits among stakeholders, including those not included in the project’s net benefits at market prices
• At this stage it is still useful to distinguish between
Referent Group and Non-Referent Group Net Benefits
Trang 32Distribution of Project Benefits
B (non-referent group net benefits)
A (referent
Trang 33NFG Case Study: Project & Private